Item 6FCITY 01
SOUTHLAKE
Department of Planning & Development Services
STAFF REPORT
November 28, 2012
CASE NO: ZAl2 -096
PROJECT: Site Plan for Verizon Wireless Expansion
EXECUTIVE
SUMMARY: On behalf of Verizon Wireless, Halff Associates, Inc. is requesting approval of a Site
Plan for an expansion of the existing facility on property located at 500 W. Dove Rd.
and described as Lot 1, Block 1, Solana Addition, an addition to the City of Southlake,
Tarrant County, Texas. SPIN # 1.
REQUEST DETAILS: The applicant is requesting approval of a site plan for a Verizon Wireless expansion to
add a two - phase, two -story expansion with approximately 5,800 square feet of floor
area on each floor and an approximately 6,500 square foot service yard. The ground
floor (one- story) Phase 1 expansion will house a redundant chilled water plant. The
Phase 2 second -story is labeled as unassigned shell space. A backup generator and
four air - cooled chillers will be contained within the service yard adjacent to the building
expansion. Since the expansion area will not house additional employees, no
additional parking is proposed with this expansion. The original concept plan for
Verizon approved in 2001 showed a three -story parking garage in the area of the
proposed expansion, but since expansion areas that were planned for administrative
space are being developed as mechanical and electrical infrastructure, a parking
garage is not needed or planned at this time.
To address concerns about the chain link fence that was originally proposed around
the service yard, the Planning and Zoning Commission added a condition in their
recommendation for approval to replace the chain link fence with a wrought iron fence.
Revised renderings showing the wrought iron fence have been provided by the
applicant.
ACTION NEEDED: 1) Conduct a public hearing
2) Consider approval of a site plan
ATTACHMENTS: (A)
(B)
(C)
(D)
(E)
(F)
Background Information
Vicinity Map
Plans and Support Information — Link to PowerPoint Presentation
Site Plan Review Summary No. 3, dated November 27, 2012
Surrounding Property Owners Map and Responses
Full Size Plans (for Commission and Council Members Only)
Case No.
ZAl2 -096
STAFF CONTACT: Ken Baker (817)748 -8067
Richard Schell (817)748 -8602
Case No.
ZAl2 -096
BACKGROUND INFORMATION
ITA
/e1 »I[91e1►1116
PROPERTY ADDRESS:
Verizon Wireless
Halff Associates, Inc.
500 W. Dove Rd.
PROPERTY DESCRIPTION: Lot 1, Block 1, Solana Addition
LAND USE CATEGORY: Mixed Use
CURRENT ZONING: "NRPUD" Non - residential Planned Unit Development District
HISTORY: - A Rezoning and Concept Plan for Solana (Non - residential) to "NR -PUD" Non -
Residential Planned Unit Development with "C -3" General Commercial District,
"0-2" Office District, "HC" Hotel District, and "CS" Community Service District
uses was approved by City Council on October 17, 1995.
- A site plan (ZA01 -056) was approved by City Council on June 14, 2001.
- A preliminary plat (ZA01 -058) for Lots 1 and 2, Block 1, Solana Addition was
approved by City Council on June 14, 2001.
- A final plat (ZA01 -059) for Lot 1, Block 1, Solana Addition was approved June
14, 2001.
- A site plan (ZA11 -050) to add an approximately 56,529 square foot two -story
expansion to the existing Verizon Wireless facility for increased network space
and area for infrastructure and a service yard surrounded by a twenty (20) foot
wall adjacent to the expansion was approved November 15, 2011.
Construction is underway on this expansion.
PATHWAYS PLAN: Southlake's Pathway System Master Plan shows a planned ten (10) foot
multiuse trail adjacent to the S.H. 114 frontage and an existing eight (8) foot
trail adjacent to west Dove Rd. When the site plan for Verizon Wireless was
approved in June of 2001, the Council motion stipulated that if the ten (10) foot
trail along SH 114 was constructed within ten years, the applicant would pay
their pro -rata share of the construction.
TREE PRESERVATION: Five (5) existing trees are proposed to be removed for the expansion. One of
the Post Oaks that is proposed to be removed is in decline and does not
require mitigation. The four trees to be mitigated total 39 caliper inches. Seven
(7) 4" caliper Live Oaks and three (3) 4" caliper Bald Cypress trees totaling
forty (40) caliper inches are shown as mitigation trees on the Overall
Landscape Plan.
CITIZEN INPUT/
BOARD REVIEW: A SPIN Meeting for this project was held for November 5, 2012. The SPIN
Report is attached as Attachment D of this report.
PLANNING AND ZONING
COMMISSION ACTION: November 8, 2012; Approved (7 -0) subject to Site Plan Review Summary No. 2
dated November 2 nd and Staff Report dated November 2 noting the
applicant's willingness to conduct a sound study prior to permitting, noting the
applicant's willingness to replace the shrubs and trees that have been
impacted during construction of the other phase and also the shrubs and trees
Case No. Attachment A
ZAl2 -096 Page 1
that will be impacted by this construction and also noting the applicant's
willingness to construct a wrought iron fence as opposed to a hurricane fence
around the chillers.
STAFF COMMENTS: Attached is Site Plan Review Summary No. 3, dated November 27, 2012.
Case No. Attachment A
ZAl2 -096 Page 2
Vicinity Map
Verizon Wireless
0
9-
G
SH 114
1111.
N
ZAl2 -096
Site Plan
500 W. Dove Rd.
T _E
0 550 1,100 2,200
s Feet
Case No. Attachment B
ZAl2 -096 Page 1
IkilVANVli %Iky /;a4AaIN1V
WFW
■ Wick Fisher White
• E.C. Bruce Ernst, P.E.
President
November 1,2012
• Vice Presidents
expansion to be a very large 3 -story parking garage, refer to the original concept
Christopher C. Arnold, P.E.
City of Southlake
Patrick C. Chan, P.E.
Department of Planning and Development
Anthonv M. Dil.eonardo,
P g
P
LEED AP, CxA
1400 Main Street - Suite 310
Stephen P- white, P.E.
Southlake, TX 76092
LEED AP
A 2N chilled water plant expansion is planned to the northwest side of the
z
• Associates
RE:
Verizon Wireless
Matthew T. Cofone, P.E.
lower floor level will be flush with the ground floor of the existing facility. The
500 West Dove Road
CEM. LEED AP, CBIE
z
building will be built in two phases.. Phase 1 will be constructed first and with
Baice O. Gessner
phase two being constructed at a later date.
2N Chiller Plant- Development Plan
E. Daniel Jewell, P.E.
Cover Letter and Narrative
Robert A. Knese, P.E.
WFW #1120155
LEED AP
Steven L. Marks, P.E.
Second Revision
Lawrence Myers, P.E.
Jeffrey E. Pills
Chan V. Thai, P.E.
To Whom it May Concern:
Below is a description of the existing building and the proposed building
expansion:
The existing Verizon Wireless (VZW) Southlake facility is located at 500 West
Dove Road in Soutlllake, Texas. It is primarily a 2 -story building with a small a
third story portion which will not be impacted by the proposed work. It is
situated on a 25 acre site, bounded by State Highway 114 to the west, West Dove
Road to the south, Kirkwood Boulevard to the east, and a neighboring property to
the north.
The original planned expansion concept in 2001 was for this break wing
expansion to be a very large 3 -story parking garage, refer to the original concept
plans included. The scope has changed and VZW is now proposing a small
expansion for equipment to support a redundant chiller plant. The original plan
for the building was to add more administrative areas. Due to VZWs growth and
c n
need for equipment to support that growth, telecom equipment, and mechanical
P4
and electrical infrastructure are required. There is additional parking planned in
the future, but not a garage at this time.
W
W
A 2N chilled water plant expansion is planned to the northwest side of the
z
expansion, extending from the existing break room wing at the ground floor. The
expansion will be a 2 -story expansion with for 5,800 sgfteach floor. The
~
lower floor level will be flush with the ground floor of the existing facility. The
C7
upper level will be level with the existing first floor break room area. The
z
building will be built in two phases.. Phase 1 will be constructed first and with
W
phase two being constructed at a later date.
111 South Independence Mall East ■ Suite 400 • Philadelphia, PA 19106 • 215- 627 -0200 ■ 215- 627 -8240 fax ■ www.wfweng.com
Case No. Attachment C
ZAl2 -096 Page 1
WFW
■ Wick Fisher White
City of Southlake
Department of Planning and Development
RE: Verizon Wireless
500 West Dove Road
2N Chiller Plant- Development Plan
Cover Letter and Narrative
WFW #120155 -2- November 1, 2012
Second Revision
A backup generator and four air- cooled chillers will be within a new mechanical
yard to the northwest of the expansion.
New spaces in the expansion will include space for an air handling unit, chilled
water storage and pumps, electrical rooms, a preaction sprinkler room and a
service area with an overhead door to the exterior. Interior connection to the
existing ground floor will be via. a double door into the existing Site Maintenance
Room.
The existing site is zoned NR -PUD (non- residential planned unit development)
with C -3, 0-2, HC and CS (general commercial, office, hotel and community
service) designations also. The design conforms to all zoning and site
requirements.
Site access is via West Dove Road and Kirkwood Boulevard. Existing parking is
provided primarily to the south side of the site. At this time parking required for
the expansion will be provided on -site in an expanded parking area being built
under the scope of the Data Center Expansion Wing project. The design team
will continue to assess the parking needs of this project in subsequent design
phases. The perimeter of the property is open with landscaping throughout. The
expansion will continue the design strategy set by the existing landscape design,
which requires chain -link fencing at mechanical yards as required by VZW
design standards. Chain -link fencing will surround the new mechanical yard
only and will match existing fencing already on site. Several trees will be
removed to make room for the expansion and will be replaced along with any
other landscaping required per the City of Southlake. The landscaping design
will continue to be developed in subsequent phases.
Underground site utilities are in the vicinity of the expansion to the southwest
and will need to be protected during construction. Any asphalt paved areas and
disturbed landscaping will all be restored to match existing conditions.
Case No. Attachment C
ZAl2 -096 Page 2
WFW
■ Wick Fisher White
City of Southlake
Department of Planning and Development
RE: Verizon Wireless
500 West Dove Road
2N Chiller Plant- Development Plan
Cover Letter and Narrative
WFW #120155 -3- November 1, 2012
Second Revision
General Building g escriptions
Applicable Codes in addition to the VZW Standards governing the proposed
work include:
• Building Code: 2009 IBC
• Electrical Code: 2008 NEC
• Mechanical Code: 2009 IMC
• Plumbing Code: 2009 IPC
• Energy Conservation Code: 2009 IECC
• Fire Code: 2009 IFC
The existing structure is constructed as a type IIB building, consisting of a tilt -up
concrete wall panel system with metal deck with concrete fill supported by an
unprotected steel beam and column system. The structural aspects of the
proposed addition are covered in the Structural Basis of Design. The interior is
constructed entirely of non - combustible 1 -hour construction, 518" Type - "X"
gypsum wallboard (GWB) over metal stud construction. The interface between
the proposed and existing construction will be separated by a 2" expansion joint,
structurally separating them. The new addition will be constructed to match the
existing exterior in appearance per VZW architectural standards. The exterior
wall will be 8" CMU with vapor barrier, rigid insulation and a brick veneer to
match the existing facility. Additionally the parapet area will be finished in EIFS
to match existing. The structure will be steel columns and beams. The roof will
be concrete slab on metal deck; this arrangement will allow for a future second
floor to be constructed if the need arises. The interior of the building, including
the underside of the exposed roof deck and structural framing will be painted to
match existing. Where existing exterior wall is to remain, the exposed concrete
panels will be furred and covered with GWB and painted to match the new
interior color scheme.
The new ground floor system will be reinforced concrete slab on grade.
Case No. Attachment C
ZAl2 -096 Page 3
WFW
■ Wick Fisher White
City of Southlake
Department of Planning and Development
RE: Verizon Wireless
500 West Dove Road
2N Chiller Plant- Development Plan
Cover Letter and Narrative
WFW #120155 -4-
Second Revision
November 1, 2012
Minimal work will occur within the existing building. A door will be provided to
communicate between the expansion and existing Site Maintenance Area. This
door will be for convenience only- all egress and exiting requirements are
provided in the expansion design. Additionally, the expansion does not change
egress or exiting from the existing facility. The new door assembly will meet
current VZW fire rating requirements and all wall penetrations will be
firestopped per current VZW and Code Standards.
Space Allocation by Room
First Level
Electrical Room A
668 SF
Electrical Room B
85 SF
Electrical Room C
90 SF
Preaction Room
204 SF
Chilled Water Plant
4.327 SF
Phase 1 Total
5,374 SF
Second Level
Space to be determined 5800 SF
If you have any questions in reference to the above, or need additional
information, please feel free to call.
Very truly yours,
AMD:rw
WICK FISHER WHITE
Anthony M. DiLeonardo
Case No. Attachment C
ZAl2 -096 Page 4
SITE PLAN
VICpNTV MAP - N,TS.
N ',
's
PROPOSED °
EXPANSION ,
FF
r
E�
0
0
t
°
�xao\�1
STOCKTON
DRIVE
BENGHMF
Case No.
ZAl2 -096
Attachment C
Page 5
USOUTHLAKE
SPIN MEETING REPORT
CASE NO. ZAl2 -096
PROJECT NAME:
SPIN DISTRICT:
MEETING DATE:
MEETING LOCATION
Verizon Wireless Expansion
SPIN # 1
November 4, 2012; 7:00 PM
1400 Main Street, Southlake, TX
Training Rooms 3C — 3D
TOTAL ATTENDANCE: Ten (10)
• SPIN REPRESENTATIVE(S) PRESENT: Rob Baker #1
• APPLICANT(S) PRESENTING: Wick Fisher White, Jacobs Wyper, et al (5)
• STAFF PRESENT: Caroline Eckel, Planner I
STAFF CONTACT: Richard Schell, Planner II: (817)748 -8602 or rschelI(Q -6. south lake.tx.us
EXECUTIVE SUMMARY
Property Situation
• The Verizon Campus is located at 500 W. Dove Road, bordered by S.H. 114 to the west
and Kirkwood Blvd. to the east.
Development Details
• Site Plan proposed for a two- phase, two -story Verizon Wireless expansion with
approximately 5,380 square feet of floor area on each floor and an approximately 6,500
square foot service yard.
• Phase I of the expansion will be for equipment storage. Phase II would happen at a later
date, and is currently undesignated space. It could house additional equipment or be
used for administration. No additional parking required.
The plan presented at SPIN:
Phase I
Case No. Attachment D
ZAl2 -096 Page 1
Phase II
QUESTIONS / CONCERNS
• Can you see it from S. H. 114?
Phase I, no. You would only see the top of the parapet of the existing building.
Phase II, you may see the top of the parapet.
• Will the expansion add to the noise level?
This expansion should not add any additional noise, beyond the current noise
level. The added generators in this area are part of a redundant system, so they
will not run all of the time. They will be exercised once a month.
• With the current expansion under way, there are already additions to the building with
new generators, and now you're adding more generators? I am concerned that the noise
will increase.
This is a redundant system, exercised monthly, and only running when the other
system is down. We will conduct a sound study.
• Another developer is proposing a residential development on the property north of the
Verizon Campus, Williamsburg Estates. The backyards of those homes may face this
new expansion.
c We will coordinate with that developer.
• Although the expansion is not visible from the road, we would prefer anything other than
chain link fencing.
It is tucked behind the building, and you will never see it.
• The current phase of construction – although it's not part of this proposed project— has
killed trees along the perimeter of the site, and the location of the construction trailers
are awful.
We will report back.
• Once the second story is added during Phase II, will you not see this addition from S.H.
114 or the service road?
c, You may see the top corner of the parapet. Maybe.
Case No. Attachment D
ZAl2 -096 Page 2
• If, in the future, additional development occurs around the property and trees are
removed, will the generators /chain link fence be visible? We don't want for the entrance
to our city to lock industrial.
Very little would be visible. Landscaping on our property buffers the view.
We still don't like the chain link fence. It is not appropriate for our city. We would prefer a
masonry wall for sound abatement.
The proposed chain link fence is matching the existing chain link fencing
currently used on the back side of the property.
Please coordinate with the developer of Williamsburg Estates to the north. We are
concerned about low home values in that area adjacent to S.H. 114, and the view of this
expansion may make those homes more difficult to sell. It is important for us to preserve
property values.
We will coordinate with that developer, conduct a sound study, and look closely
again at our sightlines. We are sure that landscaping on both properties will
provide a buffer.
Since the proposed expansion includes a large space for equipment storage, wil[ this
cause more truck traffic in the area, for deliveries or distribution?
No, the equipment is for use within the building. It is data center equipment.
The current construction yard on the Verizon Campus has been problematic. Where will
the construction yard/staging be for this project?
We would have an open bid for this project. However, it would be convenient if
the group working on the current project could stay. Their construction
trailers /equipment would already be in place and we would not need to set up a
new staging area.
The current construction site has a temporary parking lot, is it planned to become
permanent? This proposed expansion will require no additional parking?
C We believe the current temporary lot is planned to become permanent; additional
parking was planned as part of the originals campus. It is likely needed to
accommodate visitors to the building, but no additional parking will be needed for
this proposed expansion. The proposed space Is being used only to house
equipment.
With all of the construction, and especially with the additional parking becoming
permanent, additional landscaping along Kirkwood Blvd. is important to us. Homes back
up to Kirkwood along the east side of the campus. Additional landscaping and
replacement of trees would help provide a buffer.
The 3 rd Phase of Kirkwood Hollow often experiences power outages, especially during
the summer. We wonder if this neighboring campus drains our power.
We have excellent back -up systems in place which help to prevent us from losing
power. So it may appear that our lights are on when yours are out, but we just
have extensive emergency systems in place.
SPIN Meeting Reports are general observations of SPIN Meetings by City staff and SPIN Representatives. The report is neither verbatim nor official
meeting minutes; rather it serves to inform elected and appointed officials. City staff, and the public of the issues and questions raised by residents and
the general responses made. Responses as summarized in this report should not be taken as guarantees by the applicant. Interested parties are
strongly encouraged to follow the case through the Planning and Zoning Commission and final action by City Council.
Case No. Attachment D
ZAl2 -096 Page 3
SITE PLAN REVIEW SUMMARY
Case No.: ZAl2 -096 Review No.: Three Date of Review: 11/27/12
Project Name: Site Plan — Verizon Wireless Expansion
APPLICANT: Ignacio Herrera
Halff Associates, Inc.
1201 N Bowser Road
Richardson, TX 75081
Phone: (214) 217 -6646
E -mail: iherrera @halff.com
OWNER: Keith Shuda
Verizon Wireless
145 Chubb Way
Brachbura, NJ 08853
CITY STAFF HAS REVIEWED THE ABOVE REFERENCED PROJECT RECEIVED BY THE CITY ON
11/20/12 AND WE OFFER THE FOLLOWING STIPULATIONS. THESE STIPULATIONS ARE HEREBY
MADE CONDITIONS OF SITE PLAN APPROVAL UNLESS SPECIFICALLY AMENDED BY THE CITY
COUNCIL. IF YOU HAVE ANY QUESTIONS OR NEED FURTHER CLARIFICATION, PLEASE CONTACT
RICHARD SCHELL AT (817) 748 -8602 OR DENNIS KILLOUGH AT (817) 748 -8072.
Tree Conservation /Landscape Review
Keith Martin
Landscape Administrator
Phone: (817) 748 -8229
E -mail: kmartin @ci.southlake.tx.us
TREE CONSERVATION COMMENTS:
The symbol in the legend on Sheet L1.01 that is labeled as Texas Red Oak 3" caliper is labeled on the
plan as Claudia Wannamaker Magnolias 3" caliper. There are six trees shown. Please change one of
the labels so that the plan matches the legend.
There are five (5) existing trees that are proposed to be removed for the development expansion. One
of the Post Oaks that is proposed to be removed is in decline and does not require mitigation. The four
trees to be mitigated total 39 caliper inches. The ten trees shown to be provided on Sheet L1.00 total
40 caliper inches.
Please be aware that all existing trees shown to be preserved on the City Council approved Tree
Conservation Plan must be preserved and protected during all phases and construction of the
development. Alteration or removal of any of the existing trees shown to be preserved on the approved
Tree Conservation Plan is a violation of the Tree Preservation Ordinance and the zoning as approved
by the Southlake City Council. Please ensure that the layout of all structures, easements, utilities,
structures grading, and any other structure proposed to be constructed do not conflict with existing
trees intended to be preserved.
LANDSCAPE COMMENTS:
The proposed landscaping is compliant. The applicant is proposing to also provide additional
Case No. Attachment E
ZAl2 -096 Page 1
landscaping across the access and in the bufferyard.
All of the required bufferyards and interior landscape plantings were installed during the initial
development of the property. Because the area surrounding the development is primarily turf /pasture,
a lot of the required bufferyard shrubs were placed within the parking area and closer to the building.
# Indicates required items.
Indicates informational staff comments.
Fire Marshal Review
GENERAL COMMENTS:
Automatic fire sprinkler system and fire alarm will be required for addition to existing building.
Submit plans to Reed Fire Protection, 14135 Midway Road, Suite G260, Addison, Texas 75001.
Phone 214 - 638 -7599.
Remote Fire department connection and underground piping must be hydrostatically tested after it
is relocated to a permanent position.
Provide signage for Fire Department Connection.
Provide signage for all electrical rooms and other pertinent areas.
FIRE LANE COMMENTS:
Fire lanes require a minimum 30 foot inside turn radius and a minimum 54 foot outside turn radius.
(per 2009 I.F.C. Sec. 503.2.4)
Dead -end fire lane indicated on prints must be a maximum of 150 feet long.
FIRE HYDRANT COMMENTS:
Fire hydrant locations are satisfactory as shown on the submitted plan.
INFORMATIONAL COMMENTS:
All construction plans to be submitted for a building permit must conform to the edition of the
International Fire Code currently amended and adopted.
Building Inspections Review
Susie Hernandez
Plans Examiner
(817) 748 -8238
Accessibility:
Must meet Texas Accessibility Standards.
Lighting:
Case No. Attachment E
ZAl2 -096 Page 2
Must meet City Lighting Ordinance.
Comments:
A construction trailer for this project may not be allowed based on existing projects on this site and
existing trailers.
Public Works /Engineering Review
Steve Anderson, P.E.
Civil Engineer
Phone: (817) 748 -8101
E -mail: sanderson @ci.southlake.tx.us
Cr7N1 0 1 1N1 VIA lKeT197JiIJiIN1 0 1 111 &'1
No comments.
General Informational Comments:
A SPIN meeting is scheduled for November 5, 2012.
No review of proposed signs is intended with this site plan. A separate building permit is required
prior to construction of any signs.
All mechanical equipment must be screened of view right -of -ways and residential properties in
accordance with the Zoning Ordinance No. 480, as amended.
All lighting must comply with the Lighting Ordinance No. 693, as amended.
All development must comply with the Drainage Ordinance No. 605 and the Erosion and Sediment
Control Ordinance No. 946, as amended.
It appears that this property lies within the 75 LDN D /FW Regional Airport Overlay Zone and will
require construction standards that meet requirements of the Airport Compatible Land Use Zoning
Ordinance No. 479.
Development must comply with all requirements in Zoning Ordinance No. 480, Section 43, Overlay
Zones.
The applicant should be aware that prior to issuance of a building permit a Plat must be processed
and filed in the County Plat Records, a fully corrected site plan, landscape plan, irrigation plan,
and building plans, must be submitted for approval and all required fees must be paid. This may
include but not be limited to the following fees: Park Fee, Perimeter Street Fee, Water & Sewer
Impact and Tap Fees, and related Permit Fees.
Denotes Informational Comment
cc
Case No. Attachment E
ZAl2 -096 Page 3
SURROUNDING PROPERTY OWNERS
Verizon Expansion
19
16
18
17
20
SPO #
1.
Owner
Mesenbrink, Daniel S Etux M L
Zoning
RPUD
Land Use
Medium Density Residential
Acreage
0.67
Response
NR
2
Kirkwood Hollow
Homeowners,Asn
RPUD
Medium Density Residential,
1.17
NR
3
Kirkwood Hollow
Homeowners,Asn
RPUD
Medium Density Residential
0.70
NR
4
Kirkwood Hollow
Homeowners,Asn
RPUD
Medium Density Residential,
0.09
NR
5.
Litwin, Mark S
RPUD
Medium Density Residential
0.51
O
6.
Arison, Joan C Etvir Alan S
RPUD
Medium Density Residential
0.44
NR
7.
Green, Kayle C Etux Tina A
RPUD
Medium Density Residential
0.40
NR
8.
Agualimpia, Juan & M Issacs
RPUD
Medium Density Residential
0.38
NR
9.
Kirkwood Hollow Ho Assoc
RPUD
Medium Density Residential,
0.74
NR
10.
Zhou, Jun Etux Na Li
RPUD
Medium Density Residential
0.38
NR
11.
Bollini, Sashidhar Etux Sesha
RPUD
Medium Density Residential
0.37
NR
12.
Mansoor, Shadan
RPUD
Medium Density Residential
0.40
NR
13.
Kirkwood Hollow Ho Assoc
RPUD
Medium Density Residential,
0.32
NR
14.
Southlake, City Of
RPUD
Medium Density Residential
0.44
NR
15.
Kirkwood Hollow Ho Assoc
RPUD
Medium Density Residential
0.46
NR
16.
Kirkwood Hollow Home Own Ass
RPUD
Medium Density Residential
0.14
NR
17.
Verizon Wireless Texas Llc
NRPUD
Mixed Use
24.86
NR
18
Maguire Ptnrs - Solana Ltd
NRPUD
100 -Year Flood Plain, Mixed
Use
4.19
NR
19
Maguire Prtnrs Solana Holdings
NRPUD
Mixed Use, 100 -Year Flood
Plain
19.99
NR
20.
Dove 114 Infinity Llc
SP2
Mixed Use
54.44
F
Responses: F: In Favor
Case No.
ZAl2 -096
O: Opposed To U: Undecided NR: No Response
Attachment F
Page 1
Notices Sent:
Responses Received
Twenty (20)
Four (4) — Two mail outs and two responses from two owners
Case No. Attachment F
ZAl2 -096 Page 2
IN;&1 11e7►6- -1*arelaI:RIiJi /e11111111111115el1j1
Notification Response Form
ZAl2 -096
Meeting Date: November 8, 2012 at 6:30 PM
Dove 114 Infinity Llc
-'121 S Carroll Ave
Southlake Tx, 76092
A1620 1
Direct questions and mail responses to:
City of Southlake
Planning & Development Services
Notification Response
1400 Main St; Ste 310
Southlake, TX 76092
Phone: (817)748 -8621
Fax: (817)748 -8077
PLEASE PROVIDE COMPLETED FORMS VIA MAIL, FAX OR HAND DELIVERY
BEFORE THE START OF THE SCHEDULED PUBLIC HEARING.
Being the owners of the property so noted above. are hereby
in favo opposed to undecided about
(circle or underline one)
the proposed Site Plan referenced above.
Space for comments regarding your position:
Signature:
Additional Signature/
Printed Name(s):
Must be property owner(s) wh
Phone Number (optional):
Date:if /Z—
Date:
Case No. Attachment F
ZAl2 -096 Page 3
Notification Response Form
ZAl2 -096
Meeting Date: November 8, 2012 at 6:30 PM
Dove 114 Infinity Llc
-1121 S Carroll Ave
Southlake Tx, 76092
A1620 1
Direct questions and mail responses to:
City of Southlake
Planning & Development Services
Notification Response
1400 Main St; Ste 310
Southlake, TX 76092
Phone: (817)748 -8621
Fax: (817)748 -8077
PLEASE PROVIDE COMPLETED FORMS VIA MAIL, FAX OR HAND DELIVERY
BEFORE THE START OF THE SCHEDULED PUBLIC HEARING.
Being the owner(s) of the property so noted above, are hereby
r inor of opposed to undecided about
(circle or underline one)
the proposed Site Plan referenced above.
Space for comments regarding your position:
Signature:
Additional S(gnature
Printed Name(s):
Must be property owner(s) wh
Phone Number (optional):
printed at top.
Date:
Date:
contact the Planni g Department. One form per property.
Case No. Attachment F
ZAl2 -096 Page 4
Notification Response Farm
ZA1 2 -095
Meeting Date: November 9, 2012 at 6 :30 PM
Llh+rin, Mark S
417 Cr&ard Dill Dr
uthlakc fix,. 76092
22768E 1 1
PLEASE PROVIDE COMPLETED rORMS VIA MAIL, FAX OR HAND DELIVERY
BEFORE THE START OF THE SCHEDULED PUBLIC HEARING.
Being the owner(s) of the property so noted above, are hereby
in fever of oppesed v ,~ undecided about
(circle or underline ones
the proposed Site Plan referen d above. �'- ��� �r�4:
Space for comments regarding your position:
fl I N)Vk 116 (_ + 0 V4
Signature_
d
�a j A A45 14 ,
�4
`TLIGY NL-f
Date r & - 7014-1 tom .
Additional Signature: hWL _ _ Date:
Printed Narne(s):
Must be o+wn� s) whaw n s are printed a'. Le OthwWas tanlad the Plannin Department tw form r pany-
Rr�Y r{ . erne{ 1 - p �'- #1 � W
Phone Number ( optional ):
Case No. Attachment F
ZAl2 -096 Page 5
Notification Response Farm
ZAl2 -096
Meeting Date: Novomber 8, 2012 at 6.30 PM
Litwin, Mark S
417 Orchard Hill Dr
outhlake Tx, 76092
22768E 1 1
PLEASE PROVIDE COMPLETED FORMS VIA MAIL, FAX OR HAND DELIVERY
BEFORE THE START OF THE SCHEDULED PUBLIC HEARING.
Being the owner(s) of the property so noted above, are hereby
in favor of opposed t undecided about
(circle or underline one)
the proposed Site Platy referenced above. NOV 1 2412A .4x.6:54
Space for comments regarding your position:
_1L
Signature:
Date; 1-16
Additional Signature: Date, �a�2.
Printed Names }: aA �� t
Must ve praaerty Dwner(s) whose names) are panted at top. Qtheiwlae eon4act the Planning Department. One farm per prWerl+f..
Phone Number (optional): � 1 � W l
Case No. Attachment F
ZAl2 -096 Page 6
I �� ID
6 OAL4M - �K6 W V�" 2'