Item 4CConstruction Contract for 20-inch water line along SH 114
Item 4C
Item 4C
Award a construction contract for a 20 inch water line along S.H. 114 from North White Chapel to Town Square with Wilson Contractor Services, LLC in the amount of $1,731,720.30
Project Location
20 Inch Water Line
Bid opening May 31, 2011
Eight bids received
Wilson Contractor Services, LLC submitted low bid
Design engineer recommends low bidder
20 Inch Water Line
Project Includes:
8,377 LF of 20 inch water line
Fittings
Restoration of disturbed areas
Alternate Bid selected for additional boring to protect existing trees and landscape
20 Inch Water LineFinancial Considerations
Contract Award:
Apparent low bidder – Wilson Contractor Services, LLC in the amount of $1,731,720.30 for the Alternate Bid
Contract award is within the City Council approved CIP budget
90 day delayed start to acquire easements
20 Inch Water LineFinancial Considerations
BIDDER BID AMOUNT
Wilson Contractor Services,LLC $1,731,720.30
Saber Development $1,848,324.75
Circle C Construction $2,064,219.00
CPS Civil, LLC $2,093.248.00
Wright Construction $2,036,318.00
S.J. Louis Construction $2,134,271.51
Gin-Spen, Inc. $2,184,306.40
North Texas Contracting $2,289,042.25
Staff Recommendation
Award construction contract for a 20 inch water line along S.H. 114 from North White Chapel to Town Square with Wilson Contractor Services, LLC in the amount of $1,731,720.30
Questions:Bob Price 817-748-8097