Item 6I r
-C,S�v. t-eu, `ry
Southlake Town Square
Garden District
Proposed Development Phasing Plan
Phase I — Stage 1 (Land Development):
• Projected Timing
o Land development - March 2014 to June 2014
o First Brownstones (Model, Spec homes) construction begins July 2014
• Site Work
o Mass Grading of entire site
o Shaping of Oval Park
o Slope shaping of open space to Park Ridge Boulevard
• Road Construction
o Meeting Street constructed
o Summit Avenue extended to Meeting Street
o Park Ridge Boulevard reconfigured to eliminate median
o Alley extended east to Park Ridge Boulevard
• Brownstone Lot Development
o Storm Water pipe installation (New lines on Meeting Street and Park Ridge Blvd
frontage)
o Sewer pipe installation (New line on Meeting Street, existing on Park Ridge Blvd)
o Electric Power installation in alley (including transformer relocation)
o Natural Gas Lines installed (Connection to existing distribution line in alley)
o Telecommunication lines installation in alley
Phase I — Stage 2 (Landscape / Hardscape):
• Projected Timing
o Landscape /Hardscape installation - December 2014 to March 2015
o First Brownstones (Model, Spec homes) construction completion — May 2015
• Oval Park Landscape and Hardscape
o All walking paths and interior retaining walls installed
o Park/Street trees and other landscaping installed
o Benches, tables, future art plaza installed
o Community garden installed
o Bocce Court installed
• Dog Park Installation
o Fencing, play area, double gate
• Open Space Landscaping
o Sprigged with Coastal Bermuda grass (temporary irrigation)
o Wildflower seed in designated areas