DPS Headquarters Construction Bid
Item 9A
Approve Change Order #1 to the Construction Manager at Risk contract with Lee Lewis Construction, Inc. in the amount of $1,925,913 for the demolition of the existing DPS East facility,
and the civil work for the new DPS facility.
December 4, 2007
DPS Headquarters
The project plans for the construction of a new DPS Headquarters facility to house both the Police and Fire Services were presented to the City Council in April 2007.
Following that meeting, the construction documents were prepared involving a number of our staff along with a variety of technical consultants and our architect Robert Garza and Associates.
DPS Headquarters
This change order represents the initial contract for the construction of the new DPS Headquarters facility and involves the site work, utility construction and demolition of the old
facilities on the site. This work should take about 4 months to complete.
The construction manager at risk prepared the bid documents and bids were received on 15 November 2007.
Following the opening the bids were analyzed to determine the lowest and best bid.
The contract is actually with the construction manager at risk and cannot exceed the amount of the change order.
DPS Headquarters
The change order was reviewed by the Crime Control Board on 27 November 2007
The Crime Control Board voted 6 to 0 to recommend the change order for Lee Lewis Construction, Inc. in the amount of $1,925,913.
DPS Headquarters
The original estimate for this portion of the construction was $1,985,880
The bid recommended is $1,925,913 and is approximately $60,000 below the estimate
Innovation ◊ Integrity ◊ Accountability ◊ Commitment to Excellence ◊ Teamwork
Questions?
Jim Blagg ext. 8601