Item 4D
Approve amendment no. 1 to the professional services agreement with Graham and Associates, Inc. for engineering for the construction documents and right-of-way documents for F.M. 1938,
Precinct Line Road from State Highway 114 to West Southlake Boulevard
Action Requested
Additional Engineering Fee Request
Project delays
Increase in construction costs
Changes in construction phasing approach
Engineering challenges
Additional Engineering Fee Request
Splitting construction plans into 2 phases $ 80,000
Additional right-of-way research, surveys,
strip map revisions, etc. 56,150
Offsite drainage analysis and plans 68,295
Environmental assessment (Phases I & II) 42,297
Total of Additional Engineering Costs $246,742
Additional Funding
Provided by Tarrant County Precinct 3 Commissioner Gary Fickes
County Precinct 3 discretionary funds
No additional costs to cities
RECOMMENDATION
Approve amendment no. 1 to the professional services agreement with Graham and Associates, Inc. for engineering for the construction documents and right-of-way documents for F.M. 1938,
Precinct Line Road from State Highway 114 to West Southlake Boulevard