Item 4GITEM 4G
Award construction contract to JLB Contracting, in the amount of $897,191.66 for paving, drainage, and utility improvements to Shumaker Lane and Sunshine Lane and provide for construction
phase contingencies
Shumaker Lane/Sunshine LaneLocation Map
Shumaker/Sunshine Lane
Awarded to Jackson Construction
Requested to be released from contract
Contractor – JLB Contracting
Engineer Recommends New Low Bidder
Total Bid $897,191.66
Construction Phase Contingency - 129,808.34
Project Budget $1,027,000.00
Shumaker Lane
CIP amount budgeted - $490,578
Amount bid - $490,360
Sunshine Lane
CIP funds available - $ 1,133,564.00
Amount bid - $ 536,640.00