White Chapel Blvd Widening - Letter for Temporary Construction Easement (Ledbetter Family) CITY OF
SOUTHLAKE
Public Works Administration
1400 Main Street I Suite 320 I Southlake, Texas 76092 I (p) 817- 748 -8098 I (f) 817- 748 -8077
May 8, 2013
[Certified Mail, Return Receipt Requested
# 7010 0290 0002 2574 6438]
Bob Ledbetter
100 Churchill Circle
Southlake, Texas 76092
Re: OFFER: 100 Churchill Circle, Southlake, Texas
City of Southlake Road Widening Project
All Trees and shrubs within six feet of the retaining wall and a ten
foot wide temporary Construction Easement being located at the
western most back property line as shown in the attached drawing
in the City of Southlake, Tarrant County, Texas
Dear Mr. Ledbetter:
The City of Southlake (City) is in the process of acquiring a temporary construction for the
Widening of White Chapel Blvd. which is needed to serve the existing development in the City,
and is necessary to serve the public health, safety and welfare. Because the City's negotiations to
purchase a temporary construction easement, has been successful to date, an offer is being
submitted.
• Temporary Construction Easement 2,672 sq feet x $1 = $2,672.00
• 5 Large Trees at $1,000 each = $5,000.00
• 1 Small Tree at $500 each = $ 500.00
• 6 Large Multi - Branch Shrubs at $250 each = $1,500.00
Total: $9,672.00
For the temporary construction easement, all trees and shrubs within six feet of the wall on the
property needed by the City for this project. Every effort will be made to save all trees and
shrubs but as a precaution all homeowners will be paid for trees and shrubs within six feet of the
new retaining wall. The City Council has authorized me to make a Total Offer of $9,672.
During the construction process, a temporary eight foot screening fence will be installed. This
fence will be made of chain link and covered with black construction material as to block the
view of your property. All sprinkler heads in the construction easement will be capped during the
construction and reconnected at the end of the project. This construction easement is for a period
Invocation • Intcgrin • Accountability • Commitm to Excellence • Icam■ork
Bob Ledbetter Page 2 of 2
May 2, 2013
of two years and the construction of the permanent retaining wall will be a high priority on this
project.
The old wall will be removed and replaced with a new brick screening wall constructed on the
edge of the City's street right of way adjacent to a 6 ft wide concrete sidewalk. The screening
wall will be 7 foot high from the finished elevation of the sidewalk. All side yard fences will be
reattached at the City's expense to the new screening wall.
The City would prefer to resolve this matter with you by agreement; please respond to this offer
no later than by May 22, 2013.
We hope you will give this offer serious consideration. If in agreement, please sign the offer
letter and return it to the City of Southlake in the attached envelope. If you have any questions,
or wish to discuss this matter or the City's offer in more detail, please contact Mr. Jerry Hodge of
Hodge & Associates at (817) 991 -3161 or jerryh64 @verizon.net.
Sincerely,
Steven D. Anderson, P.E.
Civil Engineer
cc: Robert Price, P.E., Director of Public Works
EXECUTED this / day of / Jq ,2013