Item 4HItem 4HApprove Guaranteed Maximum Price w/ Dean Constructionin the amount of $6,631,811.66 for Construction of North Park
Chris Tribble
Director of Community Services
Background
June 2009 – Hired SRA
Nov 2009 – SPIN Meeting
Feb 2010 – PB and P&Z Site Plan
May 2010 – CC Approved Site Plan
Aug 2010 - FY11 SPDC CIP Proj #4
Nov 2010 – Hired Dean as CMR
Jan 2011 – Bids Opened GMP Est.
Mar 2011 – Anticipate Construction
Mar 2012 – Anticipate Completion
Financial Considerations
CMR is bound to an agreed GMP that is determined from actual advertised bids received January 19, 2011
Additional Information
SPDC and Parks Board will consider at Joint SPDC/Parks Board meeting February 15, 2011