Item 4BApprove Change Order No. 1 with Wilson Contractor Services, for the 20-inch water line along SH 114 from North White Chapel Boulevard to Town Square in the amount of $143,219.59
Item 4B
Requested Action
Approve Change Order No. 1:
Wilson Contractor Services
20-inch water line improvements
Cost of $143,219.59
Contract with Wilson Contractor Services
City Council awarded on July 15, 2011
Approve Change Order No. 1
Approve Change Order No. 1
Change Order No. 1
Pipe addition/deduction $86,241.20
Utility conflict resolution 17,098.97
Additional water valves and
appurtenances 39,879.42
Total $143,219.59
* Change Order No. 1 requires City Council action
Financial Considerations
Funding is available
Funding source: FY2011 and FY2012 capital improvement budget
Location Map
Questions:Bob Price (817) 748-8097