Item 4BItem 4B
Approve Amendment No. 3 to the existing Professional Services Agreement for design services on the FM1709 sidewalks with Jacobs Engineering Group in the amount of $49,130.00
FM1709 Sidewalks
Site Location
FM1709 Sidewalks
Original Contract – Feb, 2009
Amendments No. 1 & 2– Nov 09 & May 10
Amendment No. 3 - $49,130
2010 State Transportation Enhancement Program - $1.7M Grant
Repackage construction
TxDOT plan format
Requires TxDOT approval
Amendment No. 3
Original Contract $138,750
Amendment No. 1 $ 30,080
Amendment No. 2 $ 7,200
Amendment No. 3 $ 49,130
$ 86,410*
Total Contract Amount $225,160
* $86,410 is above the City Manager’s signatory authority
Funding
Design – CIP Funds Authorized
Construction – 2010 State Transportation Enhancement Program
$1.7M matching grant for construction only
Engineering is not reimbursable
For schedule. Click Here
Recommendation
Approve Amendment No. 3 to the existing Professional Services Agreement for design services on the FM1709 sidewalks with Jacobs Engineering Group in the amount of $49,130.00
Questions?
FM1709 Sidewalks
Original contract – $138,750
February, 2009
3.3 miles of sidewalk along FM1709 from Pearson Lane to Commerce Street
Survey, construction documents, SWPPP, and traffic control plan
FM1709 Sidewalks
Amendment No. 1 – $30,080
Administrative approval – November, 2009
Repackage plans for phased bidding - 2009 Priority Sidewalks
Amendment No. 2 – $7,200
Administrative approval – May, 2010
2009 Priority Sidewalks – revisions to plans, TxDOT and TDLR submittal
TxDOT permit approved for construction
Project Schedule
Design
Incorporate all sidewalks
1st Qtr 2011
Plans to TxDOT Area Office for Review
1st Qtr 2011
Construction begins
3rd Qtr 2011