Item 4MItem 4M Approve the Utility Adjustment Agreement Amendment to the DFW Connector Master Utility Adjustment Agreement in the amount of $156,859.58 for design and construction of the
relocation of City water and wastewater utilities for the DFW Connector project
Requested Action
Approve the Utility Adjustment
Agreement Amendment to the DFW Connector Master Utility Adjustment Agreement in the amount of $156,859.58
for design and construction of the
relocation of City water and wastewater utilities for the DFW Connector project
DFW Connector
Water Line Relocation
Waterwater Relocation
Background Information
Master Utility Adjustment Agreement (MUAA)
– Approved by Council November 16, 2010
Utility Adjustment Agreement Amendment
– supplement to the MUAA
outlines the estimated costs of design and construction and terms of reimbursement from the city to North Gate Constructors
Financial Considerations
TxDOT relocation cost responsibility
50% of relocation costs for utilities within the existing ROW
100% of relocation costs for utilities outside the existing ROW
Remaining share is the responsibility of the city PLUS any betterment
Final reimbursement from the city will be based on the actual costs incurred during construction.
The costs for the design and construction of the utility relocations is as follows:
Total Construction Cost $324,916.91
Southlake’s Share* $120,856.58
Betterments to the system $36,003.00
Total $156,859.58
North Gate’s Share* $168,057.33
*based on eligibility ratio
Financial Considerations
Questions?