2003-02-05City of Southlake, Texas
.t
MEMORANDUM
January 28, 2003
TO: Crime Control and Prevention District Board of Directors
FROM: Rick Black, Director of Public Safety
SUBJECT: Approve funding of the Strategic Plan Report as developed by Trott
Communications Group to Join the Northeast Tarrant County Consortium
Radio System for Public Safety Radio Communications.
Action Requested: Approve funding to execute a contract and join the Northeast Tarrant County
Consortium Radio System.
Background
Information: On January 25, 2002 the Crime Control and Prevention District approved the
staff recommendation to direct Trott Communications to develop a strategic
radio plan. The plan has been finalized and is provided to you under separate
cover as an attachment to this request. The plan can be summarized as
follows. The City should adopt a standard of radio coverage at the "95%
coverage standard" for portable radios in their normal mode of operation. Any
solution should support mutual and automatic aid responses with surrounding
cities. A view of expansion and future technologies must also be taken into
accounting.
As you may recall the Department of Public Safety currently operates between
two different trunked radio systems, Fort Worth and Denton. Trott reviewed
the coverage of both systems. Neither the Fort Worth nor Denton system
penetrates more than 24% of Southlake for in -building coverage. In most
cases, neither system overlaps the other thus forcing officers to frequently
make system changes to be able to communicate. Neither Denton nor Fort
Worth is accepting the addition of any more units on their respective systems.
The Trott report basically presents the City with only two viable choices.
1. Do nothing and wait for future technology and frequencies to
develop. Purchase a system in the future and dedicate staff to the
operation of it.
2. Join the Northeast Tarrant County Consortium as a member of that
group with system management representation.
The Northeast Tarrant County Consortium consists of the cities of Bedford,
Euless, Keller, Colleyville, and Grapevine. The Consortium has indicated
willingness for Southlake to become a member of the system. In order to join
the system, Southlake would be responsible for a proportionate cost of the
original system construction plus costs associated with the addition of the
Southlake 800 MHz channel to the existing system. A portion of those costs
would be reimbursable when future cities join the system.
6A - 1
rime Control and Prevention District Board of Directors
January 28, 2003
Page 2
Financial
Considerations: The Northeast Tarrant County Consortium has offered the use of their trunked
radio system for a buy -in fee of $469,775 and the addition of the City of
Southlake's 800 MHz channel to the system, estimated at $400,000. The City
currently pays $48,000 annually to the City of Fort Worth for use of the Fort
Worth system. That amount would be reduced to $24,000 and paid to the
Northeast Tarrant County Consortium after joining. These funds are currently
recorded in the Crime Control Prevention District Capital Improvement Plan
fund.
Citizen Input/
Board Review: None
Legal Review: They City Attorney will review and approve the final agreement with the
Northeast Tarrant County Consortium.
Alternatives: Deny funding of the strategic radio plan and staff will continue to explore
measures to improve the safety and operational function of its current radio
system.
Supporting
Documents: "City of Southlake, Texas Strategic Plan — Public Safety Radio Systems"
Report from the Trott Communications Group.
Staff
Recommendation: Staff recommends approving the funding of the strategic radio plan as
submitted.
6A- 2
SOUTHLAKE CRIME CONTROL AND PREVENTION DISTRICT
1/2% SALES TAX REPORT
2002-03 Collected Budget Balance
Budget to Date Balance Percent
$ 2,180,696 $ 365,570 1,815,126 83.24%
-8.50%
7A- 1
ar
Percent
Fiscal Year
Percent
Fiscal Year
Percent
Increase/
2001-02
Increase/
2002-03
Increase/
MONTH
N
(Decrease)
Actual
(Decrease)
Actual
(Decrease)
October
886
26.10%
$192,022
21.62%
$180,396
-6.05%
November373
75.79%
190,845
17.53%
185,174
-2.97%
December
237,687
132.29%
281,020
18.23%
-
-100.00%
January
157,640
16.24%
159,364
1.09%
-
-100.00%
February
147,534
49.43%
158,580
7.49°x6
-
-100.00%
March
206,912
115.86%
210,042
1.51%
-
-100.00%
April
185,555
34.76%
201,261
8.46%
-
-100.00%
May
213,711
68.82%
196,725
-7.95%
-
-100.00%
June
223,490
84.54%
224,631
0.51%
-
-100.00%
July
190,151
20.40%
190,257
0.06°x6
-
-100.00%
August
180,172
48.86%
181,522
0.75%
-
-100.00°x6
September
199,217
62.63%
216,716
8.78%
-
-100.00%
$2,262,328
$2,402,985
$365,570
TOTAL
Three Year Revenue Comparison
by Month
300000-
00000250000200000
250000-
200000
150000
100000
50000
0
�AN �(y \g 0� �n� ^qP
■ Fiscal Year 2000 01 Actual ■Fiscal
Year 2001-02 Actual ❑Fiscal
Year 2002-03 Actual
Actual
Budget
Actual
Estimated
(budget -est.) %
2001-02
2002-03
2002-03
2001-02
Difference
Change
October $
192,022
174,259
180,396
180,396
$ 6,137
3.20%
November
190,845
173,191
185,174
185,174
11,983
6.28%
December
281,020
255,024
-
255,024
-
0.00%
January
159,364
144,622
-
144,622
-
0.00%
February
158,580
143,910
-
143,910
-
0.00%
March
210,042
190,612
-
190,612
-
0.00%
April
201,261
182,643 -
182,643
-
0.00%
May
196,725 178,527 -
178,527 -
0.00%
June
224,631
203,851
-
203,851
-
000%
July
190,257 172,657 -
172,657 -
0.00%
August
181,522 164,730 -
164,730 -
0.00%
September
216,716 196,669 -
196,669 -
0.00%
TOTAL
$2,402,985 $ 2,180,696 $ 365,570 $ 2,198,816 $ 18,120
-8.50%
7A- 1
SOUTHLAKE CRIME CONTROL AND PREVENTION DISTRICT
1/2% SALES TAX REPORT
2002-03 Collected Budget Balance
Budget to Date Balance Percent
$ 2,180,696 $ 1,201,634 979,062 44.90%
Fiscal Year
Percent
Fiscal Year
Percent
Fiscal Year
Percent
2000-01
Increase/
2001-02
Increase/
2002-03
Increase/
MONTH
Actual
(Decrease)
Actual
(Decrease)
Actual
(Decrease)
October
$157,886
26.10%
$192,022
21.62%
$180,396
-6.05%
November
162,373
75.79%
190,845
17.53%
185,174
-2.97%
December
237,687
132.29%
281,020
18.23%
283,333
0.82%
January
157,640
16.24%
159,364
1.09%
176,353
10.66%
February
147,534
49.43%
158,580
7.49%
156,983
-1.01%
March
206,912
115.86%
210,042
1.51%
219,395
4.45%
April
185,555
34.76%
201,261
8.46%
-
-100.00%
May
213,711
68.82%
196,725
-7.95%
-
-100.00%
June
223,490
84.54%
224,631
0.51%
-
-100.00%
July
190,151
20.40%
190,257
0.06%
-
-100.00%
August
180,172
48.86%
181,522
0.75%
-
-100.00%
September
199,217
62.63%
216,716
8.78%
-
-100.00%
$2,262,328
$2,402,985
$1,201,634
TOTAL
_
Three Year Revenue Comparison
by Month
$300,000 T
I
$250,000
$200,000
$150,000
j
$100,000
$50,000
$0
0
dly
V0 eCa� S:p �o
Oq 1 °0
Fiscal Year 2000-01
Actual ■ Fiscal
Year 2001-02 Actual 0 Fiscal Year 2002-03 Actual J
Actual
Budget
Actual
Estimated
(budget -est.)
%
2001-02
2002-03
2002-03
2001-02
Difference
Chan e
October
$ 192,022
174,259
180,396
180,396
$ 6,137
3.20%
November
190,845
173,191
185,174
185,174
11,983
6.28%
December
281,020
255,024
283,333
283,333
28,309
10.07%
January
159,364
144,622
176,353
176,353
31,731
19.91%
February
158,580
143,910
156,983
156,983
13,073
8.24%
March
210,042
190,612
219,395
219,395
28,783
13.70%
April
201,261
182,643
-
182,643
-
0.00%
May
196,725
178,527
-
178,527
-
0.00%
June
224,631
203,851
-
203,851
-
0.00%
July
190,257
172,657
-
172,657
-
0.00%
August
181,522
164,730
-
164,730
-
0.00%
September 216,716
196,669
-
196,669
-
0.00%
TOTAL $2,402,985
$ 2,180,696
$ 1,201,634
$ 2,300,712
$ 120,016
ent of Southlake DPS Phone 817 481 2421
Southlake Vc
�r}� 667 N. Carroll Fax 817 481 2529
�"" �' - • Southlake, Texas 76092
Public Safety
• •� A �AL • • ►-�
Improving Emergency Service Delivery without
Increasing Direct Cost to Residents.
Overall Concept
The long term Strategic Plan for the Southlake Department of Public Safety anticipates a
community build -out of approximately 33,000 residents and a daytime working population
between 50,000 to 60,000. While no one can accurately predict the future, other cities of
our size and population require police staffing of 80 to 120 depending on the crime rate
and the financial condition of the city. In order to meet Fire Services standards of
coverage, a minimum of three strategically located stations are required. Emergency
medical services coverage varies depending on the risks present and the age of the
population. Three EMS medic units will probably be all that is ever required for this city.
These factors are the basis of the Crime Control and Prevention District Board's planning
efforts.
The North Facility is conceptually planned as a Department of Public Safety headquarters,
housing DPS Administration, police and fire operations and other critical functions such as
the holding facility, emergency dispatch center, emergency operations center, and police
criminal investigations.
The current DPS facility, located at 667 N. Carroll, was built in 1956 and is woefully
inadequate in both space and layout. The current size and design prevents optimum
performance from the employees of the department. The antiquated holding facility and
lack of a secure juvenile holding facility continues to be of high concern. While it was
constructed well for the period when it was built, it was constructed in stages spanning
many years. Fire Operations continues to operate in very cramped quarters making quick
turnout time (responding out of the station) difficult. Current operations of both Police and
Fire Services are hindered by the design.
DPS Administration
DPS Administration consists of nine personnel who provide leadership and support to the entire
department of public safety consisting of police services, fire services, building services and support
services.
The Director of Public Safety is responsible for the overall leadership, direction and operation of public
safety (police, fire, buildings and support divisions).
The Chief of Police Services, Chief of Fire Services and Chief of Administrative Services serve as
deputy directors and are responsible for the management and operations within their respective
divisions.
The DPS Administrative Secretary, Records and Budget Administrator and Office assistant provides
the overall administrative and clerical assistance needed by the department of public safety.
The Professional Standards Coordinator is responsible for the oversight of accreditation standards,
hiring/promotional processes and internal affairs investigations within the Southlake Department of
Public Safety.
The Training Coordinator is responsible for the training, education, career development and
maintenance of licenses/certifications for all personnel in the Department of Public Safety.
Current offices for eight of these staff members are in the building at 667 N. Carroll. Direct access by
the Director of Public Safety to the Deputy Director's is hindered by building design. Direct access by
the Chief of Police and Chief of Fire to their operational managers is hindered by building design. The
one conference room available currently doubles as a police patrol briefing room and a conference
(meeting) room. Anytime a meeting is conducted with outside personnel, effort is required to "remove
from view" the confidential police information on the bulletin boards used by officers during briefing
time. All of the DPS Administrative staff at 667 N. Carroll will move to the north facility and an efficient
administrative office layout will be designed including easy citizen access.
Police Operations
Police Operations currently consist of Field Operations and Investigations. Field Operations includes
patrol and traffic as well as the animal control function. The patrol function currently operates out of 667
N. Carroll. Police Officers meet here for briefing before each shift, get their vehicles and equipment,
and operate out of the facility all day. While most of their time is spent in the field, each of the three
facilities provided a significant support function to the officers in their districts. This includes a report
writing area, weapons and equipment storage, access to reports, forms and publications for
distribution, a training area, and locker room.
Our current facility has a closet in the kitchen for weapons storage, a locked cabinet in the public
hallway for ammunition storage, a 12 x 16 room in the metal shed out back as a male locker room for
42 officers, and female lockers are in the upstairs hallway with access to a restroom for changing.
There are additional critical needs for secure areas such as an armory for storage and repair of
weapons, room for storage of uniforms and equipment, and a radio storage room.
Patrol Supervisors consist of a Field Operations Lieutenant, four Sergeants, and four Corporals. These
supervisors need office space for proper administration of their responsibilities. Currently the four patrol
Sergeants and four Corporals share an office. While few of these supervisors are on duty at any one
time, some level of privacy is needed when reviewing or counseling a subordinate officer regarding
their performance or conducting internal investigations.
Traffic officers currently operates out of the West Facility. Traffic currently has one Sergeant, one
Corporal, and seven motor officers. The current area for motorcycle storage at the West facility is
sufficient for eight motorcycles while still leaving room for proper use of the DWI operations.
A critical need for the North Facility is related to the Criminal Investigations Section. Criminal
Investigations currently has four detectives housed in a 12 x 20 room on the second floor at 667 N.
Carroll. Many times these detectives are on the telephone at the same time and the close quarters
reduce their efficiency. There are no adequate interview rooms or storage space for crime scene
equipment or supplies. The room currently used for interviews of victims, witnesses and suspects is
also the CID library, file room, fax room, and non -secure juvenile holding room. To adequately perform
Criminal Investigations today, several additional interview rooms for victims or suspects, as well as
office and storage space is needed.
An additional critical need for the North Facility is related to the holding facility. The current facility
consists of a three cell holding facility with two bunks in each cell. It was built for a much smaller city
and at a time when State jail standards did not exist as they do today. While cameras and speakers
have been added to monitor the prisoners, officers must still make routine checks of the jail frequently.
There is inadequate space to properly process and segregate prisoners and on several occasions
surrounding agencies have been used for emergency jail space. We have recently implemented jail
capacity management plans which prohibit arrests on Southlake warrants and not confirming Southlake
warrants when the holding facility is at capacity. Clearly, the city is in need of a larger and more
manageable holding facility.
A related issue is the lack of any secure juvenile holding area. By State law, juveniles must be
separated from adult prisoners by sight and sound. That means they have to have separate entrance
and exits, separate holding areas, and cannot come into contact with adult prisoners. We currently
have no secure facility for juveniles and if they are arrested for criminal offenses, they must remain
handcuffed and in the presence of an officer for up to six hours before they are transported to the
3
Juvenile Detention facility in Fort Worth. A secure juvenile holding facility is planned for the north facility
to more effectively meet the requirements of state law.
The Property Room is managed in the Criminal Investigation Division. The east facility property room is
extremely small. This system requires the Property Officer to leave the building frequently to drive to
the West Facility to obtain property for release, transfer, or disposal. An additional property room with
an area for property release to citizens is planned for the North Facility. The Property Officer
(Operational Services Assistant) will move to the North Facility when completed.
4
Fire Operations
Fire operations currently consists of fire suppression and fire prevention. Fire suppression, personnel
includes firefighter/paramedics who respond to all emergencies within the city. Personnel are currently
housed at the east and west facility. A minimum of eight firefighters are available in the city for 24 hour
emergency response. Fire Prevention includes a Fire Marshal and a Fire Inspector. These personnel
are housed at the east Facility, in the same office.
One paramedic engine and one ambulance work out of the east Facility and one paramedic engine
runs out of the west facility. A backup ambulance unit is housed at the west facility and is operated
when staffing permits. Most areas of the City, with the exception of the far north, are within the five-
minute response time travel distance from the two existing stations. An additional station at the North
Facility will place over 95% of the city within that response time distance. Currently the vast majority of
fire and EMS calls are from areas along 1709 allowing a quick response from the current facilities.
Construction plans for the North Facility includes a fire and EMS operation however, current demands
in that area is small. As Highway 114 is completed and new residential and business development
emerges, this demand will grow to our North. Because of the cost savings in simultaneous
construction, the fire and EMS facility components should be constructed as part of the north facility for
future use. As demand increases over future years and as the City is able to support the additional
operational cost, a Paramedic Engine can be added to provide both fire and Advanced Life Support to
the north end of the City. An additional ambulance could be added even later when the demand
justifies its expense.
5
Training and Community Room
At least one classroom/community room is currently planned for the north facility. While the Training
Coordinator offices at the West Facility, there is a need for training facilities at every station. These
rooms are necessary to provide on-site in-service training for personnel assigned to that station. It also
allows for the use of the facility by members of the community for meeting and other activities.
Police Services currently rents the DFW Airport Firearms Training Center for at least two days each
quarter and hourly at other times to keep all personnel adequately trained and qualified with their
firearms. This rental typically exceeds $9,000 per year. Consideration is being given to including
underground, open-air firearms training center on site for officer's use. Not only would this eliminate the
rental but also would reduce the overtime and lost time wasted by officers going to and from the DFW
range. There is also the possibility of income from the rental of the range to other local agencies when
we are not using it.
Also under consideration is a police vehicle driving track to provide officers with necessary driving skills
training on a more regular basis. Currently officers are assigned to the EVOC (Emergency Vehicle
Operations Course) every three years. Because of the lack of facilities the regional EVOC training
classes are usually delayed and attendance restricted. Having a driving track would allow more
extensive and more frequent training in this critical area of job performance. The same track would
also be used by fire services in training on their equipment.
Fire Services is also in need of an on-site training facility. The building of a tower and fire simulation
facility would greatly improve the preparedness of our Fire Services staff.
6
Emergency Operations Center.
The City of Southlake currently has no Emergency Operations Center designed to run the city in the
event of a major disaster. The East Facility training room (old Council Chambers) has been wired to
work as a makeshift EOC should the need arise. The age of the building as well as the non -reinforced
glass at one end of the room makes this location vulnerable to natural disasters. The necessary
equipment for the operation of this facility must be physically brought into the EOC each time it is
activated.
A new "hardened" EOC would be constructed at the north facility. No personnel are permanently
assigned to this area but representatives from all City and utility companies assign personnel when an
emergency occurs.
r
Emergency 911 (Communications) Call
-- Center
DPS has just completed the electronic upgrading of the current 911 Call Center at 667 N. Carroll.
While it is electronically efficient, it is still housed in an antiquated facility that detracts for efficient
operation and safety. Typically there are two or three Communicators on duty at all times and noise
levels from within the room often make hearing the radio or 911 calls difficult. The dark and cramped
offices have a negative impact on employees and hinder efficient operations.
A new "hardened" 911 Call Center would be constructed in the North Facility. The construction method
used in this area would be modular to allow easy interior redesign. In this manner the area would
continue to serve this community through the next century. There are currently 12 Communicators and
one Communications Supervisor assigned to the 911 Call Center. All of these personnel would move
to the North Facility and the current 911 Call Center would be abandoned.
8
Cost Implications
While funding for the construction of the North Facility is provided by the Crime Control and Prevention
District, the operation of the facility and personnel assigned there comes from the City of Southlake
General Fund.
While the North Facility is planned to be a larger facility than the current property on N. Carroll, the
current headquarters is expensive to maintain. The facility, in addition to being inadequate for optimum
operations, is old and in need of frequent expensive HVAC, electrical, and plumbing repairs. Building
the North Facility, while larger, will include significant energy conservation measures not present in the
current facility. In addition it will eliminate the monthly rental of storage space for records and possibly
reduce the training costs associated with the DFW Firearms center.
The matrix, on page 10, illustrates how personnel will be assigned to the facility. With the exception of
one detention officer needed to ensure proper operation of the holding facility, no additional personnel
are needed at the time the facility opens. As the holding facility population increases, there will be a
need for dedicated staff to monitor that operation and the prisoners. Staffing of this detention position is
needed now and is independent of the actual opening of the North Facility. Firefighters needed to staff
the additional Paramedic Engine and Medic Unit are not needed until the demand increases and the
City is in a financial position to fill the need.
10
Summary
The Crime Control and Prevention District has adopted a CIP that approves the funding for the
construction of this facility in FY 2004-2005. Opening of this facility is scheduled for January, 2006. At
that time, the general fund would become responsible for the maintenance cost of that facility.
Currently, the general fund is not capable of supporting the additional firefighter/paramedics
Clearly the City of Southlake General Fund budget will not support the addition of fire or EMS services
personnel for this facility over the next couple of years. However, the DPS Administrative and Support
personnel as well as the Police Services personnel planned for this facility already exist and currently
office at the current East Facility. The only exception is the need for at least one jailer position which is
needed regardless of the opening of the North Facility to ensure proper operation and maintenance of
the holding facility.
Critical needs exist within both Police and Support operations for a new facility as soon as possible. Ar
updated holding facility, interview and interrogation facilities, proper and secure storage for both
property and critical response equipment, and workable office space for the 911 Call Center and Police
Criminal Investigations is needed today. An Emergency Operations Center would also be built into the
facility to ensure continuous operation of the city government during an emergency. Improvements in
these facilities are needed now to reduce liability and improve operational effectiveness.
Given the Crime Control District budget projections, a DPS North Facility can be constructed today,
including the necessary fire and EMS operational portions of the building. Building all portions of the
facility at once will allow the city to take advantage of cost savings. Staff from the current East Facility
and DPS administration personnel would move their offices to the North Facility thereby enhancing
both productivity, services and reducing the liability existent in the current facility. As the need
increases for additional fire and EMS services and funding becomes available, the fire and EMS
personnel can be added. Such additions can be done gradually as the need dictates.
11