Item 4EItem 4E
Approve Change Order No. 4 for the South White Chapel Boulevard / Continental Boulevard Intersection Improvements project with Quality Excavation, Ltd. in the amount of $36,254.05
S. White Chapel Blvd./Continental Blvd. Intersection Improvements
Approve Change Order No. 4 with Quality Excavation, LTD
Background:
Contract awarded to Quality Excavation, Ltd. - May 2009
Approve Change Order No. 4 with Quality Excavation, LTD
Previous change orders approved by the City Manager bring the total to $56,587.52 which is above the City’s Manager’s signatory authority:
Change Order No. 1 (Jul. 2009) $7,583.47
Change Order No. 2 (Aug. 2009) $11,250.00
Change Order No. 3 (Dec. 2009) $1,500.00
Change Order No. 4 (May 2010) $36,254.05
Total $56,587.52
Change Order No. 4 is for the reconciliation of
miscellaneous changes during construction,
including:
Additional electronic message boards to notify commuters of lane closures and traffic delays due to construction
Temporary pavement, as needed, to allow the intersection to remain open to traffic during construction of the roundabout
Approve Change Order No. 4 with Quality Excavation, LTD
Approve Change Order No. 4 with Quality Excavation, LTD
Previous Contract Amount $536,387.68
Proposed Change Order No. 4 $36,254.05
Total Contract Amount $572,641.73
Funds for construction of the project, including this change order, are budgeted in the FY 2008, FY 2009 and FY 2010 Capital Improvement Program
Recommendation
Approve Change Order No. 4 for the South White Chapel Boulevard / Continental Boulevard Intersection Improvements project with Quality Excavation, Ltd. in the amount of $36,254.05