ITEM 4I
Approve Professional Services Agreement with Freese and Nichols, Inc. for Engineering Design Services for Segments A and F of the North Water Supply Line Project
Action Requested
Background
February , 2007 – Awarded Route Study
Yielded 2 possible alignments
Preferred Route – FM 1938
Background
Segments A and F – Common to both routes
Need projected Summer 2009
Survey and Engineering work can begin
Background
29,000 L.F. - Total Project Length
7,500 L.F. – Segments A and F
Services Provided
Basic Services - $ 152,900
Special Services - $ 79,300
Total Contract Amount - $ 232,200
Financial
Design Services Funds (A & F)
$232,200
Available from previously approved CIP
Construction Phase Funds (A & F)
$ 2,709,820
Approved in previous and current CIP