Item 5DCity of Southlake, Texas MEMORANDUM January 4, 2002 TO: Billy Campbell, City Manager FROM: Rick Black, Director of Public Safety (Ext. 2421) SUBJECT: Approval of Change Order No. 5 to CMPA, Inc. for the Department of Public Safety — West Facility — City of Southlake Project No. 00 -3320. Action Requested: Approve Change Order No. 5 to CMPA, Inc. Background Information: The City of Southlake entered into an agreement with CMPA, Inc. for the construction of the Department of Public Safety — West Facility on December 12, 2000. Change Order No. 5 is necessitated as a result of the following issues: Item #1 — Landscapinz Modifications In the early stages of the project, staff requested a proposal from CMPA to make six changes to the Landscaping Plan for the facility. After receiving the proposal from CMPA, the decision was made to accept only two of the items; 1) replacing one Dwarf Holly with a Carissa Holly at no additional cost and 2) replacing the specified Weathermatic irrigation control panel with a Rainbird irrigation control panel, for equipment consistency reasons, for an increase in cost of $4,174.50. PSA and staff have reviewed this proposal and find it to be acceptable. It is recommended that this change be approved for an increase of $4,174.50. Item #2 — Interior Gas Line Modifications In Change Order No. 4, it was explained that the gas service for building would be moved from the front of the building to the back of the building. This change necessitated changes to the interior gas piping, as well. However, CMPA proposed to make these changes for no change in price. This item is, therefore, accepted for no change in price. Billy Campbell January 4, 2002 Page 2 Item #3 Additional 3 / " Backflow Assembly During installation of the plumbing for the building, it was determined that an additional 3 /4" backflow preventer assembly was required in the area of the sally port in order to meet code requirements. Staff requested a proposal from CMPA to provide the additional backflow preventer. CMPA proposed to provide the backflow preventer for an increase of $405.14. PSA and staff have reviewed this proposal and find it to be acceptable. It is recommended that this change be approved for an increase of $405.14. Item #4 — HVAC Duct Revisions Minor issues have been identified by the PSA that required minor changes pertaining to the HVAC ducting in the building. Staff requested a proposal from CMPA to make these changes. CMPA proposed to make these changes for no change in price. Therefore, this item is approved for no change in price. Item #5 — Additional Phone/Data Lines The City's Technical Services Department requested installation of two additional phone /data lines in order to allow communications and data transfer between all City facilities. CMPA proposed to provide the additional lines for $121.00. PSA and staff have reviewed this proposal and find it to be acceptable. It is recommended that this change be approved for an increase of $121.00. Item #6 — Likht Fixture /Ceilinz Framinz Conflict An RFI from CMPA identified a conflict between lighting fixtures and the ceiling framing. Staff, PSA and CMPA identified a solution to the conflict that could be accomplished at no additional cost. Therefore, this item is approved for no change in price. Billy Campbell January 4, 2002 Page 3 Item #7 - Ventilation Steel Rid ,-e Plates During installation of the HVAC systems, it was determined that, though ridge vents had been installed in the roof ridges, the steel ridge plates located under the roof ridge vents had not been vented. Without the ridge plates being vented, the roof ridge vents can not operate properly and can not effectively vent the building's attic space. Ventilation of the attic space is preferred in order to reduce heating and cooling loads and moisture accumulation in this space. Staff requested a proposal from CMPA to ventilate the ridge plates after they had been installed. CMPA proposed to vent the ridge plates for an increase of $1,293.00. PSA and staff have reviewed this proposal and find it to be acceptable. It is recommended that this change be approved for an increase of $1,293.00. Financial Considerations: The Contract currently provides a "Contingency" item in the amount of $150,000.00. If approved, these changes can be included under this "Contingency" item and no change in the Contract Amount or the Contract Time will occur as a result of these changes. The balance of the Contingency item is as follows: General Conditions Contingency Change Order No. I Change Order No. 2 Change Order No. 3 Change Order No. 4 Change Order No. 5 Balance in Contingency Citizen Input/ Board Review: None $150,000.00 >11,868.00> > 6,800. 00> > 6,212. 00> > 4,758. 00> > 5,993.64> $114,368.36 Legal Review: None Billy Campbell January 4, 2002 Page 4 Alternatives: Supporting Documents: Staff Recommendation: W . This Change Order No. 5 must be approved in order for the project to progress. Change Order No. 5 Staff has reviewed this proposal and finds it to be acceptable. It is recommended that this change be approved for $5,993.64. Place the aforementioned Change Order No. 5 on the January 7, 2002 City Council Agenda for Council review and consideration. 4 CHANGE ORDER No. 5 Dated: December 11, 2001 OWNER'S Project No. 00 -3320 Architect's Project No. 415610 Project Department of Public SafetyBuilding — West Facility OWNER City ofSouthlake Contract for Construction of the DPS West Facility Contract Date: 12112100 To: CMPA, Inc Contractor You are directed to make the changes noted below in the subject contract: Southlake, Texas Owner By: Billy Campbell Title: City Manager Date: 2002 Nature of the changes: Field modifications as follows: Landscaping Modifications (RFP #2) I LS Replace Dwarf Holly with Carissa Holly @ $0.00 = $ 0.00 1 LS Irrigation system revisions @ $4,175.50 = 4,175.50 Total (RFP #2) $4,174.50 Interior Gas Line Modifications (RFP #10) 1 LS Interior gas line modifications @ $0.00 = $ 0.00 Total (RFP #10) $0.00 5 Additional 3 / " Backflow Preventer Assembly (RFP #13) 1 ea Additional baclflow preventer at sally port HVAC Duct Revisions (RFP #14) 1 LS HVAC Duct revisions Additional Phone/Data Lines (RFP #15) 2 ea Add two (2) phone /data lines Light Fixture/Ceiling Framing Conflict (RFP# 17) 1 LS Resolution of light/framing conflict Ventilating Steel Ridge Plates (RFP #18) 1 LS Cutting vents in steel ridge plates General Conditions — Contingency Change Order No. 1 Change Order No. 2 Change Order No. 3 Change Order No. 4 Change Order No. 5 Balance in Contingency @ $405.14 Total (RFP #13) n $0.00 Total (RFP # 14) @ $60.50 Total (RFP #15) n $0.00 Total (RFP #17) @ $1,293.00 Total (RFP # 18) Total Change Order No. 5 6 $405.14 $405.14 $0.00 $0.00 $121.00 $121.00 $0.00 $0.00 $1,293.00 $1,293.00 $5,993.64 $150,000.00 <$11,868.00> <$6,800.00> <$6,212.00> <$4,758.00> <$5,993.64> $114,368.36 These changes result in the lollowing adjustment of contract price and contract time: Contract Price Prior to this Change Order Net Increase Resulting from this Change Order Current Contract Price Including this Change Order $ 3,375,500.00 S 0.00 $ 3,375,500.00 Contract Time Prior to this Change Net Increase Resulting from this Change 365 days (Days or Date) (Days) Current Contract Time Including this Change Order 365 days (Days or Date) The above changes are recommended: The above changes are recommended: Phillips, SwagerAssociates Architect/Engineer By: Date: City ofSouthlake City 2002 By: Title: Construction Manager Date: . 2002 The above changes are accepted: NSPE -ASCE 1910 -8 -B (1978 Edition) CMPA, Inc. Contractor Bv: Date: 2002 7