Item 4HITEM 4I
Approve Change Order No. 4 with Circle C Construction in the amount of $62,551.41 for a 30-inch water line on T.W. King
Location Map
Approve Change Order No. 4 with Circle C Construction
Project is now complete
Proposed Change Order No. 4
Reconcile actual pay item quantities
Additional driveway repairs
Additional block sod
Additional paving quantities
Approve Change Order No 4 with Circle C Construction
Original Contract $2,635,235.00
Change Order 1 400.00
Change Order 2 (152,466.80)
Change Order 3 30,007.50
Change Order 4 62,551.41
Net Change Order (59,507.89)
Total Contract Amount $2,575,727.11
Original Project Budget $2,898,800.00
RECOMMENDATION
Approve Change Order No. 4 with Circle C Construction in the amount of $62,551.41 for a 30-inch water line on T.W. King
Questions?
Bob Price
817-748-8097
Location Map
Location Map
Approve Change Order No 4 with Circle C Construction
Background
March 2009 – City Council awarded construction contract to Circle C Construction in the amount of $2,635,235.00
June 2009 – Change Order No. 1 approved by City Manager’s office in the amount of $400 eliminated a 12-inch gate valve and added a 12-inch tapping sleeve and valve to allow the water
line to stay in service
Approve Change Order No 4 with Circle C Construction
Background
December 2009 – Change Order No. 2 approved by City Manager’s office in the amount of ($152,466.80) for revised paving design for Florence Road and TW King Road
March 2010 – Change Order No. 3 approved by City Manager’s office in the amount of $30,007.50 for driveway repairs due to paving activities