Item 4B. Approve Change Order No. 4 for the Caylor Wholesale Meter Modification
Requested Action
Approve Change Order No. 4
to the contract with
Circle C Construction Company
for the TW King 30" water line to
include the Caylor Wholesale Meter
Modification in the amount
$166
The requested action is to approve change order number 4 with Circle C
Construction Company for the TW King 30 -inch water line to include the Caylor
Wholesale Meter Modification in the amount of $166 thousand 700 dollars.
2
Project Location
1300 N. Caylor Road, Fort Worth, Texas
fe
r -
A
The Caylor Meter Station is located at 1300 N. Caylor Road in Fort Worth. The City
of Fort Worth currently pumps water to the Caylor ground storage tank and meter
station located west of US 377 before discharging into the water distribution system
which serves the cities of Southlake and Keller.
3
Background Information
• April 21, 2011
- Cities of Fort Worth, Southlake and Keller met to discuss the
removal and replacement of an existing 16 -inch turbine meter
from the 36 -inch water line which supplies water to Southlake
and Keller.
- The turbine meter is located at the Caylor Ground Storage Tank
and Meter Station.
• June 13, 2012
- Engineering services contract awarded for preparation of final
plans and specifications to Freese & Nichols, Inc.
• November 2012
- Change order request to the TW King 30" Water Line for the
construction of the Caylor Wholesale Meter Modification to be
constructed by Circle C Construction Company.
- City of Keller will partner with the City of Southlake through an
Interlocal Agreement to share the expenses for this project.
In April of 2011 the City of Fort requested a meeting with the Cities of Southlake and
Keller to discuss the removal and replacement of an existing 16 -inch turbine meter
from the 36 -inch water line which supplies water to Southlake and Keller. The
existing meter will be replaced with a 36 -inch magnetic meter.
In June of this year, the city of Southlake awarded an engineering services contract
with Freese & Nichols, Incorporated to prepare plans and specification for the meter
modification. Freese & Nichols worked closely with the City of Fort Worth to insure
that the proposed modifications were in compliance with Fort Worth's specifications.
Fort Worth has completed their review and a final construction cost estimate has
been submitted by Cirlce C Construction company for the installation of the
proposed 36 -inch magnetic meter.
The City of Keller has agreed to share in the costs associated with this project
through an Interlocal Agreement with the City of Southlake.
12
Proposed Change Order No. 4
• Siemens 36 -inch Magnetic
Flow Meter
- Meets requirement of
the City of Fort Worth
• Removal and disposal of
existing meter, pipes and
fittings
• Concrete adjustments for •,.«
new meter
• Installation with
appurtenances for
connection
• SCADA system connection
• Sodding and general clean
up of construction site
Yty I_I�
x.
P �t
Proposed Change Order No. 4 for the TW King water transmission line will include
the construction cost associated with the Caylor Wholesale Meter Modification.
These charges include a Siemens 36 -inch Magnetic flow meter which was approved
by the City of Fort Worth. Also, the removal and disposal of the existing equipment
to be removed, concrete adjustments for the new meter, installation, SCADA system
connections and general site clean up.
5
Financial Consideration
Original Contract
$6,739,020.00
Change Orders No. 1— No. 3 1111t _MPM + $1,500.00
Mal Contract Amount $6,907,220.00
*City of Keller will contribute $49,866.00 to this change order.
The original contract price for the TW King 30 -inch water line and meter station was
6 million 739 thousand 20 dollars with and additional 1500 dollars for change orders
1 through 3. Change order number 4 in the amount of 166,700 will revise the total
contract amount to 6,907,220. The City of Keller will contribute to this change
order 49 thousand 8hundred 66 dollars.
0
City of Southlake Strategy Map
The City of Southlake provides municipal services that support the highest quality of life
for our residents and businesses. We do this by delivering outstanding value and
unrivaled quality in everything we do.
i� �t�bard; ao,�ra:exFe�vz:. -�
®
®
®
A
Safety &
Mobility
Infrastructure
Quality
Partnerships& Performance Management
Securlty
Development
Volunteerism & Service Delivery
C3Pmvldeattraetive&
c4 An,..&keep top -tier
Mh,
unique
sp —for businesses to drivae dynamsc&
{or partnershipsClt
&re a enjoyment of pars nal
Y rl n
s ustalnetile etenom at yoluntaerinvolvement
Intererts
nvlronment
Manage the Business
51AChlevebext- I 81COI1abo—Jlh 88Fnhanceresident BCProvide 851mp— Bb OPtimice
1- 1— elates In select partner�to qusllty of lire &buxiness hlghq I" pe rferm. —f useof
dicitydiscipllnas Implementservien austalnabllitythrough me r danvaP o.pere. -1 techa 0,
saluupns teudsm s —Ice sses
Provide Financial Stewardship
Ft Adhere toflnential management F2lnwest tv ptmlde &maintain F3 AShievefiscal wellness F4EStablisli &maintain
principles &budget high qua Gtro vubllc assets antlerdx anectlw Internal tomrol;
Promote Learning &Growth
L1 Entureeutpeoplt L—hanceleadership U Attract. develop& L4c.p[te& I5 Empower lnfl
� wderztend tM1e snetegy& cepabllltiestedelivet rNeina skilled raw 111 h deN.slon- makingel.... {s
I how they tonlribut—ft —ft. , worktarca t pvrformata l in theeeganliatien
Approval of Change Order No. 4 will link this request to the City's strategy map
relative to the focus area of infrastructure by investing to provide and maintain high
quality public assets.