Loading...
Item 4DCITY OF SOUTHLAKE MEMORANDUM (October 21, 2014) To: Shana Yelverton, City Manager From: Robert H. Price, P.E., Director of Public Works Subject: Award construction contract to Green Scaping, LP for the South White Chapel bridge scour measures in the amount of $125,334. Action Requested: Award construction contract to Green Scaping, LP for the South White Chapel bridge scour measures in the amount of $125,334. Background Information: In December of 2011, the City of Southlake was notified by TxDOT of concerns regarding channel degradation over a period of years at the South White Chapel bridge. TxDOT recommended substructure scour measures in order to help stabilize the channel bottom and help prevent further erosion. The South White Chapel bridge is equally important to the Cities of Southlake and Colleyville and any costs associated with the engineering and construction will be shared equally. Halff Associates, Inc. analyzed the existing bridge and produced an engineering report with recommendations for scour mitigation. This construction contract includes the installation of rock rip -rap for scour countermeasures, concrete collars for the columns to provide structural support, and additional scour protection on the north stream bank. These improvements will stabilize the channel bottom and help prevent further erosion as recommended by TxDOT during a routine inspection. The challenge during construction will be limiting vibration of passing vehicles during the concrete collar installation. Many discussions were held with the City of Colleyville regarding ways to allow the bridge to remain open to traffic during construction and protect the workers. This contract allows Green Scaping, LP to close the bridge for up to thirty (30) days within the ninety (90) day construction time. The bridge closure is anticipated between mid - November through mid -December, weather permitting. Three (3) bids were received on September 16, 2014. The bids have been reviewed by Halff Associates, Inc and city staff and are tabulated as follows: Green Scaping, LP Klutz Construction, LLC DCI Contracting, Inc. BID AMOUNT $125,334 $217,506 $348,430 Halff Associates, Inc. recommends award of the contract to the low bidder, Green Scaping, LP. The City Staff concurs in this recommendation. Financial Considerations: The recommended contract award amount is $ 125,334. Funds are available in the Stormwater Utility Fund. The current available project budget is $134,000. The construction cost will be shared equally by City of Southlake and the City of Colleyville. An interlocal agreement with the City of Colleyville was executed on September 17, 2013. City of Southlake Cost $62,667 City of Colleyville Cost $62,667 Total Cost of Construction $125,334 Strategic Link: The South White Chapel bridge scour measures link to the city's strategy map relative to focus areas of Infrastructure. The specific corporate objectives that are met by this construction project are to invest to provide and maintain high quality public assets. The critical business outcome is to optimize resources through collaboration and partnerships to reduce costs and add service value. Citizen Input/ Board Review: N/A Legal Review: This is a standard construction services contract. Alternatives: The Council may award the contract to Green Scaping, LP. or reject all bids. Supporting Documents: Location Map Recommendation Letter Bid Tabulation Staff Recommendation: Award construction contract to Green Scaping, LP for the South White Chapel bridge scour measures in the amount of $125,334. Staff Contact: Robert H. Price, P.E., Public Works Director Cheryl Taylor, P.E., Deputy Director Public Works/City Engineer Steven D. Anderson, P.E., CFM, Civil Engineer 1. *n ;;; HALFF October 1, 2014 AVO 29761 Mr. Steve Anderson, P.E. City Engineer City of Southlake 1400 Main Street, Suite 320 Southlake, Texas 76092 Re: White Chapel Blvd over Big Bear Creek Scour Countermeasure Dear Mr. Anderson, Bids were opened on the above -referenced project on Tuesday, September 16, 2014 at the City of Southlake. Three (3) bids were received and they ranged from a low bid of $125,334.00 to a high bid of $348,340.00. C. Green Scaping, LP submitted the low bid, and Klutz Construction, LLC was second with a bid of $217,506.00. We contacted the following references to verify C. Green Scaping, LP qualifications to complete the required work: Jason Moore listed as City of North Richland Hills, now Assistant to the City Manager City of Richland Hills; Larry Stipes Lantana, Project Manager/Superintendent; and Jeremy Hutt, City Engineer with the City of Colleyville. All of the above references stated C. Green Scaping have performed well on their projects. None of the references had any liquidated damages against C. Green Scaping. However, it appears C. Green Scaping has not performed this specific type of bridge work for any of those references. Mr. Moore stated C. Green Scaping satisfactorily completed a concrete trail and 6-7 large cast -in -place concrete drainage structures with rock riprap erosion control as part of the City of North Richland Hills Multi Use Trail Project. While references to the contractor's work is positive, Mr. Hutt with the City of Colleyville was concerned because he did not readily associate this contractor with the types of work required for this project. Mr. Hutt's final recommendation was to conduct a pre - award meeting between the City of Southlake, the City of Colleyville, and the contractor. A pre -award meeting was conducted on September 25, 2014 at the City of Southlake. The meeting was attended by representatives of the City of Southlake, City of Colleyville, Halff Associates, and Cody Johnson represented C. Green Scaping as the project manager. The meeting addressed several project specific issues. C. Green Scaping unit prices for "Site Preparation & Mobilization" and "Temporary Construction Entrance" were significantly lower than the other bidders. "Site Preparation and Mobilization" as identified in the plans was to include temporary shoring of the bridge during construction. Mr. Johnson explained the unit price of the shoring was distributed into all bid items and not specifically into "Site Preparation & Mobilization", but is included in the total bid price. Their ,p; HALFF intention for shoring the bridge is to use a system of screw jacks and/or pole shores set on timber pads in the creek bottom to ensure the integrity of the bridge during construction. The details of the temporary construction entrance including grading, surface, and protection of the existing road shoulder were discussed and Mr. Johnson confirmed their unit price covered all required work to be performed under the bid item. The second item of concern was the response provided in Qualification Statement, Question 5, contractor's plan or layout for performing proposed work. The response was general and did not address key issues such as the traffic control plan, temporary shoring, details of equipment to be utilized, or construction techniques. Mr. Johnson addressed all of these issues during the meeting to our satisfaction. The next item of concern was C. Green Scaping's lack of experience in vertical concrete construction with vehicular loaded bridges. Mr. Johnson discussed multiple recent projects involving bridge piers and concrete installations in riverine environments. It was determined that C. Green Scaping was to provide additional project specific references. We contacted several additional references to verify Green Scaping, LP qualifications to complete the required work. The name of the reference and their comments are as follows: • Mary Ayala (City of Dallas) — One of the better contractors she's seen in an environmentally sensitive area; no problems she could think of working with them; all their concrete work was fine and has not had any problems in the 3 years since the project was completed. • Nick Myers (UTA) — Great contractor; very responsive; concrete and brick work was very well done; they are very detailed and timely; he highly recommends them. • Gene Moulden (City of Irving) — They did a great job; there were some issues with the geotech and they worked well getting through those issues; their concrete work was good; they kept their schedule; he would definitely work with them again. Lastly, during the pre -award meeting Mr. Johnson was asked if his company had resources available to start work around the beginning of November and achieve substantial completion within the 90 days specified in the contract. Mr. Johnson has provided a preliminary schedule and has assured us they are ready to go and did not anticipate any problems meeting the City of Southlake critical bridge opening date of January 5, 2015. In conclusion, aside from the lack of experience in this specific construction technique, we did not receive any report that leads us to believe C. Green Scaping cannot successfully complete the project. Based on our research, it is the opinion of Halff Associates, Inc. that there is no apparent reason to disqualify the bid proposal of C. Green Scaping, LP for the White Chapel Blvd over Big Bear Creek Scour Countermeasure Improvements. ,pp HALFF Please call me at (817) 847-1422 if you have any questions or comments. Sincerely, HALFF ASSOCIATES, INC. Levi Hein, PE, CFM Lead Design Engineer O O O O O O O O O O O O O O O O 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O O O N O o0 O O O O O V O O c N O M O O c� o0 0 O 0 In is M ER ER ER W N ER N ER O V O_ 00 ER ER ER ER ER ER O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O In O O O O O O O O O O O N (D v) O O O O (R O O V (R In (R O O N_ d) O O O I- � O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O 00 O O_ W O O O O O O In 'ITO OD M O O 00 (D O W 00 N 00 O V m M N W O O N N ro �_ N6"'— N— In N_ N V N I- O ER ER ER ER ul ul M (iT N O O O O O O O O O O O O O O O O O O O In O O O O O O O O 000000 m O 00 O O 00 N O V O O O In N - O M O O (iT O 00 V ER 00 ER M m (fi O O O N N In O 6c� (iT (iT (iT (iT (iT NER O O O O O O O O O O O O O O O O O O O O O O O O O O O O 0006660C.4000000 7 O O O O m In O r O O V (D O I� M W O V 00 O (D o N o M In In In d) M M N .ti ER ER ER ER ER M ER N In N (R N ul ul 6c� 6c� 6c� O O O O O O O O O O O O O O 90 O O 010 o 0 0 0 0 999 O O M O O 1 O (V O O O O O O O O O In ER O I� O M (iT O � In ER V ER V 'IT O M(r) N O (') V ER (R ER MEIN ER ER OM N O (D N N M W Lo a N Lo 'd O fn fn LL Q Q � � J J J W W fn J U U U fn fn J fn O C O U Y q o 0. o d U � D t � O W N U (6 j N t U t Ca N N U O H (6 W C O M Q O 0 X N N O O 2 W N U m° t° i0c) 0 d m'E in 0 m y N N a 0).0U aE) U co ° o- E `m 5 o E ii iE 05 m N 0> N u) U .N U) 0 y E U y d N 0 y d a a 0 0 o d m o o C u 0 E E a)o o D . r- E c U c H 00 iA 7 oD0 U M U H U z N M V In O r OD W O N M V mc.