Item 4IItem 4IApprove the conceptual design for Lonesome Dove Park Improvements
Chris Tribble
LONESOME DOVE PARK IMPROVEMENTS
FY 2008 Park Dedication Fund Project
$175,000 Budget
Scope:
Replace existing playground (2-5 yrs & 5-12 yrs)
New park amenities (Shade, Benches, Drinking Ftn & Grill)
Landscape improvements
Goals:
Provide high quality public assets
Provide attractive and unique spaces for enjoyment of personal interests
Generate new community interest and use of the park
Improve ADA accessibility, function & safety of park
LONESOME DOVE PARK
EXISTING CONDITIONS
EXISTING CONDITIONS
CONCEPTUAL SITE PLAN
ARTIST RENDERING OF SITE
LANDSCAPE STRUCTURES EVOS PLAYSYSTEM
LANDSCAPE STRUCTURES EVOS PLAYSYSTEM
PLAY ELEMENT PHOTOS
Saddle Spinner
Single-post Swing Set
Seesaw
Sparger Park in Colleyville
Shade
PROJECT SCHEDULE
August 11, 2008: District 3 SPIN Meeting held to review preliminary concept plan – positive responses from neighborhood
October 31, 2008: Follow-up review of revised concept plan distributed via email to District 3 SPIN residents – positive response from SPIN Rep David Alexander rec’d 11/10/08
November 10, 2008: Parks Board recommended approval 7-0
November 18, 2008: City Council review concept design
December 19, 2008: Anticipate 100% construction documents
January 27, 2009: Open Construction Bids
February 9, 2009: Parks Board – recommendation to award contract
February 17, 2009: City Council - award of contract
June 26, 2009: Anticipated project completion
Questions?Chris Tribble(817) 748-8021