2001-08-08 Meeting Report (Cross Timber Hills Sewer)Issues Relating to the Cross Timber Hills Neighborhood Sewer Project
Question and Answer Summary from S.P.I.N. Neighborhood #12 Meeting August 8, 2001
NOTE This draft is a work -in- progress and does not yet include all answers to all of the
questions. We will post these questions and any others that are raised along with available
answers on the City's website as soon as possible www.ci.southlake.tx.us
1. GENERAL INFORMATION
A. What are the areas that City staff looked at in the neighborhood today? How many
problem areas were identified during this evaluation? How many problem areas has
staff identified in the project? Answer
B. Is there a form to address smaller issues? Where can I get copies of the forms to
document follow -up items? Answer
C. I live nextdoor to the house that burned down which is being re- built. What recourse
do I have with others that cause erosion problems due to construction? Is the lady
who is rebuilding the house going to be required to hook onto sewer? If this is
required, will that delay their ability to move in the house until the project is
completed? Answer
D. Does the City have the ability to test soil to determine whether or not a house would
be required to hookup to sewer? Can that testing occur this spring to determine who
is required to hookup? Answer
E. Everyone has individual issues, is the purpose of this forum to address the individual
specifics, or cover generalities? Answer
F. Can another meeting be scheduled in 5 -6 weeks to evaluate progress on the project
and the follow -up items? Answer Yes. SPIN #12 Representative Jackie Phillips
has already requested a follow -up meeting; at this time the initial feel is to have a
follow -up meeting during the week of September 21 For updates on the meeting
status, please contact Jackie at (817) 481 -9662, or John Eaglen at the City of
Southlake at (817) 481 -1433.
2. PROJECT TIMELINE ISSUES FOLLOW -UP TIMELINE ISSUES
A. What is the estimate for the project to be completed and evaluation of follow -up items
are to begin? Are driveway issues to be included with roadway issues, or are these
items to be assessed separately? Will driveways damaged be repaired or replaced?
Answer
B. Some of us have written requests submitted to the City repeatedly and have been
constantly given an extension, it is getting to the point of the year where the weather
may impact some of the homeowner issues. Why can't the City begin to address
some of the homeowner issues now versus at the completion of the project? Answer
C. A letter dated July 1 from Ms. Franco projected a completion date for sixty (60) days,
why has there been an extension of ninety (90) days on top of this when there has
been no weather issues that have impacted work conditions? Answer
D. At the beginning of the project, videotaping occurred prior to construction to
document the original condition. I didn't participate in that process, so what type of
procedures do I need to follow to request repairs to the driveway and to address
erosion problems? Answer
E. 1359 Lakeview I have one "replace" drive, what is the timeline for this to occur?
Answer:
Cross Timber Hills Neighborhood Sewer Q A Summary Page I of 5
Issues Relating to the Cross Timber Hills Neighborhood Sewer Project
Question and Answer Summary from S.P.I.N. Neighborhood #12 Meeting August 8, 2001
F. When ninety (90) days is mentioned as an extension, does this mean an extension
period of ninety (90) days for construction of sewer only, or does this include a
projected completion of follow -up items? Answer
G. What are the plans and projected timeline to address damages that occur from here on
out to completion of the project? Answer
H. When can we expect to hook up to sewer on Meadow Glen? Answer
I.
2. CONTRACTOR ISSUES
A. What does the contract with the City require the contractor to repair? Answer
B. I think that the road issues and repair reconstruction should be completed by the
contractor, is this in the plans for that to occur? Answer
C. Is there a retainage clause in the contract based on performance? If so, what is the
amount of this? Does the contractor have to address all of the identified follow -up
items or pay the retainage amount? Answer
D. Has liquidated damages not occurred because of the City's willingness to grant
continual extensions to the contractor on this project? Answer
E. On Twin Creek, the contractor knocked down the utility pole. As a result the utility
lines are lower, why are the contractor utilities not required to set the pole and utility
lines at the previous levels? Answer
F.
3. ROADWAY ISSUES
A. What are plans to address pavement failure directly attributable to the contractor?
Answer
B. From Lakeview to Woodbrook, the whole section of the roadway has failed, what are
plans to immediately address this area? Answer
C. The time that the contractor has been on the roads has impacted the road base, what
are the City's plans to assess the road issues, and to distinguish what amount of
damage is attributable to the contractor versus wear and tear? Answer
D. One item of concern voiced during the construction period has been that the City's
maintenance of the roads has been fairly good, and that the condition of the road sub-
base has allowed for some success in maintenance, however the construction has
eroded the quality of the road base. What will happen when a patchwork approach to
repairing the road sub -base will only last for a short period of time and it comes time
to address again? Can the City and /or contractor commit to restoring the sub -base to
the original condition prior to this construction? Answer
E. I know that funding is an issue with the City right now, and we have experienced how
long it takes to get things through the City, how long will it take to complete road
repairs? Will the sub -base be repaired replaced, or will the repairs replacement be
on the overlay only? What kind of timeline are we looking at for road repairs to
occur? Answer
F. In terms of temporary road repairs, when will this begin? How long would these
items take to complete? What would be the projected completion date for these
items? Answer:
Cross Timber Hills Neighborhood Sewer Q A Summary Page 2 of 5
Issues Relating to the Cross Timber Hills Neighborhood Sewer Project
Question and Answer Summary from S.P.I.N. Neighborhood #12 Meeting August 8, 2001
G. With respect to completing repairs and /or replacement to the roads, it has occurred to
me that everyone may not connect to the sewer at the same time. What is the
potential that as individuals connect that road damages occur that undo what repairs
the contractor or the City will make? Answer
H.
4. SILT BUILDUP POND AND /OR CREEK ISSUES
A. Can the items involving the ponds and /or creeks be prioritized to begin now versus
getting into later in the year and a potential "rainy" season? Answer
B. When the contractor crossed Higgins Creek, they stored dirt on the other side of the
pond, and this began to roll into the lake when rains began. Did the contractor fully
comply with the erosion control ordinance provisions throughout this project, because
I did not remember any type of erosion curtain placed in the storage area? Answer
C. As they begin to remove foliage, the potential for silt buildup in the pond area is
greater when the rainy season hits. Can erosion control be utilized in areas where
they have to dig out? Answer
D. 1363 Lakeview What has been happening in the dirt storage area by Lakeview is
that there are differing components in the dirt, and these items are going in the pond
when sprinklers are running and it takes all of the silt buildup out of the ditch. Would
a soil engineer be able to quantify through material analysis the impact of the
construction on the silt buildup in the pond? Answer
E. Is the City going to address the pond issues before the completion of the ninety (90)
day period? Answer
F. Can the silting issue be quantified by an example in front of my house? I have a
culvert at the front of the property that has built up 6" of silt since construction began.
Is it not possible to quantify by taking 6" of mass by the length of the culvert to
quantify the contractor's impact? Answer
G.
5. TREE PRESERVATION AND MITIGATION ISSUES
A. What is the time period allotted for tree replacement mitigation from the time the
tree dies? Answer
B. In the contract, if a tree dies three (3) years later, is the contractor obligated to replace
the tree? Answer
C. If the City will not replace trees in easements, does this include temporary easements
also? Answer
D. If my driveway is in an easement, does the contractor have to replace the drive if they
do not have to replace trees in the easement? Answer
E. Is there something that can be done now to address and save trees that are in jeopardy
now and could die in the future? Answer
F. If the project is completed in ninety (90) days, can we look at extending the
evaluation period for trees into the spring to identify all of the trees that would be
eligible for replacement mitigation? Answer
G. When does the two (2) year maintenance bond period begin, at the completion of the
project? Answer
Cross Timber Hills Neighborhood Sewer Q A Summary Page 3 of 5
Issues Relating to the Cross Timber Hills Neighborhood Sewer Project
Question and Answer Summary from S.P.I.N. Neighborhood #12 Meeting August 8, 2001
H. It sounded earlier as if the City would be responsible for trees versus the contractor,
certainly extending the evaluation period into the spring would help identify all tree
issues that are attributable to the contractor. However, if the extension doesn't occur,
can we assess the contractor for trees that die within the two (2) year maintenance
bond period? Answer
L When do you plan to start the replacement process? Does the replacement process
begin within the ninety (90) days or after completion of that period? Answer
J. Does the City assess the contractor for tree replacement mitigation for root system
damage that occurs as they drag trackhoes across yards? What is the documentation
process for this type situation? Answer
K. My sprinkler system was damaged and it took several months to repair and get online
again, since that time I have had two (2) trees die. How do I determine the
relationship between the contractor's actions to the sprinkler system and the death of
the trees? How do I go about documentation procedures? Answer
L. I would like to see the City give the benefit of doubt on tree replacement mitigation
issues to the residents versus the contractor, why do I perceive that the situation is
reversed? Answer
M. In regards to minimum replacement criteria, I would like to see the City do the right
thing for homeowners and the potential re -sale value of their homes through
replacement and mitigation efforts with larger diameter trees. What is the potential to
evaluate the criteria? Answer
N. In 1998 -99 when City staff presented this project to the neighborhood, we were
assured that the contractors and the City would take a "tree friendly" approach. The
City has failed to protect the trees in the neighborhood, and did not take a proactive,
tree friendly attitude. Why did the City not follow through on their initial
commitment? Answer
O. Why does the residents have to prove that the contractor killed trees versus them
having to prove that they did not do it? Answer
P. What can people do now to document their tree concerns so that in the future there
are fewer issues with determining fault? Answer
Q. I have a concern over the equity of measurement, the trees that die are measured 4'
off the ground, but your mitigation criteria use measurements at the base. Does this
type of criteria seem equitable? Answer
R. Are replacement trees to come from the City's tree farms? If not, will residents get to
pick the replacement trees? Answer
S. In a long -term perspective, if there is service requirements to the sewer in five years,
are there still going to be protections from mitigation for trees removed in easements?
Answer
T.
6. OPERATIONS ISSUES
A. The contractors are continuously running up and down the street with the trackhoes
gratuitously and it seems excessive, and I believe it has contributed to the condition
of the road base, is this constant activity necessary and what is the common practice
from similar projects? Answer
Cross Timber Hills Neighborhood Sewer Q A Summary Page 4 of 5
Issues Relating to the Cross Timber Hills Neighborhood Sewer Project
Question and Answer Summary from S.P.I.N. Neighborhood #12 Meeting August 8, 2001
B. The contractor has had workers out grooming the back yards of areas where it doesn't
make sense to be working at that particular time, it doesn't seem as if the contractor
has coordinated the empolyees in the most effective manner. What is the response to
that observation? Answer
C.
Cross Timber Hills Neighborhood Sewer Q A Summary Page 5 of 5