Authorize a professional services agreement with Teague Nall and Perkins, Inc.
for
drainage improvements on Dove Road from Carroll Avenue to Dove Creek
Action Requested
Project Purpose
Insufficient Drainage Capacity
Water Over Road
Road Closures
Provide outfall for Dove and Carroll Roundabout Drainage
Dove Road Drainage Improvements
Project Location
Dove Road Drainage ImprovementsCarroll Ave. to Dove Creek
Feasibility Study Completed
December 2007
Enclosed Storm Sewer System
8 ft. x 5 ft. Box Culvert Construction
Funding Source
Design - FY 2008 Stormwater CIP Funds
Project Budget
Basic Services
Task 1 - Prelim. & Final Design $143,300
Task 2 – Bid & Construction Admin 25,100
Subtotal – Basic Services $168,400
Special Services
Task 3 – Public Involvement $10,500
Task 4 – Design & Property Surveys 70,700
Subtotal – Special Services $81,200
TOTAL DESIGN FEE $249,600
Project Schedule
Design Completion – 2nd Quarter 2008
ROW & Utility – 3rd Quarter 2008
Construction Begin – 3rd Quarter 2008
Construction Complete – 4th Quarter 2008