Advance Funding Agreement for the construction of a turnaround bridge at SH 114 and Carroll Blvd.
Advance Funding Agreement SH114 and Carroll Turnaround
East Side Only
MOU - 4 parties
Gateway Church
Cooper and Stebbins
Tarrant County
City of Southlake
Memorandum of UnderstandingSH114 and Carroll Turnaround
Completed
Survey
90% Design
Construction begins Summer 2013
Project Completion – January 2014
Carroll Ave
SH 114
Memorandum of UnderstandingSH114 and Carroll TurnaroundProject Funding
Local Participation-MOU $1,080,000
(Enhanced Aesthetics not incl)
NCTCOG/TxDOT 972,995
Project Total $2,052,995
Advance funding AgreementSH114 and Carroll Turnaround
Project Enhancements
Enhanced bridge rail
Repaint Carroll Avenue Bridge
Match FM 1709 bridge aesthetics
Questions:Bob Price (817) 748-8097