Approve amendment to the TxDOT Advance Funding Agreement for the FM1709 Median Project in the amount of $187,286.80
Requested Action
Approve amendment to the TxDOT Advance Funding Agreement for the FM1709 Median Project in the amount of $187,286.80
Amendment to TxDOT Advance Funding Agreement
Amendment to the AFA for irrigation design changes
Irrigation piping changed to provide sleeves under median noses
Valves and control system changes
Added gate valves
Original Agreement approved by the City Council on September 15, 2009
TxDOT construction on-going
Amendment to TxDOT Advance Funding Agreement
Irrigation System Change Order $165,740.53
TxDOT Admin Costs (City Funded) $ 21,546.27
Total Cost $187,286.80
Median and Irrigation Funding by Southlake