Item 4E Audio1
The construction of the roundabouts at the intersections of Dove at North Carroll
Avenue and Dove at North White Chapel Boulevard link to the city’s strategy
map relative to the focus areas of Mobility, Infrastructure, and Performance
Management and Service Delivery. The specific corporate objectives that are
met by this construction project include: Providing travel convenience within city
and region ; Providing high quality customer service; and Investing to provide
and maintain high quality public assets.
2
The Dove Road project is divided into two units. Unit 1 is comprised of the
roundabout at Dove Road and North Carroll Avenue and the storm drain and
waterline along Dove Road from Carroll Avenue to Lonesome Dove. Unit 2 is
the roundabout at Dove Road and North White Chapel Blvd.
4
Unit 1 of the Dove Road Intersection and Drainage Improvements project is
being closed out early to allow for a landscape contractor to install irrigation and
landscaping for the beautification of the roundabout at Dove Road and North
Carroll Avenue.
6
This slide shows the temporary roadway which will be constructed within the
northeast corner property belonging to the City. The original construction
phasing detoured traffic from North White Chapel thru the roundabout at Dove
and Carroll to SH114. The detour allowed for the intersection to remain closed
to traffic during construction. The revised phasing plan would allow North White
Chapel to remain open to traffic during construction.
The next 3 slides will show the revised construction phasing. The contractor is
currently installing and relocating utilities within the intersection. Phase 1 also
includes the construction of the temporary roadway within the nec property as
well as the west and east legs of the intersection. The section of Dove road,
between Kirkwood and White Chapel Blvd. will be closed to traffic during the first
phase due to cuts in the roadway of up to 7-8’ in depth. The closure will begin
on Tuesday, April 7 th. The remainder of the intersection will remain open to
traffic.
Phase 2 will be the construction of the north leg of the intersection. Commuters
from North White Chapel will be able to reach SH114 by way of 2 3-way stops
within the intersection.
Phase 3 will be the construction of the south leg of the intersection which will be
constructed under traffic.
During the final phase of construction, the intersection will operate as a
roundabout while the contractor installs curbs, brick pavers, stamped asphalt
crosswalks and the remaining layers of asphalt to complete the project.
12
13
14
15