Item 6BCity of Southlake
Department of Planning & Development Services
S T A F F R E P O R T
April 11, 2007
ZA06-187
CASE NO:
Site Plan for Masco Service Corporation
PROJECT:
REQUEST: On behalf of Masco Service Corp., Hammers & Partners: Architecture, Inc. is
requesting approval of a site plan. The plan proposes the development of a 12,675
square foot building for offices and repair and assembly of electronic parts on
approximately 1.49 acres of an overall 4.01 acre tract. The property is located at 1200
N. Kimball Avenue. Masco Service Corp. currently occupies the existing building on
the property and has outgrown the facility.
The following variance is being requested:
Driveway stacking depth - The minimum stacking depth required for this site is 75
feet. The applicant is providing approximately 5 feet of stacking.
Building articulation - The applicant is requesting approval of the building design as
submitted.
Staff has recommended aligning the proposed drive with the existing street
Tumbleweed Trail across N. Kimball Avenue. The proposed drive is offset from the
existing street Cripple Creek Trail approximately 113 feet. The applicant has addressed
the recommendation in their variance request letter included as part of Attachment C.
At the March 6, 2007 City Council meeting, the applicant requested to table the case to
allow time to address the following:
Item Comments
Revise the elevations of the building to better fit Revised the exterior materials from a primarily
1.
the residential character of the areaconcrete masonry unit veneer to a 100% stone veneer
Change from Hardi Plank Siding to Portland cement
plaster with vertical reveals
Although not requested by Council, the applicant
revised the Landscape Plan by incorporating a
curvilinear design in front of the building
Case No.
ZA06-187
At the April 3, 2007 City Council meeting, the applicant requested to table the case to
allow time to address the following:
Item Comments
1.Provide a better rendering of the building and The applicant will be presenting revised renderings
photos of other similar projects, specifically and images at the City Council meeting.
showing the wires & vine growth
2.Change the screening along the north & west The applicant has revised the screening to be an
property lines to be an evergreen screen 8-feet in evergreen screen. The Landscape Plan has been
height revised showing the screen and the types of plant
materials to be used.
3.Label the berm height and width on the site plan The applicant has labeled the berms on the Landscape
and add boulders on the berm Plan to be a maximum of 24-inches in height and
being approximately 44 feet in length and 10 feet in
width. A total of 4 landscape boulders are provided at
the end of each berm.
4.Provide exhibits of the perimeter screening and The applicant will be presenting exhibits for the
the berm screening and the berm at the City Council meeting.
Change the 5-gallon plants to be larger than 5-The applicant has not identified an increase in plat size
5.
gallon in size along the N. Kimball Ave frontageand will be discussing the issue at the meeting.
1. Conduct public hearing
ACTION NEEDED:
2. Consider site plan approval
ATTACHMENTS: (A) Background Information
(B) Vicinity Map
(C) Plans and Support Information
Site Plan Review Summary No. 6, dated April 11, 2007
(D)
(E) Surrounding Property Owners Map
(F) Surrounding Property Owners Responses
(G) SPIN Meeting Report
(H) Full Size Plans (for Commission and Council Members Only)
STAFF CONTACT: Ken Baker (748-8067)
Ben Bryner (748-8602)
Case No.
ZA06-187
BACKGROUND INFORMATION
OWNER: Masco Service Corporation
APPLICANT: Hammers & Partners: Architecture, Inc.
PROPERTY SITUATION: 1200 N. Kimball Avenue
LEGAL DESCRIPTION: Tract 2A3, situated in the F. Throop Survey, Abstract No. 1511
LAND USE CATEGORY: Medium Density Residential with a T-2 Transition District overlay option.
CURRENT ZONING: “B-1” Business Service Park District
HISTORY: The City of Southlake placed the "B-1" zoning on the property with approval of
Comprehensive Zoning Ordinance No. 480 on September 19, 1989.
TRANSPORTATION
Master Thoroughfare Plan
ASSESSMENT:
The Master Thoroughfare Plan recommends N. Kimball Avenue to be a 2-lane,
undivided roadway with 88 feet of right-of-way. Adequate right-of-way is
being dedicated for this road.
Existing Roadway Network
The proposed site will have one (1) access directly onto N. Kimball Avenue.
The drive is proposed to be a full access drive. A future common access
easement is conceptually shown to provide a future access to the site from E.
Highland Street. A common access is shown to provide access to the existing
parking spaces adjacent to N. Kimball Avenue for the existing building. The
two existing, non-conforming drives are proposed to be eliminated as part of
this site plan proposal.
N. Kimball Avenue is currently a two lane, undivided thoroughfare.
May, 2006 traffic counts on N. Kimball Ave (between Highland St &
Dove St)
24hr 4,1863,907
North Bound (NB) () South Bound (SB) ()
NB 226424
Peak A.M. () Peak P.M. ()
5:15 – 6:15 p.m.
11:15 – 12:15 a.m.
SB 432296
Peak A.M. () Peak P.M. () 4 – 5 p.m.
7:15 – 8:15 a.m.
Case No. Attachment A
ZA06-187 Page 1
Traffic Impact
Use Sq. Ft. Vtpd* AM-AM-PM-PM-
IN OUT IN OUT
Office 12,675 140 17 2 3 16
*Average Vehicle Trips Per Day
*The AM/PM times represent the number of vehicle trips generated during the peak travel times
on E. Highland St.
PATHWAYS
MASTER PLAN: The Pathways Master Plan recommends a 6-foot sidewalk along the west side
of N. Kimball Avenue. The sidewalk is shown on the site plan. A 5-foot
sidewalk is conceptually shown along the north side of E. Highland Street.
WATER & SEWER: A 6-inch water line currently exists along the west side of N. Kimball Avenue
and along the north side of E. Highland Street. The applicant is proposing to
extend a sanitary sewer line north from an existing 6-inch sanitary sewer line
that exists in Shady Lane.
DRAINAGE ANALYSIS: Drainage from this site will be to a proposed underground detention basin
which will discharge into the existing drainage sewer system in N. Kimball
Avenue.
TREE PRESERVATION: The applicant is proposing to take existing tree credits for the required
landscaping within the north and west bufferyard areas. Credits shall only be
granted if the tree/s are in healthy condition and all requirements of the Tree
Preservation Ordinance have been met as determined by the Landscape
Administrator at the time of inspection for a Permanent Certificate of
Occupancy.
Consolidated Land Use Plan Recommendations
SOUTHLAKE 2025:
The underlying Land Use Designation is Medium Density Residential and the
optional designation is T-2.
Site Specific Comments
The S.H. 114 Corridor Plan recommends limiting incompatible non-residential
uses permitted under the current zoning.
Southlake Pathways Plan Recommendations
The required 6 ft. sidewalk along Kimball Avenue is shown on the site plan. A
5 ft. sidewalk along East Highland Street is also shown on the plan.
P&Z ACTION: February 22, 2007; Approved (6-0) subject to Site Plan Review Summary No.
3, dated February 16, 2007; granting the variance to driveway stacking depth;
granting the variance to building articulation; and requiring the access easement
to be tied into the existing driveway off of E. Highland Street.
Case No. Attachment A
ZA06-187 Page 2
COUNCIL ACTION: March 6, 2007; Approved (6-0) to table this item at the applicant’s request to
the March 20, 2007, City Council meeting.
Prior to the March 20, 2007 meeting, the applicant requested to table this item
to the April 3, 2007 meeting.
April 3, 2007; Approved (7-0) to table this item at the applicant’s request to the
April 17, 2007, City Council meeting.
STAFF COMMENTS: Attached is Site Plan Review Summary No. 6, dated April 11, 2007.
N:\Community Development\MEMO\2006cases\06-187SP.doc
Case No. Attachment A
ZA06-187 Page 3
Case No. Attachment B
ZA06-187 Page 1
Case No. Attachment C
ZA06-187 Page 1
Overall Concept Plan
Case No. Attachment C
ZA06-187 Page 2
Previously Submitted Site Plan
Case No. Attachment C
ZA06-187 Page 3
Revised Site Plan
Case No. Attachment C
ZA06-187 Page 4
Previously Submitted Landscape Plan
Case No. Attachment C
ZA06-187 Page 5
Revised Landscape Plan
Case No. Attachment C
ZA06-187 Page 6
Elevations
Case No. Attachment C
ZA06-187 Page 7
Case No. Attachment C
ZA06-187 Page 8
Case No. Attachment C
ZA06-187 Page 9
Case No. Attachment C
ZA06-187 Page 10
Case No. Attachment C
ZA06-187 Page 11
Case No. Attachment C
ZA06-187 Page 12
Tree Conservation Plan
Case No. Attachment C
ZA06-187 Page 13
SITE PLAN REVIEW SUMMARY
ZA06-187Six04/11/07
Case No.: Review No.: Date of Review:
Site Plan
Project Name: - MASCO Service Corp
APPLICANT: Masco Service Corp. ARCHITECT: Hammers + Partners
Jeff Massey Shane Bostick
1200 N. Kimball Ave 501 Second Ave, Suite 1000-A
Southlake, TX 76092 Dallas, TX 75226
Phone: (817) 481-8205 Phone: (214) 370-8100
Fax: (817) 488-8918 Fax: (214) 370-8102
CITY STAFF HAS REVIEWED THE ABOVE REFERENCED PROJECT RECEIVED BY THE CITY ON 04/10/07 AND WE
OFFER THE FOLLOWING STIPULATIONS. THESE STIPULATIONS ARE HEREBY MADE CONDITIONS OF SITE PLAN
APPROVAL UNLESS SPECIFICALLY AMENDED BY THE CITY COUNCIL. IF YOU HAVE ANY QUESTIONS OR NEED
FURTHER CLARIFICATION, PLEASE CONTACT BEN BRYNER AT (817) 748-8602.
1.Label the required lengths of the bufferyards in the "Length" column of the Bufferyard Calculation
Chart. Required lengths equal the length of the property lines.
2.The following changes are needed with regard to ingress/egress driveways:
a.Label the stacking depth being provided for the site. Staff measures ±5' for the stacking depth.
b.Provide the minimum stacking depth for the proposed drive. A minimum stacking depth of 75'
(A variance
is required based on the site having more than 50 spaces with only one driveway.
has been requested.)
3.Provide horizontal and vertical articulation meeting the requirements of Ord. 480, Section 43.13 (a)(4)
on all facades of the building. Based on a wall height of 9'-4", the maximum length permitted for a
wall and roof line is 28'. After full evaluation of the elevations, staff feels that the design of the
(A variance has been
building, with its unique roof line, does not comply with vertical articulation.
requested.)
INFORMATIONAL COMMENTS
* A fully corrected plan that includes all associated support plans/documents and conditions of
approval is required before any ordinance or zoning verification letter publication or before
acceptance of any other associated plans for review. Plans and documents must be reviewed
and stamped “approved” by the Planning Department.
* All development must comply with the City’s Drainage Ordinance No. 605 and detain all post
development run-off.
Case No. Attachment D
ZA06-187 Page 1
* All buildings must be designed such that no mechanical equipment shall be visible. This shall include
equipment on the roof, on the ground, or otherwise attached to the building or located on the site.
Refer to Section 43.13(a)(3).
* The proposed site does not exceed the maximum permitted impervious coverage area percentage of
70% for the "B-1" Zoning District. The impervious coverage area percentage of this is approximately
70%.
* No review of proposed signs is intended with this site plan. A separate building permit is required prior
to construction of any signs.
* The applicant should be aware that prior to issuance of a building permit a Plat must be processed and
filed in the County Plat Records, a fully corrected site plan, landscape plan, irrigation plan, and
building plans, must be submitted for approval and all required fees must be paid. This may include but
not be limited to the following fees: Park Fee, Perimeter Street Fee, Water & Sewer Impact and Tap
Fees, and related Permit Fees.
Case No. Attachment D
ZA06-187 Page 2
Case No. ZA06-187 Review No. 3 Dated: 4/11/07 Number of Pages: 1
Project Name: Masco Service Corp. -- Site Plan
Contact: Cheryl Taylor, Civil Engineer Phone: (817) 748-8100 Fax: (817) 748-8077
Email: ctaylor@ci.southlake.tx.us
The following comments are based on the review of plans received on 2/8/2007. It is the applicant’s
responsibility to contact the department representative shown above and make modifications as required by the comment.
GENERAL COMMENTS:
* Use the City of Southlake GPS monuments whenever possible.
WATER AND SANITARY SEWER COMMENTS:
* Fire hydrants and water meters must be located in an easement or in the ROW.
* Fire lines shall be separate from the service lines.
* Sanitary sewer manholes are required at 500’ maximum spacing and at the end of all public sewer lines.
DRAINAGE COMMENTS:
* All storm sewer pipes within the ROW shall be RCP.
* Proposed driveway culverts must be sized by an engineer and submitted for approval to the City
Engineer.
* This property does not drain into a Critical Drainage Structure.
* The discharge of post development runoff must have no adverse impact on downstream properties and
meet the provisions of Ordinance # 605.
INFORMATIONAL COMMENTS:
* Submit civil construction plans (22” X 34” full size sheets) directly to the Public Works Administration
Department for review. The plans shall conform to the most recent construction plan checklist, standard
details and general notes which are located on the City’s website.
http://www.cityofsouthlake.com/PublicWorks/engineeringdesign.asp
* A ROW permit shall be obtained from the Public Works Operations Department (817) 748-8082
to connect to the City’s sewer, water or storm sewer system.
* A Developer’s Agreement will be required for this development and may need to be approved by the City
Council prior to any construction of public infrastructure. Construction plans for these improvements must
be approved by Public Works prior to placing the Developer’s Agreement on the City Council agenda for
consideration.
* Any hazardous waste being discharged must be pretreated Ordinance No. 836.
* This review is preliminary. Additional requirements may be necessary with the review of
construction plans.
*=Denotes informational comment.
Case No. Attachment D
ZA06-187 Page 3
Case No Review No.Dated: Number of Pages:
. 06-187 Three April 11, 2007 1
Project Name:
Masco Service Corp. (Site Plan)
ContactPhone:Fax:
: Keith Martin (817) 748-8229 (817) 481-5713
===========================================================================
The following comments are based on the review of plans received on February 5, 2007 . Comments
designated with a number may be incorporated into the formal review to be considered by either the
Planning and Zoning Commission or City Council. Other items will not be addressed by either the P&Z
or City Council. It is the applicant’s responsibility to contact the department representative shown above
and make modifications as required by the comment.
===========================================================================
TREE CONSERVATION COMMENTS:
1. The applicant is proposing to take existing tree credits for the required landscaping within the north and
west bufferyard areas. Credits shall only be granted if the tree/s are in healthy condition and all
requirements of the Tree Preservation Ordinance have been met as determined by the Landscape
Administrator at the time of inspection for a Permanent Certificate of Occupancy.
Case No. Attachment D
ZA06-187 Page 4
COMPREHENSIVE PLAN REVIEW SUMMARY
ZA06-187/023Three4/11/07
Case No: Review No.: Date of Review:
Project: Masco Service Corp.
Application Type: Site Plan and Plat Showing
Contact: Jenny Crosby Phone: (817) 748-8195 Email: jcrosby@ci.southlake.tx.us
Consolidated Land Use Plan Recommendations
The underlying Land Use Designation is Medium Density Residential and the optional designation is T-2.
Site Specific Comments
The S.H. 114 Corridor Plan recommends limiting incompatible non-residential uses permitted under the current
zoning.
Southlake Pathways Plan Recommendations
The required 6 ft. sidewalk along Kimball Avenue is shown on the site plan. A 5 ft. sidewalk along East
Highland Street is also shown on the plan.
L:\Meetings\DRC\Reviews\Comp Plan\2006\ZA06-187-3 Masco 2007-02-15.doc
Case No. Attachment D
ZA06-187 Page 5
Surrounding Property Owners
Masco Service Corp.
SPO # Owner Zoning Land Use Acreage
1. Low Density Residential
Patterson, Burton Etux Virgini SF1-A 3.992
2. Low Density Residential
Patterson, Burton Etux Virgini SF1-A 2.437
3. Low Density Residential
Huning, Eric Etux Mary SF1-A 2.614
4. Medium Density Residential
Patterson, Burton Etux Virgini AG 6.055
5. Low Density Residential
Graham, Gerald C Etux Barbara SF1-A 2.028
6. Medium Density Residential
Massey, Jeff B1 4.015
7. Medium Density Residential
Holliday, Richard Etux Mary B1 0.682
8.
City of Grapevine
Case No. Attachment E
ZA06-187 Page 1
Surrounding Property Owner Responses
Masco Service Corp.
Notices Sent: Eight (8)
Responses Receive: One (1)
Richard & Mary Holliday
, 2575 Ridgecrest Dr, submitted a Notification Response Form
Favor
in on February 15, 2007 (attached).
Case No. Attachment F
ZA06-187 Page 1
Case No. Attachment F
ZA06-187 Page 2
SPIN MEETING REPORT
CASE NO.
ZA06-187
PROJECT NAME:
Masco Service Corp.
1200 N. Kimball Avenue
SPIN DISTRICT:
5
MEETING DATE:
6:30PM, February 12, 2007
MEETING
LOCATION:
1400 MAIN STREET, SOUTHLAKE, TEXAS
MEETING ROOMS 3A & 3B
TOTAL ATTENDANCE:
Approximately Seventeen (17)
SPIN REPRESENTATIVE(S) PRESENT:
Jan Francis (5) and Lou Hillman (6)
APPLICANT(S) PRESENT:
Shane Bostick and Mack Elam of Hammers + Partners
Architecture, Inc. and Jeff Massey of Masco Service Corporation
STAFF PRESENT:
Planner Clayton Comstock
STAFF CONTACT:
Clayton Comstock, (817)748-8269; ccomstock@ci.southlake.tx.us
APPLICANT PRESENTATION SUMMARY
Masco Service Corporation Company Overview
Repairs & refurbishes helicopter parts
Company has officed in current facility since 1984
Business has outgrown current facility; workspace needs to be updated and upgraded
Workspace analysis shows 12,000 to 13,000 square feet of floor space is needed
o
Design Concepts of New Facility
Air hanger type building to represent their business in aviation industry
Focus on arches, ribbed panel roofing
o
Examples: air hangers, American Airlines Center, Kimball Art Museum
o
Incorporate traditional Southlake masonry design
Blend between steel/metal, masonry and arches
o
Low profile; not appropriate to build high in this part of Southlake
o
Practical application of office and workshop space needs
Focus on energy efficiency
Presentation of Final Design
Building to be located on a lot adjacent to the north of current facility
Building placement constrained by 60-foot power line easement running through the property
Energy efficiency
Roof window element to allow light into workshop area
o
Windowed offices placed on North and East sides to allow light in
o
South and West sides generally closed to natural light – practical placement of bathrooms, utility
o
rooms, etc. on these sides
Case No. Attachment G
ZA06-187 Page 1
SPIN MEETING REPORT – PAGE 2
QUESTIONS & DISCUSSION
What will happen to the current building you’ve been in since 1984?
QUESTION:
RESPONSE: It is under contract to be sold for office space for a local company that owns boat marinas.
How many employees work at the current facility? How many will be employed at the new
QUESTIONS:
facility? About how many employees will the marina company have? Will there be a net
increase in the total number of people working on the two properties?
RESPONSE: Masco currently has 35 employees working at its current facility and 45 are to be officed at the new
site. The marina company employs about six (6), so there will be an increased head count of
approximately 15-20 people on the two sites combined.
What material will be used for the roofing?
QUESTION:
RESPONSE: The innermost layer will be 22-gauge steel ribbed paneling like that of an airline hanger. The
outermost layer will be a regular standing seam metal roof with a dark gray matte finish. A layer of
insulation will be added for energy efficiency.
The use of standing seam metal on such a long roof.
CONCERN:
How will the property have vehicular and pedestrian access?
QUESTIONS*:
RESPONSE: The property will have driveway access on to N. Kimball Avenue to the east and access to the south
to E. Highland Street by means of a common access easement through the property to the south (the
current Masco facility). The access to the south will not be built with the current improvements,
and will only be necessitated by the future street improvements on Kimball Ave. Sidewalks will be
placed within the dedicated Rights-of-Way (R.O.W.) of E. Highland Street and N. Kimball Avenue.
Are the building setbacks on Kimball measured from the current R.O.W. or the new, proposed
QUESTION:
R.O.W.?
RESPONSE: Building setbacks along Kimball are measured 30-feet from the new R.O.W.
Future widening and placement of medians on Kimball – property will not have left-turn access
DISCUSSION:
from north-bound Kimball.
Future development of Gateway Church, traffic in the area and the placement of Kirkwood
DISCUSSION:
Boulevard extension.
Is the property on septic or sewer?
QUESTION:
RESPONSE: The property is currently on a septic system, but sewer will be extended to service the site.
How and how often do you dispose of solvents used in your operations?
QUESTION:
RESPONSE: They are stored on site until a service comes and collects them. We have only required the service
about once every five years.
* A summarized combination of questions on the same subject.
SPIN Meeting Reports are general observations of SPIN Meetings by City staff and SPIN Representatives. The report is neither
verbatim nor official meeting minutes; rather it serves to inform elected and appointed officials, City staff, and the public of the issues
and questions raised by residents and the general responses made. Responses as summarized in this report should not be taken as
guarantees by the applicant. Interested parties are strongly encouraged to follow the case through the Planning and Zoning Commission
and final action by City Council.
Case No. Attachment G
ZA06-187 Page 2