Approve an amendment to the Advance Funding Agreement with TxDOT for the FM1709 Median and Deceleration Lane Project in the amount of $375,000
Requested Action
Approve an amendment to the Advance Funding Agreement with TxDOT for the FM 1709 Median and Deceleration Lane Project in the amount of $375,000
FM1709 Median and Deceleration Lane Project
Original Agreement approved by the City Council on September 15, 2009
TxDOT construction of medians and deceleration lanes – complete, with some clean-up remaining
Amendment to TxDOT Advance Funding Agreement
Pre-construction Meeting – May 2010
Begin Construction – June 2010
Original Contract Time – through August 2011
Project Completion – September 2012
Damage and Delay Claim by the Contractor
Utility conflicts at all deceleration lane locations
Re-design of plans and TxDOT approval
Revised continuity of work due to overlapping of median construction with deceleration lane construction
Utility Conflicts
City of Southlake
Private Irrigation
TxDOT
Verizon
Level 3
Oncor
AT&T
Lone Star Gas
Atmos
Qwest
City of Southlake
One Source
Tri-County
AFA AmendmentFunding by Southlake
Change Order No. 23 $375,000
TxDOT Admin Costs (waived) 0
Total Cost (negotiated w TxDOT) $ 375,000
Funding for the change order is available in the Traffic Management Bond residual fund.