Loading...
Item 9AItem 9A CITY OF SOUTH LAKE MEMORANDUM (August 20, 2013) To: Shana Yelverton, City Manager From: Robert H. Price, P.E., Director of Public Works Subject: Award construction of North Kimball Avenue from Kirkwood Boulevard to Dove Road to Pavecon, LTD in the amount of $3,464,780.40 Action Requested: Award construction of North Kimball Avenue from Kirkwood Boulevard to Dove Road to Pavecon, LTD in the amount of $3,464,780.40. Background Information: This project includes the widening of North Kimball Avenue from Kirkwood Boulevard to East Dove Road from a 2-lane asphalt roadway to a 4-lane divided concrete roadway including landscaped medians, as adopted by the City Council in the Master Thoroughfare Plan. The construction of North Kimball Avenue from Kirkwood Boulevard to Dove Road is a partnership between Southlake and Grapevine in anticipation of the increased traffic due to the construction of the DFW Connector project on SH114. Once the construction along SH114 is complete, Kimball Avenue will be the easternmost entrance onto the SH114 main lanes from which traffic will be able to access the managed lanes. Approximately 2,500 linear feet of 12-inch water line and 2,000 linear feet of 8-inch sanitary sewer improvements will be constructed along North Kimball Avenue from Kirkwood Boulevard to Dove Road to comply with the City's water and wastewater master plans. Also included in the project are 2,200 linear feet of storm drain, 6-foot sidewalks on either side of the roadway, landscaping and irrigation, decorative hardscape, and concrete rock veneer retaining walls and screening walls. Four (4) bids were received on July 30, 2013 for the construction of North Kimball Avenue. The bids have been reviewed by Kimley- Horn and Associates, Inc. and city staff and are tabulated as follows.. Contractor Standard Bid (A) Time Bid x $1,000 (B) A+B Pavecon, LTD. $3,464,780.40 300 x $1,000 $3,764,780.40 JLB Contracting, LLC $3,505,708.28 470 x $1,000 $3,975,708.28 Quality Excavation, Ltd. $3,685,448.25 356 x $1,000 $4,041,448.25 Lone Star Civil Const., Inc.$3,733,422.02 350 x $1,000 $4,083,422.02 The city instituted a slightly different bidding process in order to try and have the project completed at an accelerated pace. An "A+B" bidding process was used whereby the contractors bid the number of calendar days for the construction of the project. An incentive/disincentive is established based on completing the project within the timeframe. In summary, the "A+B" bidding method requires the contractor to consider both the cost of constructing the project along with the time required for final acceptance of the project. The "A" component is the traditional bid amount (sum of all bid prices). The "B" component is the "bid" of the total number of calendars days determined by the contractors to complete the project, multiplied by an specified dollar amount per day (as determined by the City). In this case, the city determined the dollar amount per day for incentive/disincentive as $1,000 per day along with the maximum incentive of $30,000 for completing the project at least 30 days early. Pavecon, the low bidder, bid 300 days for the construction of the project; therefore, the "B" amount is $300,000. The total "B" amount ($300,000) is only used for the basis of comparing bids and not to be used to determine final payment. The project is recommended to be awarded to the contractor with the lowest total "A+B" amount. The recommended amount of the contract that Council will be considering is only the "A" component. Again, the "B" component is only used for a basis of determining the low bidder. At the completion of the project, the calendar days are counted and any days over/under are multiplied by the specified $1000/day to determine the final incentive/disincentive amount, up to $30,000 maximum. If the Contractor goes over the 300 calendar days to complete the project, the Contractor is charged the specified $1000/day for each day they are over with no maximum disincentive. A breakdown of Southlake's portion of major project components of the bid is as follows: Description Cost Paving $1,424,949.93 Drainage $163,645.53 Water $296,183.67 Sewer $140,384.85 Sidewalks $175,135.81 Landscape/Irrigation $155,879.96 Total Southlake Cost $2,356,179.75 Total Grapevine Cost $1,108,600.65 Total Construction Bid $3,464,780.40 The low bid was approximately 10% higher than the engineer's estimate of $3,173,645. Kimley-Horn Associates, Inc. recommends award of the contract to the low bidder, Pavecon, LTD. The City Staff concurs in this recommendation. Financial Considerations: The recommended contract award amount is $3,464,780.40. The contract amount is approximately 10% higher than the design consultant's opinion of probable costs. The proposed FY2014 CIP annual budget submitted for City Council's consideration has requests of an additional $1,000,000 in the FY14 General Fund Capital Improvement Plan and $500,000 in the FY14 Utility Fund Capital Improvement Plan budget to complete this project. A portion of North Kimball Avenue north of Shady Lane is within the city limits of Grapevine. The inter local agreement between the cities of Southlake and Grapevine for the construction of Kimball Avenue from Shady Lane to Dove Road spells out the funding agreement between the two cities. The City of Grapevine will reimburse the City of Southlake 100% of the cost of their construction, material testing and their utility relocations. The final participation amount shall be determined from the actual construction contract unit bid items and prices. Based on the bids received, the City of Grapevine's share of the cost is $1,108,600.65. The City of Grapevine will also reimburse the City of Southlake its share of the design cost as a percentage of the total construction cost. Grapevine's proportional share of the engineering design of the project is $138,099.58, which is approximately 12.7% of the total design cost of the project. Strategic Link: The construction of Kimball Avenue links to the city's strategy map relative to focus area of Mobility, Infrastructure, Partnerships and Volunteerism, and Performance Management and Service Delivery. The specific corporate objectives that are met by this construction project are to provide travel convenience within the City and region, to invest to provide and maintain high quality public assets, promote opportunities for partnerships and volunteer involvement and to collaborate with select partners to implement service solutions. The Critical Business Outcome is to optimize resources through collaboration and partnerships to reduce costs and add service value. Citizen Input/ Board Review: N/A Legal Review: This is the standard construction services contract that has been previously reviewed by the City Attorney. Alternatives: The Council may award the contract to Pavecon, LTD or reject all bids. Supporting Documents: Location Map Recommendation Letter Bid Tabulation FY2014 CIP Project Status Form Staff Recommendation: Award construction of North Kimball Avenue from Kirkwood Boulevard to Dove Road to Pavecon, LTD in the amount of $3,464,780.40 Staff Contact: Robert H. Price, P.E., Public Works Director Cheryl Taylor, P.E., City Engineer Steven D. Anderson, P.E., CFM, Civil Engineer Legend 46 Pro,' S- 7. OD �tjmpq,-, U-1 I `= Kimley-Horn and Associates, Inc. July 31, 2013 Via Mail and Email Ms. Cheryl Taylor, P.E. City of Southlake 1400 Main Street, Suite 320 Southlake, Texas 76092 Re: North Kimball Avenue (Kirkwood Boulevard to Dove Road) Bid Results KHA No. 061237001 Dear Cheryl: On July 30, 2013, the City of Southlake received bids for the North Kimball Avenue (Kirkwood Boulevard to Dove Road) project. Each bid submitted consisted of two parts Standard Bid (A) and Time Bid (B). A daily value of $1,000 per calendar day was established as an incentive -disincentive provision. A maximum incentive of $30,000 was established ($1,000 per day for early completion up to 30 days) with no maximum disincentive ($1,000 per day over the Time Bid). The sum ofA+B was used to determine the lowest evaluated bid. The following four bids were received, and detailed bid tabulation is attached for your review. Contractor Standard Bid (A) Time Bid x $1,000 (B) A+B Pavecon, LTD. $3,464,780.40 300 x $1,000 $3,764,780.40 JLB Contracting, LLC $3,505,708.28 470 x $1,000 $3,975,708.28 Quality Excavation, Ltd. $3,685,448.25 356 x $1,000 $4,041,448.25 Lone Star Civil Const., Inc. $3,733,422.02 350 x $1,000 $4,083,422.02 Kimley-Horn and Associates, Inc. has reviewed the low bidder's qualifications and has verified that the Contractor's bonding company is licensed in the State of Texas. Based on these reviews, it appears that Pavecon, Ltd. is the lowest responsive bidder based on the sum of A+B in the amount of $3,764,780.40 with 300 calendar days. The contract award amount to be considered by Council is based on the Standard Bid (A) component only ($3,464,780.40) plus a bonus incentive of up to $30,000. If you have any questions or comments, please give me a call. Very truly yours, KIMLEY-HORN AND ASSOCIATES, INC. L. Nathan Ante, P.E. LNA:j 1p Enclosure KALAC Roadway\061237.001\CCA-PHASE2\Bidding\Rec Award Letter.doc ■ Suite 275 2201 West Royal Lane Irving, Texas 75063-3206 TEL 214 420 5600 FAX 214 420 5680 BID TABULATION KIMLEY-HORN AND ASSOCIATES, INC. CHECKED BY:�^-�- Nathan Ante, P.E., 7/30/13 Owner: City of Southlake Job No.: 61237001 Project: North Kimball Avenue (Kirwood Blvd to Dove Road) Date: July 30, 2013 BIDDER 1 BIDDER 2 BIDDER 3 BIDDER 4 Pavecon , LTD 3 222 Roy Orr Blvd. Grand Prairie, Texas 75050 JLB Contracting, LLC P.O. Box 24131 Fort Worth, Texas 76124 Quality Excavation, Ltd. 5700 US Hwy 377 Aubrey, Texas 76227 Lone Star Civil Construction, Inc. 320 Windsor Centre Trail, Ste 500 Flower Mound, Texas 75028 Item No. Item Description Quantity unit unit Price Item Cost unit Price Item Cost unit Price Item Cost unit Price Item Cost Base Bid 1 IMOBILIZATION 1 LS $164,016.16 $164,016.16 $138,650.00 $138,650.00 $86,000.00 $86,000.00 $322,419.60 $322,419.60 2 GENERAL SITE PREPARATION 1 LS $118,172.00 $118,172.00 $68,200.00 $68,200.00 $136,000.00 $136,000.00 $185,384.66 $185,384.66 3 UNCLASSIFIED STREET EXCAVATION 26,000 CY $8.55 $222,300.00 $16.90 $439,400.00 $15.00 $390,000.00 $9.06 $235,560.00 4 BORROW/EMBANKMENT 4,000 CY $8.27 $33,080.00 $5.15 $20,600.00 $19.00 $76,000.00 $9.27 $37,080.00 5 TEMP EROS, SEDIMENT AND WATER POLLUTION 1 LS $22,789.48 $22,789.48 $12,190.00 $12,190.00 $48,000.00 $48,000.00 $17,525.84 $17,525.84 6 8" REINF CONC PAVEMENT CL P1 , P2 WITH 25,000 SY $39.20 $980,000.00 $37.59 $939,750.00 $40.00 $1,000,000.00 $41.00 $1,025,000.00 7 RIBBON CURB DOVE CLA 300 LF $24.18 $7,254.00 $9.60 $2,880.00 $19.00 $5,700.00 $31.02 $9,306.00 8 CEMENT STABILIZED SUBGRADE 6" 29,000 SY $3.96 $114,840.00 $2.15 $62,350.00 $3.50 $101,500.00 $2.62 $75,980.00 9 CEMENT 42 LBS/SY 609 TON $119.05 $72,501.45 $117.00 $71,253.001 $117.00 $71,253.00 $124.75 $75,972.75 10 2" HMAC SURFACE COURSE TY D 1,550 SY $12.09 $18,739.50 $10.40 $16,120.00 $13.00 $20,150.00 $14.01 $21,715.50 11 3" HMAC BASE COURSE TY B 650 SY $22.05 $14,332.50 $15.25 $9,912.50 $22.00 $14,300.00 $20.52 $13,338.00 12 6" HMAC BASE COURSE TY B 900 SY $29.56 $26,604.00 $29.05 $26,145.00 $39.50 $35,550.00 $36.21 $32,589.00 13 CONCRETE DRIVEWAY APPROACH 785 SY $37.43 $29,382.55 $45.85 $35,992.25 $46.00 $36,110.00 $40.39 $31,706.15 14 ASPHALT DRIVEWAY 2" TY D ON 4" TY B ON 380 SY $36.30 $13,794.00 $46.50 $17,670.00 $35.50 $13,490.00 $45.91 $17,445.80 15 CONCRETE DRIVEWAY (6" REINF ON COMPACTED SUBGRADE 80 SY $37.43 $2,994.40 $45.85 $3,668.00 $46.00 $3,680.00 $64.01 $5,120.80 16 CONCRETE DRIVEWAY GRAHAMS 200 SY $41.58 $8,316.00 $51.10 $10,220.00 $68.00 $13,600.00 $51.54 $10,308.00 17 CONCRETE DRIVEWAY SHARED ACCESS 425 SY $40.33 $17,140.25 $49.251 $20,931.25 $73.00 $31,025.00 $44.78 $19,031.50 18 REINF CONCRETE STREET HEADER 570 LF $13.56 $7,729.20 $8.55 $4,873.50 $16.00 $9,120.00 $6.42 $3,659.40 19 5" REINF CONC SIDEWALK 3,000 PSI 4,000 SY $33.44 $133,760.00 $39.60 $158,400.00 $36.00 $144,000.00 $35.11 $140,440.00 20 REINF CONC SIDEWALK ADJACENT TO RETAINING 250 SY $62.07 $15,517.50 $48.80 $12,200.00 $55.00 $13,750.00 $49.80 $12,450.00 21 RETAINING WALL ADJACENT TO SIDEWALK HT UP 1,600 SF $27.46 $43,936.00 $12.15 $19,440.00 $25.00 $40,000.00 $35.71 $57,136.00 22 STONE VENEER 1,600 SF $21.06 $33,696.00 $37.00 $59,200.00 $17.00 $27,200.00 $30.38 $48,608.00 23 4" CONCRETE FLUME ADJACENT TO RETAINING 1,500 SF $6.33 $9,495.00 $5.75 $8,625.00 $5.00 $7,500.00 $16.04 $24,060.00 24 BARRIER FREE RAMP TxDOT TYPE 1 10 EA $1,060.00 $10,600.00 $690.00 $6,900.00 $1,000.00 $10,000.00 $678.92 $6,789.20 25 BARRIER FREE RAMP TxDOT TYPE 5 4 EA $1,737.00 $6,948.00 $1,060.00 $4,240.00 $1,250.00 $5,000.00 $934.96 $3,739.84 26 BARRIER FREE RAMP TxDOT TYPE 7 23 EA $1,141.00 $26,243.00 $690.00 $15,870.00 $1,000.00 $23,000.00 $1,257.97 $28,933.31 27 BARRIER FREE RAMP TxDOT TYPE 22 1 EA $3,511.00 $3,511.00 $1,515.00 $1,515.00 $1,700.00 $1,700.00 $1,695.43 $1,695.43 28 MONOLITHIC MEDIAN NOSE - TYPE 1 15 EA $706.00 $10,590.00 $545.00 $8,175.00 $1,200.00 $18,000.00 $1,305.21 $19,578.15 29 MONOLITHIC MEDIAN NOSE -TYPE 2 3 EA $1,411.00 $4,233.00 $490.00 $1,470.00 $1,500.00 $4,500.00 $1,824.86 $5,474.58 30 PIPE RAIL WITH HORSE FENCE PATTERSON 1,110 LF $26.85 $29,803.50 $25.50 $28,305.00 $29.00 $32,190.00 $16.82 $18,670.20 31 PIPE RAIL WITH HORSE FENCE BARBARIA 330 LF $65.27 $21,539.10 $55.30 $18,249.00 $70.00 $23,100.00 $16.82 $5,550.60 32 6' STOCKADE FENCE STEAGALL 50 LF $26.32 $1,316.00 $23.40 $1,170.00 $29.00 $1,450.00 $22.42 $1,121.00 33 TEMPORARY FENCING 1,100 LF $3.53 $3,883.00 $6.40 $7,040.00 $4.00 $4,400.00 $3.36 $3,696.00 34 TRAFFIC CONTROL 1 LS $185,595.37 $185,595.37 $75,000.00 $75,000.00 $37,000.00 $37,000.00 $117,372.43 $117,372.43 35 ADDITIONAL TEMP ASPHALT PAVEMENT 3" TY B 500 SY $34.69 $17,345.00 $31.55 $15,775.00 $44.00 $22,000.00 $46.75 $23,375.00 36 4" WHITE THERMOPLASTIC LANE LINE STRIPE 1,700 LF $1.04 $1,768.00 $1.25 $2,125.00 $1.15 $1,955.00 $3.05 $5,185.00 37 8" SOLID WHITE THERMOPLASTIC TURN BAY 200 LF $1.58 $316.00 $1.60 $320.00 $1.70 $340.00 $4.68 $936.00 38 12" SOLID WHITE THERMOPLASTIC CROSSWALK 200 LF $3.16 $632.00 $3.40 $680.00 $3.40 $680.00 $9.35 $1,870.00 39 24" SOLID W HATE THERMOPLASTIC STOP BAR 160 LF $6.32 $1,011.20 $6.20 $992.00 $6.80 $1,088.00 $18.70 $2,992.00 40 4" SOLID DOUBLE YELLOW THERMOPLASTIC 725 LF $2.09 $1,515.25 $2.45 $1,776.25 $2.25 $1,631.25 $6.17 $4,473.25 41 12" SOLID YELLOW THERMOPLASTIC CHEVRONS 45 LF $3.16 $142.20 $5.30 $238.50 $3.40 $153.00 $9.35 $420.75 42 FIRE LANE THERMPLASTIC STRIPE 200 LF $3.16 $632.00 $0.30 $60.00 $3.40 $680.00 $9.35 $1,870.00 43 SOLID WHITE THERMOPLASTIC ARROW 25 EA $126.32 $3,158.00 $132.90 $3,322.50 $136.00 $3,400.00 $374.07 $9,351.75 44 SOLID WHITE THERMOPLASTIC WORD 1 EA $142.11 $142.11 $186.00 $186.00 $153.00 $153.00 $420.83 $420.83 45 TY II-C-R RAISED PAVEMENT MARKER LANE LINE 350 EA $3.06 $1,071.00 $3.45 $1,207.50 $3.50 $1,225.00 $9.04 $3,164.00 46 TY II -A -A RAISED PAVEMENT MARKER CHEVRONS 50 EA $3.06 $153.00 $3.45 $172.50 $3.50 $175.00 $9.04 $452.00 47 FURNISH AND INSTALL SIGNAGE 1 LS $12,721.06 $12,721.06 $7,283.00 $7,283.00 $14,000.00 $14,000.00 $13,548.69 $13,548.69 48 CONDUIT PVC) (SCHD 40 4" FOR TRAFFIC SIGNAL 1,500 LF $7.27 $1Q905.00 $7.35 $11,025.00 $6.00 $9,000.00 $7.74 $11,610.00 49 IGROUND BOXTY D 162922 W/APRON FOR 8 EA $578.95 $4,631.60 $584.77 $4,678.16 $600.00 $4,800.00 $616.61 $4,932.88 50 STREET LIGHT FOUNDATION 19 EA $831.58 $15,800.02 $840.00 $15,960.00 $1,200.00 $22,800.02 $885.68 $16,827.92 51 CONDUIT PVC) (SCHD 40 2" FOR STREET 3,850 LF $4.53 $17,440.50 $4.55 $17,517.50 $5.00 $19,250.02 $4.82 1 $18,557.00 52 RELOCATE EX DECORATIVE STREET 2 EA $3,710.53 $7,421.06 $3,748.00 $7,496.00 $2,850.00 $5,700.02 $3,95'L94 $7,903.88 53 PROJECT SIGN 2 EA $789.48 $1,578.96 $345.55 $691.10 $525.00 $1,050.02 $448.45 $896.90 54 RELOCATE EX MAILBOX 9 EA $154.64 $1,391.76 $576.72 $5,190.48 $700.00 $6,300.02 $525.951 $4,733.55 55 18" RCP CLASS III 1,200 LF $51.55 $61,860.001 $87.301 $104,760.00 $109.00 $130,800.02 $64.171 $77,004.00 56 24" RCP CLASS III 350 LF $62.89 $22,011.50 $97.951 $34,282.50 $88.00 $3Q800.0n $64.21 $22,473.50 PAGE 1 OF 2 BID TABULATION KIMLEY-HORN AND ASSOCIATES, INC. Owner: City of Southlake Job No.: 61237001 Project: North Kimball Avenue (Kirwood Blvd to Dove Road) Date: July 30, 2013 Item No. Item Description Quantity Unit 57 30" RCP CLASS III 400 LF 58 36" RCP CLASS III 200 LF 59 RECESSED CURB INLET- 10' 16 EA 60 RECESSED CURB INLET- 10' TOP 4 EA 61 DROP INLET -4'x4' 11 EA 62 JUNCTION BOX -5'x5' 2 EA 63 SAFETY END TREATMENT TXDOT PSET-PD 1 EA 64 ICONVERT EX DROP INLET INTO A JUNCTION BOX 4 EA 65 ADJUST EXISTING STORM DRAIN MANHOLE 1 EA 66 TRENCH SAFETY - STORM DRAIN 2,150 LF 67 8" PVC SDR 26 SANITARY SEWER 2,000 LF 68 4'DIAMETER SANITARY SEWER MANHOLE 2 EA 69 SDIAMETER SANITARY SEWERMANHOLE 2 EA 70 CONNECT TO EXISTING SANITARY SEWER 1 LS 71 4" STANDARD SERVICE CONNECTION W/ 9 EA 72 4" DEEP SERVICE CONNECTION W/ CLEANOUT 21 EA 73 ADJUST EX. SANITARY SEWER MANHOLE 1 EA 74 TRENCH SAFETY - SANITARY SEWER 2,000 LF 75 12" PVC C-900 DR-18 WATER LINE 2,500 LF 76 8" PVC C-900 DR-18 WATER LINE 80 LF 77 6" PVC C-900 DR-18 WATER LINE 20 LF 78 12" GATE VALVE 9 EA 79 8" GATE VALVE 2 EA 80 6" GATE VALVE 1 EA 81 8" TAPPING SLEEVE AND VALVE 1 EA 82 ADJUST EX WATER VALVE 8 EA 83 FIRE HYDRANT ASSEMBLY INLCUDES LEADNALVE 9 EA 84 CAST IRON FITTINGS 8 TON 85 WATER SERVICE 9 EA 86 WATER METER BOX 9 EA 87 2" BLOW -OFF ASSEMBLY 1 EA 88 CONNECT TO EX 6" PVC 1 EA 89 CONNECT TO EX 8" PVC 2 EA 90 CONNECT TO EX 12" PVC 1 EA 91 CUT, PLUG & BLOCK EX 6", 8", and 12" WATER LINES 1 LS 92 TRENCH SAFETY - WATER 2,600 LF 93 IRRIGATION SYSTEM MEDIANS 1 LS 94 ADJUST AND RESTORE EX IRRIGATION SYSTEMS 1 LS 95 STAMPED INTEGRAL COLOR LIGHT -DUTY 9,400 SF 96 STAMPED INTEGRAL COLOR HEAVY-DUTY 2,150 SF 97 CONCRETE MOWSTRIP 220 LF 98 4" TOPSOIL 17,500 SY 99 GROUNDCOVER SEED 2,500 SY 100 GROUNDCOVER SOD 15,000 SY 101 GROUNDCOVER RED DRIFT ROSE 180 EA 102 GROUNDCOVER ASIAN JASMINE 1,100 EA 103 SHRUB 3 GAL PURPLE PIXIE LOROPETALUM 140 EA 104 SHRUB 3 GAL DWARF YAUPON 600 EA 105 TREE 3" CATHEDRAL LIVE OAK 6 EA 106 TREE 3" CHITALPA 3 EA 107 TREE 3" CAL SAVANNAH HOLLY 6 EA 108 TREE 3" CAL CRAPE MYRTLE'DYNAMITE RED' 4 EA 109 TREE 3" CAL CRAPE MYRTLE'NATCHEZ' 2 EA 110 HARDWOOD MULCH Y DEPTH 100 CY 111 STEEL EDGING 150 LF Total Amount of Base Bid Items 1-111 = Standard Bid A Total Time of Bid (Calendar Days) Total of Calendar Days x$1000 = Time Bid (B) Total Bid (A) + (B) 300 470 356 350 $300,000.00 $470,000.00 $356,000.00 $350,000.00 $3,764,780,40 $3,975,708.28 $4,041,448.25 $4,083,422.02 PAGE 2 OF 2 City of Southlake FY 2014 CIP Project Status Form Street Widening - N. Kimball Avenue from Highland St, to E. Dove Rd (Phase 11) DEPARTMENT: Public Works PROJECT LOCATION: Along N. Kimball Ave. from Highland north to E. Dove Rd. PROJECT TIMELINE: Oct. 2007 to Oct. 2014 DESCRIPTION: Funding is needed for Phase II expenses to widen N. Kimball Avenue from Highland St. to E. Dove Rd. to its ultimate pavement section (4 lanes divided). Grapevine will participate in the engineering and construction costs of Phase II per an executed Interlocal Agreement. FY 14 funding is specifically requested for construction and testing costs. Updated construction costs total $3.5M for Phase II split between Southlake ($2.4M) and Grapevine ($1.1 M). JUSTIFICATION: The N. Kimball Avenue widening project spans from SH 114 to Highland (Phase 1) and from Highland to E. Dove Rd. (Phase 11). Phase I was completed in 2012. The ultimate section will add traffic lanes to alleviate traffic congestion. This is one of the last managed (HOV/Toll) lanes for the TxDOT DFW Connector Project. Dollar figures listed below reflect the entire project's funding. Actual right of way expenses exceeded initial cost estimates due to numerous condemnation cases. ALTERNATIVES / IMPACTS IF PROJECT IS NOT FUNDED: This section of N. Kimball Avenue would not be able to accomodate additional traffic once the TxDOT DFW Connector Project is complete. STRATEGIC FOCUS AREA: Mobility, Infrastructure FUND: General, Utility r New Request r Continuation Project FX- Joint Use Mandated / Replacement / Major Community F- Public Health / FX- Rehab or Protection FX- Need / Safety of Capital Stock Service Compliant with Comprehensive Plan and / or other Master Plan? Fx- List (incl ref #): MT16 - Tier 1 FX- COMPANION PROJECT? If yes, please explain: N. Kimball Avenue from SH 114 to Highland (Phase 1) FX- REVENUE GENERATING? If yes, please explain: May facilitate commercial development/re-development EXPENDITURE PROJECT ELEMENT TOTAL PRIOR 2014 2015 2016 2017 2018 UNFUNDED TOTAL PLANNING / FEASIBILITY STUDY ENGINEERING & DESIGN 1,100 1,100 LAND 2,150 2,150 TESTING 50 40 90 CONSTRUCTION 6,005 1,460 7,465 OTHER TOTAL 9,305 1 1,500 1 1 1 1 1 1 10,805 OPERATIONAL PROJECT ELEMENT TOTAL PRIOR 2014 2015 2016 2017 2018 UNFUNDED TOTAL MAINTENANCE COSTS 20 20.6 21.2 21.9 83.7 PERSONNEL COSTS TOTAL 20 20.6 21.2 21.9 83.7 FUNDING FUNDING SOURCE TOTAL PRIOR 2014 2015 2016 2017 2018 UNFUNDED TOTAL GENERAL FUND 8,045 1,000 9,045 UTILITY FUND 500 500 ROADWAY IMPACT FEE FUND 1,260 1,260 WATER IMPACT FEE FUND SANITARY SEWER IMPACT FEE sWUs CCPD SPDC PARK DEDICATION FEE FUND TOTAL 9,305 1,500 10,805 CCPD: CRIME CONTROL & PREVENTION DISTRICT SPDC: SOUTHLAKE PARKS DEVELOPMENT CORPORATION SWUS: STORMWATER UTILITY SYSTEM FUND