Item 7C
Zoning Change and Site PlanCambria Hotel and Suites atKimball Park
ZA15-032
1
Owner/
Applicant: Fillmore Hospitality
Request: Approval of a Zoning Change and Site Plan from S-P-2 Generalized Site Plan District to S-P-2 Generalized Site Plan District for the Cambria
Hotel and Suites at Kimball Park to revise the previously approved Zoning and Site Plan primarily with regard to the exterior elevations, building footprint and the layout of the ground
floor and pool area.
Location: 400 and 470 N. Kimball Ave.
ZA15-032
The applicant it requesting approval of a Zoning Change and Site Plan from S-P-2 Generalized Site Plan District to S-P-2 Generalized Site Plan District for the Cambria Hotel and Suites
at Kimball Park to revise the previously approved Zoning and Site Plan primarily with regard to the exterior elevations, building footprint and the layout of the ground floor and pool
area. Some minor changes to the parking lot landscape islands are also proposed.
A Site Plan for the Cambria Hotel and Suites was approved March 4, 2014 in conjunction with a Zoning
Change and Concept Plan for the Kimball Park development, which includes the four-story, 175 room Cambria Hotel and Suites, a three-story, 96,000 square foot office building, restaurant,
coffee shop and retail uses, and one open space lot on approximately 15.5 acres. No changes are proposed to the remainder of the Kimball Park development. The only changes proposed are
to Lot 1 of the development, which is the hotel site.
2
The future land use designation is mixed-use
3
The current zoning is S-P-2 Generalized Site Plan District.
4
Aerial View
The site is shown here at the northwest corner of E. State Hwy 114 and North Kimball Avenue on the former Mesco property.
5
Proposed Overall Exhibit
6
Proposed Changes
The footprint of the hotel is 111,897 square feet instead of 118,315 square feet.
The windows are reconfigured with louvers added for VTAC units.
The entry tower feature is squared off
with the east and south facades instead of being angled.
An accent band of brick and metal above the first floor has been removed.
The canopy at the hotel entrance is a clear polycarbonate
clad canopy instead of a metal clad canopy (support columns).
The height of the hotel lobby is a single height instead of a double height.
The height of the primary parapet is 51’-0”
instead of 47’-5” and the height to the top of the tower structure is 59’-4” instead of 59’-3”.
The layout of the ground floor and pool area have been reconfigured (detail chart on
next slide).
Required parking for the hotel is 211 spaces instead of 206 spaces due to the increase in meeting space.
Some of the parking lot landscaping on the west side of the hotel
has been revised and the dumpster enclosure has been squared off with the property line.
7
Ground Floor Area by Use
8
Hotel Entrance
Approved
Proposed
The windows are reconfigured with louvers added for VTAC units.
The entry tower feature is squared off with the east and south facades instead of being angled.
An accent band of brick
and metal above the first floor has been removed.
The canopy at the hotel entrance is a clear polycarbonate clad canopy instead of a metal clad canopy.
The height of the hotel lobby
is a single height instead of a double height.
The height of the primary parapet is 51’-0” instead of 47’-5” and the height to the top of the tower structure is 59’-4” instead of 59’-3”.
9
Hotel Entrance
Approved
Proposed
10
Conference Center Entrance
Approved
Proposed
11
Approved Overall Site Plan
10,000 sq. ft. Restaurant
4,500 sq. ft. Coffee Shop/Restaurant
9,222 sq. ft. Retail/Restaurant/Health and Well-Being
96,000 sq. ft. Office
175 Room Cambria Suites Hotel
This is the revised concept or master plan for the site (Sent to you by email last evening and provided at your place). City Council will be asked to approve a site plan for lot 1 for
the hotel site and for lot 6 the open space lot. The remainder of the site is only a concept plan approval. – meaning any regulations, renderings, or requirements will be evaluated
against future site plan applications, Review the lots.
Lot 1 – The hotel is 4 stories and 118,315 sq ft. The footprint is 31, 390 (118,318 sq ft total) and is 47.5 feet tall to
the top of the primary paphet and 59’3” to the top of the tower structure. Hotel is programed to have 175 guest rooms (average room size is 405 sf) range from 355 -596 sq ft.; 8,380
sq ft conference center, and a 1,995 sf fitness center. 211 parking spaces provided.
Lot 2 – Out parcel for a 10,000 sq ft restaurant,a 15 x 25 sign easement will run with the property.
63 parking spaces.
Lot 3 – The concept plan proposes a three story office development with a 32,000 sq ft footprint for a total of 96,000 sq ft. The regulations for this building
have been changed to allow for up to four above grade floors with the ground floor used for parking. Also the regs allow for a parking deck. These changes allow parking ratios to meet
4/1000 sq ft. (326 parking spaces).
Lot 4 shows a 4,500 sq ft coffee shop and restaurant with a drive through. Any restaurant use will exclude fast food. 52 parking spaces.
Lot 5
– 9,222 sq foot restaurant, retail and Health and Well –being building 54 Parking spaces.
12
Site Plan Revisions (Lot 1)
Proposed
Approved
13
Ground Floor Revisions
Approved
Proposed
14
Patio/Pool Revisions
Approved
Proposed
15
East Elevation
Approved
Proposed
16
South Elevation
Approved
Proposed
17
West Elevation
Approved
Proposed
18
North Elevation
Approved
Proposed
19
P & Z Action
April 23, 2015; Approved (5-0) subject to Site Plan Review Summary No. 1, dated April 16, 2015, subject to the staff report dated April 17, 2015, approving each of the proposed changes
as presented; noting for the record the applicant’s willingness to get with Commissioner Springer to explore alternate options to the louver window issue and cooling towers; also noting
the applicant’s willingness prior to coming to Council to prepare a rendering of the entryway so they can see the difference between the approved two story height versus the twelve foot
height that is being proposed and also noting the applicant’s willingness to try to match the proposed entry feature at the front of the hotel with the entry at the conference center
entrance.
20
Applicant’s Responses to P & Z Action
21
Conference Center Entrance
Approved
Proposed
22
Revised Canopies per P&Z Motion
Conference Center Canopies
23
Revised Pool Area Canopy
24
Proposed Front Canopies
25
Questions?
26
Approved Concept Plan
Richard to update
27
Hotel Site Plan - Lot 1
28
Updated landscape Plan
29
Permitted Uses
Lot 1: “HC” Hotel District to also include
Restaurant and Bar, which are accessed from interior lobby
Conference Center totaling 8,380 sq. ft. of meeting and support space
Lots 2, 4
& 5: “C-2” Local Retail Commercial District Uses limited to:
Restaurant (Bar is a permitted Accessory Use) (No fast food restaurants)
Coffee shop with drive-through service –Lot 4 only
Retail
Health and Well Being Businesses, Spa
Lot 3: “O-2” Office District Uses to include:
3-story office building with approximately 96,000 sq. ft.
Lot 6: Open Space lot with natural
vegetation, existing creek channel, new plantings and existing creek channel, new plantings and detention area
30
S-P-2 Regulations
Parking is allowed as shown on the Concept and Site Plans
Bufferyards are not required along internal lot lines
Deliveries are limited to 7:00 a.m. to 7:00 p.m.
Trash pick-up is limited
to 7:00 a.m. to 7:00 p.m. Mon –Sat
Property line adjacent to MF properties will have minimum 8’ vegetative screen
Loading zones are provided as shown on the concept and site plans
Building
lines are as shown on the concept and site plans
Overall impervious coverage for the site as a whole shall be a maximum of 70%
709 Parking spaces are proposed
31
S-P-2 Regulations for Lot 1
Cambria Suites Hotel with an “Upscale” rating according to Smith Travel Research
Indoor Services to Include:
Restaurant with lounge (approx. 1,900 sq. ft.)
Bar with on-site alcohol
consumption
175 guest suites
8,380 sq. ft. Conference Center with 5,100 sq. ft. of total meeting space and 4,320 sq. ft. of contiguous space for a ballroom with a capacity of 264 people
Administrativ
e office space
Overall impervious coverage for the site as a whole shall be a maximum of 70%
Articulation will be as shown on the elevations and site plan
32
S-P-2 Regulations for Lot 1
Outdoor Services to Include:
Patio containing leisure area with pool
Patio containing fireplace and dining
Roll-out bar service
Patio for conference spill out
Administrative office
space
33
S-P-2 Regulations for Lot 1
Hours of operation:
Food Service/Restaurant open 6:00 a.m. to no later than 11:00 p.m. 7 days a week
Bar Service open 10 a.m. to no later than 2:00 a.m. Mon. – Sat. and Sunday 11:00
a.m. to no later than 2:00 a.m.
Live music to end no later than 12:00 a.m. 7 days a week
Outdoor speakers will be shut off no later than 12:00 a.m. and any outdoor music will be discontinued
no later than 12:00 a.m. 7 days a week
34
S-P-2 Regulations for Lots 2-6
Lot 2: (C-2 zoning)
± 10,000 sq. ft. restaurant
Lot 3: (O-2 zoning)
± 96,000 sq. ft., 3-story office building
Lot 4: (C-2 zoning)
± 4,500 sq. ft. coffee shop/restaurant with drive-through
(no fast food restaurants)
Lot 5: (C-2 zoning)
± 9,222 sq. ft. retail/restaurant building with health and well-being uses permitted
(including spa, massage therapy, fitness and health
related products)
35
Proposed Cambria Suites at January 9th P&Z
This is a rendering of the hotel presented to the PZ Commission on January 9th
36
Proposed Kimball Park at February 6th P&Z
The PZ asked for a concept plan for the items -
37
Proposed Hotel
PZ - This is the rendering submitted for this meeting but the applicant will have a revised elevation.
38
Proposed Hotel
Façade materials to be revised to match elevations
Fountain to be added here
PZ
39
Landscape Plan – Lot 1
40
Pool Area
41
Parking Analysis
42
Breakdown of Hotel Floor Area
43
Tree Conservation Plan
44
Pedestrian Access Plan
45
Phase 1 Construction Plan
46
Variances Requested
1) The driveways do not meet the minimum required stacking depth of 150’. Approximately 17.6’ of stacking depth is shown on the N. Kimball Ave. driveway and 34.2’ of stacking depth is
shown on the S.H. 114 driveway.
2) Subdivision Ordinance No. 483, Section 8.01(A), as amended, requires that every lot front on a public or a private street. A variance is requested
to allow the lots to be configured as shown on the Concept Plan.
47
P&Z Action
ZA13-135 Zoning Change and Concept/Site Plan:
February 6, 2014; Approved (5-0) subject to Revised Concept/Site Plan Review Summary No. 2 and Staff Report dated January 31, 2014, approving
the two variances requested and noting the applicants willingness to address the following: 1) the entrance to the hotel on the southeast corner of the hotel, 2) the parking and landscaping
on the east side of the hotel 3) the design and layout of the retail/restaurant component around the circle with the potential for patio space on the southern side of the building as
well as the northern side, 4) clarify renderings of the hotel 5) refine the renderings to more closely resemble the materials anticipated being used, 6) place the fountain in the renderings
and 7) add pedestrian access from the hotel to the green space on the southeast portion of the lot.
48
P&Z Action
ZA13-136 Preliminary Plat:
February 6, 2014; Approved (5-0) subject to Plat Review Summary No. 2 dated January 3, 2014 and Staff Report dated January 31, 2014 with variances requested:
1) The driveways do not meet the minimum required stacking depth of 150’. Approximately 17.6’ of stacking depth is shown on the N. Kimball Ave. driveway and 34.2’ of stacking depth is
shown on the S.H. 114 driveway and 2) Subdivision Ordinance No. 483, Section 8.01(A), as amended, requires that every lot front on a public or a private street. A variance is requested
to allow the lots to be configured as shown on the Concept Plan.
49
Council Action
ZA13-135 Zoning Change and Concept/Site Plan:
February 18, 2014; Approved at 1st reading (6-1) subject to the following stipulations: approval of requested variances—driveway stacking
depth and Subdivision Ordinance regarding the public and private street access that will be configured as shown on the concept plan; concept plan review summary No. 3, dated February
11, 2014; understanding that applicant must come forward before the second reading with the following matters to be appropriately detailed and discussed (1) detailed entry feature on
front southeast corner of the hotel, which may include fountains, landscape islands and detailed renderings of such, (2) regarding Lot 6, a detailed landscape plan showing how that can
be incorporated with the federal requirements to not disturb the floodway, (3) discussion of the property owners agreement and how that may work regarding the project, (4) detailed
floor plans, more specifically the first floor and within that floor plan a detail of the outdoor public spaces and how those will be incorporated into the hotel, (5) also regarding
Lot 6, noting what can be manicured to the extent to provide for periodic maintenance within the floodway in connection with Lot 6 landscape detail and provide detailed plant material
for entire project, and (6) detailed renderings for convention center from the Kimball approach which would also include traffic circle.
50
Council Action
ZA13-135 Zoning Change and Concept/Site Plan:
February 18, 2014; Approved at 1st reading (6-1) subject to the following stipulations: approval of requested variances—driveway stacking
depth and Subdivision Ordinance regarding the public and private street access that will be configured as shown on the concept plan; concept plan review summary No. 3, dated February
11, 2014; understanding that applicant must come forward before the second reading with the following matters to be appropriately detailed and discussed (1) detailed entry feature on
front southeast corner of the hotel, which may include fountains, landscape islands and detailed renderings of such, (2) regarding Lot 6, a detailed landscape plan showing how that can
be incorporated with the federal requirements to not disturb the floodway, (3) discussion of the property owners agreement and how that may work regarding the project, (4) detailed
floor plans, more specifically the first floor and within that floor plan a detail of the outdoor public spaces and how those will be incorporated into the hotel, (5) also regarding
Lot 6, noting what can be manicured to the extent to provide for periodic maintenance within the floodway in connection with Lot 6 landscape detail and provide detailed plant material
for entire project, and (6) detailed renderings for convention center from the Kimball approach which would also include traffic circle.
51
Aerial View
52
Elevations Presented to P&Z on January 9th
53
Elevations Presented to P&Z on February 6th
54
Revised Elevations
Stucco replaced by brick
55
Elevations Presented to P&Z on January 9th
56
Elevations Presented to P&Z on February 6th
57
Revised Elevations
Stucco replaced by brick
58