Item 4BKirkwood extension to Highland Street – Change Order 1
Item 4B
Requested Action
Approve Change Order No. 1 for the Kirkwood extension contract with Conatser Construction in the amount of $134,668.50
Project Location
Background Information
Purpose:
Ordinance No. 962 established the extension of E. Kirkwood Boulevard and added it to the Master Thoroughfare Plan (MTP)
Provides increased mobility through the City
Bid Opening – October 19, 2010
November 2, 2010
Construction contract awarded to Conatser Construction Tx, L.P.
Change Order No. 1
Additional Signage and Striping
Additional Signage and Striping
Landscape and Hardscape
Re-mobilization
12” reinforced concrete pipe
Proposed Change Order No. 1
Additional Striping & Signage $ 15,056.50
Landscape/Irrigation $ 63,257.00
Hardscape $ 46,125.00
Remobilization $ 7,500.00
12” RCP $ 2,730.00
Total Change Order No. 1 $ 134,668.50
Financial Consideration
Original Contract $ 933,923.75
Change Order No. 1 $ 134,668.50
Total Contract Amount $1,068,592.25
Schedule
May 3, 2011 – 2nd Notice to Proceed issued
Expected to be complete prior to August 22, 2011 – the first day of school
Staff Recommendation
Approve Change Order No. 1 for the Kirkwood extension contract with Conatser Construction in the amount of $134,668.50.
Questions:Bob Price 817-748-8097