Item 3Recommended Sidewalk Plan Segments for FY09 Construction
ProjectLocationLengthWidth &Estimated cost Issues
#depth
38004 ‘ @ 4” $ 100,000
1Segment connecting from existing Trees,
retaining
sidewalks on East side of South Carroll at
walls,
Westmont Drive south to Bordeaux (safe
irrigation,
route for Old Union Elementary) *SP # 60
HOA, utility
box
2Segment connecting from west side of 10008’ @ 6” $ 120,000 Wall and rail,
decel lanes
North White Chapel along FM 1709 to
future sidewalk at decel lane in front of
Bicentennial Park *SP #47a & b
3Segment from east side of North Carroll at 14008 ‘ @ 4” $ 30,450 Trees, ROW,
round-about
Taylor Street south to Dove Road *SP #61
4Segment connecting from Mendez 6008’ @ 6” $ 40,620
Decel lanes
development to (decel) Foxborough Drive
*SP #126
5Segment from west side of Foxborough 4508’ @ 6” $ 30,465
Decel lanes
(decel) connecting to Diamond Circle
*SP #25
6Segment on south side of FM 1709 from 3008’ @ 6” $ 25,000
Decel lanes
existing sidewalk at Harris Methodist to
decel lane at Miron Drive *SP # 84
7Segment from west side of Player’s Circle 12008’ @ 6” $ 81,240
connecting to Davis Blvd. *SP #104
8Segment on east side of N Carroll from Bay 10008 ‘ @ 4” $ 150,000 Trees, ROW,
bridge
Meadows connecting to Whispering Dell
*SP #130
9Segment from west side of Diamond Circle 20008’ @ 6” $ 135,400
connecting to White Chapel *SP #129
10Segment/bridge connecting Gallant Ct. 1008’ @ 4” $ 10,000 Need co-op
from HOA
(Trailhead) to Johnson Place Estates *SP
#131
11Segment from existing sidewalk at 15258’ @ 6” $ 112,800 Grade
changes, wall
Chick-fil-A to existing sidewalk in front of
Georgetown and continue to connect east
to Nolen *SP #143, 143c, 143d
Neighborhood Sidewalk Program $ 50,000
Additional cost for decel lane sidewalk $ 130,000
segments – 16 x 3 feet
ROW acquisition consultant $ 50,000
FM 1709 Engineering $ 155,000
Total Estimate
$1,220,975
*SP = Sidewalk Plan