Approve Amendment No. 3 to the existing Professional Services Agreement for design services for the East Dove Road Drainage Improvements with Teague Nall and Perkins, Inc. in the amount
of $18,900.00
Amend PSA with Teague Nall and Perkins, Inc.
Background:
Teague Nall and Perkins, Inc. was hired in January, 2008
January 2009, Amendment No. 1
approved by the City Manager in the amount of $35,500.00
design of the pavement reconstruction of Dove Rd. between N. Carroll Ave. and Lonesome Dove Rd.
addition of water line improvements at the intersection of N. Carroll Ave. and E. Dove Rd.
June 2009, Amendment No. 2
approved by the City Manager
extension of a storm drain and the addition of a portion of 12” water line.
$0 change
Proposed amendment is for
design of an additional 2,800 LF of 12” water line and all related appurtenances along Dove Road between North Carroll Avenue and Lonesome Dove Road
Proposed amendment amount - $18,900.00.
Cumulative amendment
amount of $54,400.00 exceeds City Manager’s signature authority
Funds for the engineering design of the East Dove Road Drainage Improvements
included in the 2008 Capital Improvement Program.
Amend PSA with Teague Nall and Perkins, Inc.
PROJECT LOCATION MAP
Recommendation
Approve Amendment No. 3 to the existing Professional Services Agreement for design services for the East Dove Road Drainage Improvements with Teague Nall and Perkins, Inc. in the amount
of $18,900.00