West Parking Garage Lighting Background Information
Nov 3, 2009 – Council authorizes FSG contract
428 existing light fixtures
250 metal halide lamps
178 fluorescent lamps
Lighting Economic Analysis performed 2009
West Parking Garage LightingProposed Upgrades
Proposed lighting upgrades:
Upgrade to induction lighting;
Retrofit to GE Ultramax 28 Watt fluorescent lamps and ballasts.
LC-H511-80W Induction Light
Lighting Economic Analysis Background Information
Results estimate:
A savings in electricity of 249,810 KWH per year;
A savings of $25,638 for the first year.
Maintenance Cost Avoidance:
$10,718 each year for the first two years.
Estimated 5 year savings:
West Parking Garage LightingAdditional Benefits
Oncor Matching Grant
$50,000
Improved lighting/security
More efficient lighting = “Green” initiative
Project Costs
Lighting Improvements $107,178.85
Oncor Grant 50,000.00
Southlake Cost 57,178.85
Payback Period 1.6 Years
Oncor Check Presentation
Carlos De La Torre
Oncor Area Manager
Suzan Greene
Oncor Area Manager
Jeff Parrack
Southlake Facilities Manager
Crystal Seay
CleaResults – Grant Program Manager
Randy West
Facility Solutions Group
Questions