MEMORANDUM
(October 4, 2011)
To: Shana Yelverton, City Manager
From: Robert H. Price, P.E., Director of Public Works
Subject: Approve contract with Weatherproofing Technologies, Inc. for
Phase 3 waterproofing the exterior of Town Hall in the amount
of $111,694
Action
Requested: Approve contract with Weatherproofing Technologies, Inc. for
Phase 3 waterproofing the exterior of Town Hall in the amount of
$111,694
Background
Information: Since the construction of the Town Hall building in 1999 very little
maintenance to the exterior of the building has taken place prior to
this initiative. Because, rain events of varying intensities have
caused water damage to interior ceilings and walls on all sides of
the building, the first phase of this project was initiated in fiscal year
2011. The leaks are primarily due to crevices that have developed
around the window frames and joints between the brick and
masonry stones. Much of the original sealant and grout has
hardened and is no longer an effective water barrier. The products
available today are superior to those used in the original
construction and should withstand exposure to the elements and
provide greater flexibility and resistance to thermal expansion.
During fiscal year 2011 and 2012, the first two phases of the
weatherproofing project addressed the north and south elevations
of the building including the steps and handrails. Phase 3 of the
waterproofing project will address the same issues on the east and
west sides of the building completing the project. In order to
complete this work, scaffolding may have to be set up on the east
and west sides of the building in order to reach many of the
problem areas which need to be addressed. The work is planned
to begin in March and will take six to eight weeks to complete.
Phase three of the project will cost $111,694. The City of
Southlake is eligible to award this project to Weatherproofing
Technologies, Inc. through the Texas Cooperative Purchasing
Network (RFP# R5101).
Financial
Considerations: Funding for this project is available from the Facilities Infrastructure
Maintenance Fund in the amount of $114,000.
Strategic Link: The award of this service contract links to the city strategy map
relative to the focus area of Infrastructure. The specific corporate
objective is investing to provide high quality public assets.
Citizen Input/
Board Review: N/A
Legal Review: None
Alternatives: The City Council may approve or deny the agreement to provide
waterproofing services for Town Hall.
Supporting
Documents: Proposal from Weatherproofing Technologies, Inc.
Staff
Recommendation: Approve contract with Weatherproofing Technologies, Inc. for
Phase 3 waterproofing the exterior of Town Hall in the amount of
$111,694
Staff Contact: Robert H. Price, P.E., Public Works Director
Chuck Kendrick, Deputy Director of Public Works — Operations
Kurt Ackerman, Facility Services Manager
After W
This photo of the south-west corner of the building illustrates the difference in the appearance of
the cast stones before and after the project. The right side of the photo (south elevation) has
recently been cleaned, pressure -washed and sealed to prevent water penetration and mildew
formation. The left side of the photo (west elevation) has not been cleaned and sealed.
VWfi
Weatherproofing Technologies, Inc.
16902 El Camino Real, Suite 4C, Houston, TX 77058 • 281-480-7900
November 13, 2012
Kurt Ackermann
Facilities Manager
City of Southlake
600 State Street 92010
Southlake, Texas 76092
RE: Town Center East & West Elevations, building Facade repair works project.
I am providing you with a cost proposal for the following scope of work. This proposal is
performed under our TCPN #R5101 contract which complies with the state bid procurement
laws and we have invited multiple local subcontractors to bid on various disciplines of the
scope of work. Our proposal includes all supervision, labor, materials and equipment for
removal, furnishing, and installing of all necessary construction components as needed to
complete the following statement of work.
Statement of Work:
1. General Conditions:
a. Construction shall be limited to the perimeter set forth in the scope of work, for the
East and West side elevations.
b. Precautions will be taken to protect all existing surfaces to include walls, doors and
windows to construction area and building area.
c. All work to be performed in accordance with all OSHA rules and regulations.
d. Daily safety inspections will be performed.
e. Daily and final clean-up shall be provided.
2. Detailed Scone of Work:
Setup Safety equipment and staging area
Window Perimeters (frame to masonrv)
- Remove existing sealant
- Clean and prepare surface
- Apply silicone sealant per manufacturer's specification (approximately 2600 LF)
Brick and Precast Stone (includine conina)
- Power washes to remove dust, dirt and loose mortar
- Tuck point voids and cracks with color blended non -shrinking mortar
- Apply silicone sealant where precast stone meets brick (where necessary)
(approximately 6000 LF)
An " . Company
VWfi
Weatherproofing Technologies, Inc.
16902 El Camino Real, Suite 4C, Houston, TX 77058 • 281-480-7900
- Apply penetrating sealer at all masonry surfaces per manufacturer's specification
(approximately 12000 sq ft)
CLARIFICATION:
1.1 WTI Services, Inc. assumes no responsibility for the possibility of, or the
presence of mold and /or mildew resulting from water entry and/or other
sources. This includes any contamination prior to or after work is completed by
WTI Services, Inc.
1.2 Contractor shall have full access to area to complete the project.
1.3 Proposal includes regular business hours for working (no overtime included).
Total Proposal Price -------------------------------------------------- $ 111,693.38
Thank you for the opportunity to earn your business. We look forward to serving the City of
Grapevine on this and future projects.
Sincerely,
Douglas R Ng -14
WTI, Inc
Construction Manager