Item 9B Approve Amendment No. 4 to the Engineering Agreement with Nathan D. Maier Consulting Engineers Inc. for White Chapel Boulevard from Highland Street to SH 114 in the amount of $53,316
Item 9B
Requested Action
Approve Amendment No. 4 to the Engineering Agreement with Nathan D. Maier Consulting Engineers Inc. for White Chapel Boulevard from Highland Street to SH 114 in the amount of $53,316
White Chapel Boulevard Improvements
Approve Amendment No. 4 for White Chapel Boulevard from Highland to SH 114
Background:
Original contract with Nathan D. Maier Engineers Inc.
October, 2008
$264,859
Survey
Roadway Design
Dove Creek hydrology study
Approve Amendment No. 4 for White Chapel Boulevard from Highland to SH 114
Amendment No. 1 - Revised Scope
Revised Alignment at intersection of Highland
Additional 2-feet of pavement – Bike traffic
Approve Amendment No. 4 for White Chapel Boulevard from Highland to SH 114
Amendment No. 2 - Revised Scope
Additional Survey
Dual Lane Roundabout Design
Final Engineering Plans
Updated Hydrology – Countryside Office Park
Landscape Design
Subsurface Utility Exploration
Approve Amendment No. 4 for White Chapel Boulevard from Highland to SH 114
Amendment No. 3 - Revised Scope
Plan Coordination
White Chapel Boulevard from Emerald to Highland
Lowered Roundabout
Approve Amendment No. 4 for White Chapel Boulevard from Highland to SH 114
Amendment No. 4 - Revised Scope
8-inch Sanitary Sewer Design
Right of Way Acquisition Coordination
Additional Right of Way Documents
Approve Amendment No. 4 for White Chapel Boulevard from Highland to SH 114
8-inch Sanitary Sewer Design $ 12,086
Right of Way Acquisition Coordination 5,115
Additional Right of Way Documents 36,015
Reimbursable Expenses 100
Total for Amendment #4 $53,516
Financial Consideration
Original Contract $ 264,859
Amendment #1 12,285
Amendment #2 173,827
Amendment #3 14,778
Amendment #4 53,316
Total Amended Contract $519,065
Funding is available
C2 Provide travel convenience within City and region
Questions:Bob Price (817) 748-8097