Item 4C FM1938 Phase 2 Landscaping Design
Item 4C
Requested Action
Approve Amendment No. 1 to the Engineering Agreement with Transystems, Inc. for FM1938 Phase 2 landscaping design in the amount of $67,833.42
Amendment No. 1 – Revised Scope
FM 1938 Project
FM 1938
Phase 1
Phase 2
Conceptual Landscape Design
Conceptual Landscape Design
Conceptual Landscape Design
Conceptual Landscape Design
Conceptual Landscape Design
Conceptual Landscape Design
TranSystems Amendment
FUNDING
Available
Capital Improvement Program Budget for the FM1938 Phase 2
C2 Provide travel convenience within City and region
Questions:Bob Price (817) 748-8097
Preliminary Cost Estimates
Construction Cost = $1,809,050
Landscape $1,350,550
Irrigation $ 458,500
Annual Maintenance Cost = $75,000
Urban Design Plan
Urban Design Plan
Urban Design Plan
Approve PSA with TranSystems Corporation for FM1938 Phase 2
FM1938 Phase 2 Construction
Anticipated construction cost projection is $20,928,948
Engineering fee is approximately 7.2% of the construction cost
The fee for design includes both Basic Services and Special Services
Approve PSA with TranSystems Corporation for FM1938 Phase 2
Funding for FM1938 Engineering Design
Engineering design is included in the General Fund CIP - successive CIP budgets from 2001 to present
Southlake’s net obligation under this contract – approx. $790,000 with participation by Tarrant County and the City of Keller