Item 4F Department of Planning & Development Services S T A F F R E P O R T January 9, 2008 ZA07-156 CASE NO: Preliminary Plat for Lots 1 – 8, Block 1, Kimball Lake Office Park PROJECT: REQUEST: On behalf of Vision Southlake Development, McInnis Land Consultants, LLC is requesting approval of a preliminary plat for Kimball Lake office Park. The plan proposes eight (8) lots on approximately 14.46 acres for office development. The preliminary plat is consistent with the approved zoning and site plan. With the exception of variances approved with the zoning and site plan, no additional variances are requested with the preliminary plat. Consider preliminary plat approval ACTION NEEDED: ATTACHMENTS: (A) Background Information (B) Vicinity Map (C) Plans and Support Information Plat Review Summary No. 2, dated December 28, 2007 (D) (E) Surrounding Property Owners Map (F) Surrounding Property Owners Responses for Commission and Council Members Only (G) Full Size Plans () STAFF CONTACT: Ken Baker (748-8067) Dennis Killough (748-8072) Case No. ZA07-156 BACKGROUND INFORMATION OWNER: Vision Southlake Development APPLICANT: McInnis Land Consultants, LLC PROPERTY SITUATION: 600 N. Kimball Avenue LEGAL DESCRIPTION: Tract 3B, T. Mahan Survey, Abstract No. 1049 LAND USE CATEGORY: Mixed Use with an Employment Center Residential optional overlay CURRENT ZONING: S-P-2 Detailed Site Plan District and AG Agricultural District HISTORY: -City Council approved a change of zoning and site plan for Kimball Lake Office Park on December 4, 2007. TRANSPORTATION Master Thoroughfare Plan ASSESSMENT: The Master Thoroughfare Plan recommends N. Kimball Avenue to be a 4-lane, divided arterial street with 88 feet of right-of-way. Right-of-way is shown on the plan and will be dedicated as part of the platting process. Existing Area Road Network and Conditions The proposed development is proposing two (2) driveways onto N. Kimball Avenue. All proposed lots are connected through proposed common access easements. North Kimball Avenue is currently a 2-lane, undivided roadway. Plans for widening this section of N. Kimball Avenue have been approved and construction should begin soon. May 2006 traffic counts on N. Kimball Ave (between SH 114 and Highland St) 24hr 5,2904,781 North Bound (NB) () South Bound (SB) () NB 298551 Peak A.M. () Peak P.M. () 6:00—7:00PM 11:15—12:15AM SB 468346 Peak A.M. () 7:30 – 8:30 AM Peak P.M. () 3:30 – 4:30 PM PATHWAYS MASTER PLAN: The Pathways Master Plan recommends an 8-foot multi-use trail along the west side of N. Kimball Avenue. The trail was shown on the site plan. WATER & SEWER: A 12-inch water line exists along the east side of N. Kimball Avenue. A 12-inch sanitary sewer line exists along the west side of N. Kimball Avenue. DRAINAGE ANALYSIS: This site will drain to a temporary detention pond until such time as the Gateway Church project is completed. The developers of these projects have an agreement stipulating that the Gateway Church project drainage facilities will account for drainage from the Kimball Lake Office Park site. The proposed temporary detention pond will detain storm water and release it into North Kimball Avenue until the Gateway Church facilities are constructed. Case No. Attachment A ZA07-156 Page 1 TREE PRESERVATION: The submitted Tree Conservation Plan does not break down the amount of existing tree canopy to be preserved and the percentage to be removed. Instead, information is provided on the percentage of existing trees that are proposed to be preserved and percentage proposed to be removed. Across the entire site 75.81 % of the existing trees are proposed to be preserved. In Phase 1 of the development all of the existing trees are proposed to be removed. Consolidated Land Use Plan Recommendations SOUTHLAKE 2025: The underlying designation is Mixed Use and the optional designation is Employment Center Residential. Office uses are consistent with the Mixed Use designation. Mobility & Master Thoroughfare Plan/Southlake Pathways Plan Recommendations A 6 foot sidewalk is required along Kimball Avenue per the Southlake Pathways Plan. The applicant is proposing an 8 foot trail along Kimball Avenue. P&Z ACTION: January 3, 2008; Approved (6-0) subject to Plat Review Summary No. 2, dated December 28, 2007, as presented. STAFF COMMENTS: Attached is Plat Review Summary No. 2, dated December 28, 2007. N:\Community Development\MEMO\2007cases\07-156PP.doc Case No. Attachment A ZA07-156 Page 2 Case No. Attachment B ZA07-156 Page 1 Approved Site Plan Case No. Attachment C ZA07-156 Page 1 Preliminary Plat Case No. Attachment C ZA07-156 Page 2 PLAT REVIEW SUMMARY ZA07-156Two12/28/07 Case No.: Review No.: Date of Review: Preliminary Plat – Kimball Lakes Office Park Project Name: APPLICANT: McInnis Land Consultants, LLC OWNER: Vision Southlake Development, LLC Dan McInnis, P.E. Steve Paulsen th 108 W. 8 Street, Suite 300 1500 E. Southlake Blvd, Suite 200 Fort Worth, TX 76102 Southlake, TX 76092 Phone: (817) 877-4200 Phone: (817) 822-1470 Fax: (817) 877-4201 Fax: (817) 424-2890 email: dan.m@mcinnisland.com CITY STAFF HAS REVIEWED THE ABOVE REFERENCED PROJECT RECEIVED BY THE CITY ON 12/17/07 AND WE OFFER THE FOLLOWING STIPULATIONS. THESE STIPULATIONS ARE HEREBY MADE CONDITIONS OF PLAT APPROVAL UNLESS SPECIFICALLY AMENDED BY THE CITY COUNCIL. IF YOU HAVE ANY QUESTIONS OR NEED FURTHER CLARIFICATION, PLEASE CONTACT BEN BRYNER AT (817) 748-8602. 1. All lots must comply with the underlying zoning on the property. Lot 8 is zoned “AG” Agricultural District which requires a minimum lot size of 10 acres. No development activity may occur on Lot 8 as shown without an approved change of zoning to an appropriate zoning district. 2. The following changes are needed with regard to easements: a. Where adjacent property is unplatted or platted showing a 5' U.E., provide a 5' U.E. along the property line; if adjacent property is platted and shows no easement, provide a 10' U.E. along Although the subdivision ordinance requires minimum 5 to 10 the interior of the property line. foot wide easements along the perimeter of the subdivision, staff recommends that easements only be provided where needed. b. Provide easements for water, sewer and/or drainage in compliance with approved construction plans. INFORMATIONAL COMMENTS * A fully corrected plan that includes all associated support plans/documents and conditions of approval is required before any ordinance or zoning verification letter publication or before acceptance of any other associated plans for review. Plans and documents must be reviewed and stamped “approved” by the Planning Department. * All development must comply with the City’s Drainage Ordinance No. 605 and detain all post development run-off. * It appears this property lies within the 65 LDN D/FW Regional Airport Overlay Zone, requiring construction standards in compliance with the Airport Compatible Land Use Zoning Ordinance No. 479. Additionally, the “Avigation Easement and Release” shown in Appendix 3 of the Subdivision Ordinance No. 483 should be executed on subsequent Plats to be filed in the County Plat Records. * A Developers Agreement is required prior to construction of any public infrastructure. The Developer's Agreement for this addition should consider streets, drainage, park dedication requirements and fees, off-site sewer extensions, off-site drainage and utility easements and impact fees. Case No. Attachment D ZA07-156 Page 1 Public Works – Engineering DRAINAGE COMMENTS: 1. The preliminary drainage plan refers to the drainage plan prepared for the Kirkwood Road extension project. These tracts do appear on the preliminary drainage plans for the Kirkwood project, however the Kirkwood drainage plan does not include drainage coefficients for these tracts consistent with the type of development being proposed (i.e., office / commercial). The applicant has agreed to coordinate drainage plans with the Gateway Church project 2. The preliminary grading plan shows a temporary detention facility and makes reference to future drainage improvements that will serve this development and will be constructed with the Gateway Church project. The applicant has agreed to provide a written agreement with gateway Church that acknowledges this arrangement. * This property drains into Critical Drainage Structures 14 and 15 and requires a fee to be paid prior to beginning construction. ($220.80 / Acre for structure 14 and $406.50 / Acre for structure 15). * The discharge of post development runoff must have no adverse impact on downstream properties and meet the provisions of Ordinance # 605. INFORMATIONAL COMMENTS: * Submit civil construction plans (22” X 34” full size sheets) and a completed Construction Plan Checklist directly to the Public Works Administration Department for review. The plans shall conform to the most recent construction plan checklist, standard details and general notes which are located on the City’s website. * A ROW permit shall be obtained from the Public Works Operations Department (817) 748-8082 to connect to the City’s sewer, water or storm sewer system. * A Developer’s Agreement may be required for this development and may need to be approved by the City Council prior to any construction of public infrastructure. Construction plans for these improvements must be approved by Public Works prior to placing the Developer’s Agreement on the City Council agenda for consideration. * Any hazardous waste being discharged must be pretreated Ordinance No. 836. * This review is preliminary. Additional requirements may be necessary with the review of construction plans. *=Denotes informational comment. Case No. Attachment D ZA07-156 Page 2 Surrounding Property Owners Kimball Lake Office Park SPO Owner Zoning Land Use Acreage # 1. Mixed Use Kimball Road Lp I1 1.61 2. Medium Density Residential Martin Custom Homes Llc SF20A 1.085 3. Public/Semi-Public Txu Electric Delivery Co CS 2.547 4. Mixed Use Halim, Emil A MF1 0.959 5. Mixed Use Harris, Kimberly Susan SF1-A 0.951 6. Mixed Use Ekstrom, Delton E SF1-A 1.052 7. Mixed Use Coty, Rita SF1-A 0.911 8. Public/Semi-Public St Laurence Episcopal Church CS 5.354 9. Medium Density Residential Hillman, Luther L AG 3.94 10. Medium Density Residential 579 Kimball Llc AG 8.105 11. Medium Density Residential Episcopal Diocese Of Ft Worth AG 1.026 12. Mixed Use Gateway Church NRPUD 8.593 13. Mixed Use Gateway Church NRPUD 6.614 14. Mixed Use Gateway Church NRPUD 48.972 15. Mixed Use Nci Building Systems I1 15.777 16. Mixed Use Vision Southlake Dev Llc AG 14.82 Case No. Attachment E ZA07-156 Page 1 Surrounding Property Owner Responses Kimball Lake Office Park Notices Sent: Sixteen (16) Responses Received: Zero (0). Case No. Attachment F ZA07-156 Page 1