Award of bid for Bob Jones Park parking lot overlay to Peachtree Construction Ltd., in an amount not to exceed $160,295
Bob Jones Parking Lot Overlay Project
FY 2008 SPDC CIP Budget includes funding ($200,000) for 2’’ asphalt parking lot overlay (N & S soccer parking lots)
9 bids rec’d with low bid from Peachtree Construction, Ltd. ($145,722.80)
Cheatham & Associates - verified contractor qualifications & recommends awarding to Peachtree Construction, Ltd.
Includes 10% construction contingency for total project budget of $160,295.
Bob Jones Parking Lot Overlay Project
Bob Jones Parking Lot Overlay Project
Project within approved budget
Parks Board approved unanimously at their January 14, 2008 meeting
SPDC to consider at their Feb. 5, 2008 meeting
Staff is available for questions and seeks City Council approval