Item 4KITEM 4K
Approve Change Order No. 1 for the construction contract with JLB Contracting in the amount of $88,961.56 for paving, drainage, and utility improvements to Shumaker Lane and Sunshine
Lane
Shumaker Lane/Sunshine LaneLocation Map
Shumaker/Sunshine Lane
Contract Awarded to JLB Contracting October 7, 2008
Change Order Number 1 includes:
Increased Material Cost
Additional Drainage Flume
Additional Tree Bore
Shumaker/Sunshine Lane
Original Contract Award $897,191.66
Change Order No. 1 88,961.56
New Contract Total 986,153.22
Approved Project Budget $1,027,000.00