Item 6E
Approve Guaranteed Maximum Price with Lee Lewis Construction in the amount of $13,315,693for the DPS North Training Facility
Item 6E
Background
2005 – Matrix Study Recommendation
November 2008 – Selection of Robert Garza
February 2009 – Authorization to hire CMR
April 2009 – CCPD Approves Lee Lewis
November 2009 – SPIN Meeting
January 2010 – P&Z Approval
June 2010 – City Council Approval
2012 – Anticipated Construction Start
2013 – Anticipated Construction Completion
Financial Considerations
CMR is bound to an agreed GMP that is determined from actual advertised bids received on May 2, 2012.
GMP: $13,315,693
Item 4C
Questions?