Item 5IItem 5I2006 PMA Improvements
Award of Bid for Construction
2006 PMA Improvements
Design contract for this project was approved by Council on February 21, 2006.
Final design includes the rehabilitation of 33 streets throughout the city and the installation of minor related storm drainage improvements.
Bids received on May 2, 2006.
2006 PMA Improvements
Bids Received
Sunmount Corporation ($1,591,775.00)
Peachtree Construction ($1,620,650.00)
Reynolds Asphalt ($1,677,507.00)
JLB Contracting ($1,904,336.75)
After bid tabulation and review, the design engineer, Cheatham and Associates, recommended award to the low bidder, Sunmount Corporation.
2006 PMA Improvements
Staff Recommendations
Award of the 2006 PMA improvements to Sunmount Corporation in the amount of $1,591,775.
Approval of 10% construction contingency in the amount of $160,000
Funds available from the 05/06 CIP and residual funds from the 04/05 paving improvements for N. Pearson Ln.
Street Listing