Item 6I
Northeast Tarrant Pipeline
Southlake, Texas
Southlake Pipeline Facts
Carbon Steel Pipe
6.625-inch diameter with.280-inch wall thickness minimum
Length of Pipe
6” - 2 Miles
Route Construction –Horizontal Directional Drill (HDD) and Trenching
Pipeline Ground Cover:
HDD: approximately 10 -15 foot depth
Other areas: minimum 4 foot depth
Low-pressure pipeline with a N.O.P. of 330 psi
Pipeline Information Hotline:1-866-826-2081
HDD Installation Process
First Step – Drill Pilot Hole
Second Step – Enlarge Hole (Ream)
Third Step – Pull Back (Install Pipe)
Pipeline Information Hotline:1-866-826-2081
Because safety is our top priority, we will …
Design and construct the pipeline to Department of Transportation regulations;
Install high-strength carbon steel pipe;
X-ray every weld that joins each section of pipe;
Bury the pipeline with adequate ground cover and identify with aboveground markers;
Participate in the One Call System
Hydrostatically test each section of pipeline at much higher pressures than the proposed operating pressure of the pipeline before putting it into service;
Test pressure will reach 5 times the Normal Operating Pressure
Use valves to allow sections of the pipeline to be isolated for maintenance or repair
if necessary;
Employ only experienced and qualified construction contractors and inspection personnel to perform and monitor all stages of construction.
Department of Transportation statistics demonstrate that pipelines are by far the safest form of energy transportation.
SAFETY
Pipeline Information Hotline:1-866-826-2081
SAFETY
Pipeline Information Hotline: 1-866-826-2081
6” Pipeline Route
Pipeline Information Hotline:1-866-826-2081
Thank You
Pipeline Information Hotline:
1-866-826-2081