Item 4GCITY OF
SOUTHLAKI
MEMORANDUM
December 6, 2011
To: Shana Yelverton, City Manager
From: Robert H. Price, P.E., Public Works Director
Subject: Approve Amendment No. 2 to the Engineering
Agreement with Nathan D. Maier Consulting Engineers
Inc. for White Chapel Boulevard from Highland Street to
SH 114 in the amount of $173,827
Action
Requested: Approve Amendment No. 2 to the Engineering Agreement
with Nathan D. Maier Consulting Engineers Inc. for White
Chapel Boulevard from Highland Street to SH 114 in the
amount of $173,827
Background
Information: In October 2008, Nathan D. Maier Consulting Engineers, Inc.
(NDM) was hired to design the North White Chapel
Boulevard Improvement project from the intersection at State
Highway 114 down to, and including, the intersection of
Highland Street. The White Chapel Boulevard Improvement
project design was for a standard four lane divided roadway
with a raised and landscaped median.
The original professional services agreement (design
contract) in the amount of $264,859 included survey for the
entire length of the project, design of the roadway, a
hydraulic report of Dove Creek to properly size the proposed
storm sewer box culverts near State Highway 114,
determination of right of way needs and corresponding
exhibits, geotechnical investigations to determine pavement
design, and design for relocating existing water and sewer
utilities within the corridor to accommodate the proposed
roadway. The original design contract signed in 2008 was
for the final design, bid documents and construction phase
services of the White Chapel Boulevard Improvement
project.
NDM prepared and submitted conceptual design to the city
for review of a conventional four -lane divided roadway using
the existing centerline and taking right of way equally from
both sides of the proposed roadway. It was later determined
that the straight roadway alignment of White Chapel
Boulevard should be shifted at the intersection of Highland
Street so that no additional right of way will be required from
the Southlake Church, due to the proximity of the existing
building to the right of way. Since the property at the
northwest corner of the intersection belongs to the City,
there would also be a cost savings in the right of way
acquisition by shifting the horizontal alignment of the
roadway to the west.
Supplemental Agreement No. 1, in the amount of $12,285
was approved by the City Manager in January, 2010 to
revise the horizontal alignment of White Chapel Boulevard at
the intersection of Highland Street to the west and add 2 feet
of pavement on both sides of the road for bike lanes. The
design fee for the revision also included revising the new
typical sections of the roadway to include the additional 2' on
each side of the road to accommodate bike traffic.
NDM coordinated with design engineers for the White
Chapel Countryside Office Park and made alignment
recommendations for the city's waterline construction project
along Highland Street, which is now complete. NDM had
also revised the schematic layout at the intersection and
submitted it to staff for review. Design had progressed to
nearly 30% when the city suspended work on the roadway
design to allow consideration of alternative traffic control
methods at the Highland Street intersection.
Traffic circulation issues at Carroll High School caused the
staff to reconsider operation of the Highland Street
intersection. Several different types of intersection control
methods were evaluated to determine the most
advantageous approach. A traffic engineering consultant
looked at the costs and level of service (LOS) for two way
stop control, four way stop control, traffic signal control, a
single lane roundabout, and a dual lane roundabout. Staff
has presented these options to members of the City Council
and Planning and Zoning Commissioners at two Southlake
2030 work sessions. Summarizing those discussions, the
two way and four way stop control intersection and the single
lane roundabout will not efficiently handle the projected 2019
volume of traffic without excessive delay. Signal control
would be useful during the morning and afternoon peak
periods, but would not operate efficiently during the
remainder of the day and would impose continuing
maintenance and operation costs. The dual lane
roundabout, does improve capacity at the intersection and
creates the least delay for drivers of the options considered.
Council and Planning and Zoning members of the 2030
committee directed Staff to move forward with the design of
a dual lane roundabout at the intersection of North White
Chapel Boulevard and Highland Street.
Supplemental Agreement No. 2, in the amount of $173,827
is for the completion of design of White Chapel Boulevard
along the revised alignment and will include a dual lane
roundabout at the intersection of Highland Street.
The revised scope as outlined in Supplemental Agreement
No. 2 includes additional survey of up to 350' beyond the
original limits of Highland Street and up to 500' north of
Highland Street along White Chapel to accommodate the
dual lane roundabout and the revised alignment of the
intersection. The agreement also includes landscaping and
irrigation design of the proposed roundabout and the center
medians along White Chapel Boulevard. Subsurface utility
engineering work will be performed in order to verify the
location of existing water and sanitary sewer lines and any
other private utilities within the corridor that will need to be
relocated prior to beginning construction. The utility design
includes the relocation of existing sanitary sewer mains
which will be in conflict with the new pavement. The
drainage design will need to be updated to incorporate the
drainage from the new Countryside White Chapel Office
Park development that has been constructed since the
original drainage study was performed by NDM. Finally, the
revised scope includes final engineering plans, traffic control
and sequencing for construction, contract documents,
bidding of the construction project and construction
administration.
Roadway Design
$ 79,735
Survey Services
22,164
Drainage Design
7,254
Utility Design
4,654
Subsurface Utility Engineering
39,450
Landscaping and Irrigation Design
12,500
Construction Administration
2,640
Reimbursable Expenses
2,000
Right of way Exhibits
3,430
Total for Amendment #2 $173,827
The proposed amendment brings the total engineering
design cost for the White Chapel Improvement Project from
State Highway 114 to Highland Street to $450,971.
The schedule going forward anticipates that design will be
completed in the 4th quarter of calendar year 2012. Right of
way documents will be available to begin acquisition in the
3 rd quarter of 2012 and right of way acquisition completed by
the 1 St quarter of 2013. Relocation of the franchise utilities
(electric, gas, phone, etc.) will begin when right of way is
available and should be completed by the end of the 3rd
quarter of 2013. Staff anticipates the construction to be
awarded in the 4 quarter of 2013.
Financial
Considerations: Funds for the engineering design of the White Chapel
Boulevard Improvement project are included in the
previously approved Capital Improvements Program project
budget.
Strategic Link: The construction of the North White Chapel Boulevard
Improvements project links to the city's strategy map relative
to the focus areas of Mobility, Infrastructure and
Performance Management and Service Delivery. The
specific corporate objectives that are met by the construction
of this project include: C2 - Provide travel convenience
within the City and the region, B4 - Provide high quality
customer service, and F2 - Invest to provide and maintain
high quality public assets.
Citizen
Input/
Board Review: None
Legal
Review: None
Alternatives: The City Council may approve the Amendment to the
existing Professional Services Agreement or deny it.
Supporting
Documents: Location Map
Nathan D. Maier Engineers, Inc. Supplemental Agreement
No. 2
Staff
Recommendation: Approve Amendment No. 2 to the Engineering Agreement
with Nathan D. Maier Consulting Engineers Inc. for White
Chapel Boulevard from Highland Street to SH 114 in the
amount of $173,827
Staff
Contact: Robert H. Price, P.E., Public Works Director
Gordon J. Mayer, Jr., P.E., City Engineer
Cheryl Taylor, P.E., Civil Engineer
L
L
V
► �
EXHIBIT SA -2
Supplemental Agreement No. 2
FOR
WHITE CHAPEL BOULEVARD
FROM
E. NORTHWEST PARKWAY (S.H. 114) TO E. HIGHLAND STREET
FOR
THE CITY OF SOUTHLAKE, TEXAS
This Supplemental Agreement No. 2 amends the original Scope of Services dated 10/14/08
to include additional modifications to the alignment and schematic design as previously
submitted to The City of Southlake (The City) by Nathan D. Maier Consulting Engineers,
Inc. (NDM). These modifications will realign the proposed roadway for approximately
1000 ft along White Chapel Boulevard to incorporate a roundabout at the intersection of
White Chapel Boulevard and Highland Street. The proposed changes altering the original
scope include:
I. Topographic and Right -of -Way Survey
Survey of existing topographic features will be performed for approximately 50 ft of
additional width beyond previous topographic survey limits. This additional survey will
have the following limits:
• Along White Chapel Boulevard from Countryside Court to approximately 250 ft
to the south.
• Along White Chapel Boulevard from approximately 500 ft north of Highland
Street to Highland Street.
• The northwest and southwest corners of White Chapel Boulevard and Highland
Street.
• Along White Chapel Boulevard from Highland Street to approximately 350 ft to
the south.
• Along Highland Street from previous survey limits to approximately 350 ft to
the west (100 ft width).
• Along Highland Street from previous survey limits to approximately 150 ft to
the east (within existing ROW).
WHITE CHAPEL BOULEVARD 08/31/11
Page 1
Additional cross sections will be provided, as required by design, along Highland Street
to the west of the adjusted White Chapel Boulevard intersection, as well as driveways
affected by the adjusted White Chapel Boulevard centerline.
Additional survey will be required upstream of the existing cross culvert to tie
topographic features associated with the recent development of this property.
The additional survey of existing features will include overhead power lines, telephone
lines, cable TV lines and any other overhead features. Existing tower foundations and
the elevation of the lowest wires and cables will be included.
The topographic survey will also include, but not be limited to the location of
dwellings, buildings, sheds, fences, streams, roads, utilities, and the outline of wooded
or heavy brush areas, within the limits described. Any dwelling or structure adjacent to,
but not more than 50 ft outside the limits of the work, will be included in the survey.
Sufficient topographic data will be gathered to determine construction limits for
driveways, cross streets and drainage channels.
Additional survey will be gathered after the conceptual schematic has been approved by
the City. The additional survey will be incorporated into the topography gathered
during prior survey operations.
Deed research will be updated for properties within the expanded limits of the
topographic survey. Additional property and right -of -way surveys will be included for
properties west of White Chapel Boulevard and south of Highland Street.
One additional ROW staking will be field located for each affected property at the
completion of construction or at a time to be determined by the City.
IL Subsurface Utility Engineering (SUE)
A Level B SUE will be performed for the project and will include test holes to existing
water lines and sanitary sewer mains at twelve (12) locations to be verified. The utility
mapping will be approximately 60 ft each side of the proposed centerline, 200 ft east
and 400 ft west along Highland Street, and will include gathering and depicting both
City and franchise utility information. This information will be incorporated into the
existing utility mapping prepared during prior utility coordination and topographic
survey activities. Test hole locations will be coordinated between NDM, the City, and
the SUE provider after the utility mapping has been updated from the initial SUE
investigations. Test hole locations will be associated with the following City utilities:
• 12" water line running north and south generally within the existing White
Chapel Blvd. pavement. Test hole operations for this utility will require traffic
control measures and likely will require lane closures.
• 20" water line running north and south and generally within the existing White
Chapel Blvd. pavement. Test hole operations for this utility will require traffic
control measures and will likely require lane closures.
WHITE CHAPEL BOULEVARD 08/31/11
Page 2
• 12" water line running east and west generally within the existing Highland St.
pavement. Test hole operations for this utility may require traffic control
measures and may require lane closures.
• 6" sanitary sewer force main running north and south generally between the
existing White Chapel Blvd. pavement and the east ROW. Test hole operations
for this utility should not require traffic control measures or lane closures.
Additional test holes, expansion of the Level B investigation area, required closures of
the entire roadway, and more than five (5) individual lane closures will be considered
as additional services.
I1I. Conceptual Schematic Design
A conceptual schematic layout with plan and profile will be developed in roll plot
format. Additional alignment modifications to White Chapel Boulevard will be
included beginning at the south end of the project and ending approximately at Station
9 +75 at which point the original schematic alignment is matched. The alignment from
this point to the north will be along the existing roadway alignment. The White Chapel
Boulevard and Highland Street intersection will be shifted further to the west to
incorporate the roundabout.
The adjusted alignments and roundabout will be included as part of the schematic
layout, as well as typical sections and preliminary right -of -way (ROW) requirements.
The schematic will utilize existing aerial mapping and topography as a background.
After approval by the City, the additional topographic survey, as detailed above, will be
gathered.
IV. Preliminary Design
Conceptual roadway alignments and profiles will be adjusted per guidance from the
City to incorporate a roundabout at the intersection of White Chapel Boulevard and
Highland Street and to further develop the preliminary design.
The profile with preliminary cross sections will consider existing adjacent land use,
side street and driveway connections, and sight distance requirements at Highland
Street. Existing water line and sanitary sewer elevations will evaluated for adequate
clearances when developing the proposed profile.
Pavement edges will accommodate a dual lane roundabout with median islands on the
connecting streets. Layout of the roundabout intersection will follow the conceptual
layouts provided by the City as closely as possible. Pedestrian access across each
connecting roadway will include crosswalks and ADA compliant ramps.
ROW requirements will be determined based on development of the preliminary cross
sections.
A truck apron will be provided at the roundabout.
WHITE CHAPEL BOULEVARD 08/31/11
Page 3
Underdrain requirements for the roundabout will be evaluated and included as
necessary.
V. Landscape and Irrigation Design
Landscaping will be provided for the roundabout, as well as for the medians along
White Chapel Boulevard. Irrigation will be provided as required for proposed
landscaped areas.
All hardscape areas will be included in the landscape design and may include stamped
concrete for crosswalks and stamped concrete or pavers for median areas.
All landscaping and irrigation will adhere to a City - provided palette for colors and
materials, as well as City standard details and design criteria.
VI. Utility Design
Utility layouts will be developed for the relocation and lowering of the existing sanitary
sewer force main that will be in conflict with the new pavement section.
It is assumed that the 20 inch water line will not require adjustments based on the
information provided. Any adjustments to this line is beyond this scope of services.
VII. Drainage Design
Drainage area mapping and runoff computations will be revised to incorporate new
development of the watershed upstream of the cross culvert. Preliminary sizing of
this structure will also be revised for inclusion on the schematic.
Proposed channel grading will be revised based on changes in the topography due
to the new development. Preliminary grading will be included on the schematic.
VIII. Traffic Control for Roundabout
Additional layouts and details for the traffic control plan and sequencing of
construction will be provided for the inclusion of the roundabout for anticipated
additional phases of construction at this location.
IX. Final Design
The approved conceptual schematic and preliminary design will be drafted into final
form and will include the new roundabout components.
Additional typical sections and details will be prepared for the roundabout.
A grading plan for the roundabout intersection will be prepared.
WHITE CHAPEL BOULEVARD 08/31/11
Page 4
X. Construction Administration
Construction Observations - With the increased length of the project to the south and to
the west and with the additional design services provided in this supplemental, it is
anticipated that the construction duration will be lengthened by one month.
Changes & Reviews - The additional length and complexity of the project is anticipated
to increase the amount of review and coordination with the City and contractor for
services described in the original contract (Section XVIII, Paragraph E.).
WHITE CHAPEL BOULEVARD 08/31/11
Page 5
EXHIBIT D
Supplemental Agreement No. 2
For
White Chapel Boulevard
E. Northwest Parkway (S.H. 114) to Highland Street
Engineering Fees
DESCRIPTION ENGINEERING
FEE
BASIC SERVICES
Roadway Design $129,639
TOTAL BASIC SERVICES $129,639
SPECIAL SERVICES
Survey Services
$35,170
Hydraulic / Hydrology Study and Analysis
$25,485
Waterline Replacement
$19,455
Permitting
$11,160
Construction Administration
$12,470
Geotechnical Investigation
$8,000
Reimbursable Expenses
$2,900
Unit Costs $20,580
12 - Right -of -way dedication
exhibits / Easement dedication
exhibits - $1,715 each
TOTAL SPECIAL SERVICES $135,220
SUPPLEMENTAL AGREEMENT NO. 1 $12,285
WHITE CHAPEL BOULEVARD 08/31/11
Page 6
SUPPLEMENTAL AGREEMENT NO. 2
BASIC SERVICES
Roadway Design
SPECIAL SERVICES
Survey Services
Drainage Design
Utility Design
Subsurface Utility Engineering
Landscape and Irrigation Design
Construction Administration
Reimbursable Expenses
Unit Costs ($1,715 per unit)
Additional ROW Dedication Exhibits
Additional Easement Dedication Exhibits
TOTAL FOR SUPPLEMENTAL NO. 2
TOTAL ENGINEERING
$79,735
$22,164
$7,254
$4,654
$39,450
$12,500
$2,640
$2,000
$3,430
$173,827
$450,971
WHITE CHAPEL BOULEVARD 08/31/11
Page 7