Item 4H AudioSOUTHLAKE
1 5
Item 4H
Approve Guaranteed Maximum Price
w/ Dean Construction
in the amount of $6,631,811.66
for Construction of North Park
Integrity
Innovation
Accountability Chris Tribble
Commitment
to Excellence Director of Community Services
Teamwork
1
Background - Timeline
• Site Plan approved May 2010
• FY11 SPDC CIP Project #4
• Several public meetings held
since 2009
• Dean Electric selected as
Construction Mgr At Risk (CMR)
November 2010
• Bid Project & Approve GMP
January 2011
• Construction begin March 2011
• Completion March 2012
9 SOUTHLAKE
r -
- - -- r
T
E
3
Financial
Considerations
• CMR is bound to an agreed
GMP that is determined from
actual advertised bids received
January 19, 2011
NORTH PARK PROJECT BUDGET
SUMMARY:
SPDC CIP Fundin
$6,666.000.00
CCPD CIP Fundin
$517,930.87
Total Project Fundin
Amount Under Budget
$67,119.21
`Includes Engineering, Design & Construction
Costs
91 SOUTHLAKE
SPDC Project Cost'
$6,598,880.79
CCPD Project Cost
5517.930.87
$7,183,930.87
SPDC Project Cost'
$6,598,880.79
CCPD Project Cost
5517.930.87
Total Project Cost
$7,116,811.66
D
Additional Information
• SPDC and Parks Board will consider at
Joint SPDC /Parks Board meeting
February 15, 2011
0 SOUTHLAKE
5
SOUTHLAKE
1 5
Questions?