Item 4BApprove Change Order No. 4 for the Caylor Wholesale Meter Modification
Item 4B
Requested Action
Approve Change Order No. 4
to the contract with
Circle C Construction Company
for the TW King 30” water line to include the Caylor Wholesale Meter Modification in the amount $166,700.00
Project Location1300 N. Caylor Road, Fort Worth, Texas
Background Information
April 21, 2011
Cities of Fort Worth, Southlake and Keller met to discuss the removal and replacement of an existing 16-inch turbine meter from the 36-inch water line which supplies water to Southlake
and Keller.
The turbine meter is located at the Caylor Ground Storage Tank and Meter Station.
June 13, 2012
Engineering services contract awarded for preparation of final plans and specifications to Freese & Nichols, Inc.
November 2012
Change order request to the TW King 30” Water Line for the construction of the Caylor Wholesale Meter Modification to be constructed by Circle C Construction Company.
City of Keller will partner with the City of Southlake through an Interlocal Agreement to share the expenses for this project.
Proposed Change Order No. 4
Siemens 36-inch Magnetic Flow Meter
Meets requirement of the City of Fort Worth
Removal and disposal of existing meter, pipes and fittings
Concrete adjustments for new meter
Installation with appurtenances for connection
SCADA system connection
Sodding and general clean up of construction site
Financial Consideration
* City of Keller will contribute $49,866.00 to this change order.
This item is within the current authorized budget amount.
Questions:Bob Price 817-748-8097