Item 6B - Memo CITY OF Item 6B
SOUTHLAKE
MEMORANDUM
November 17, 2026
To: Alison Ortowski, City Manager
From: Daniel Cortez, Director of Economic Development & Tourism
Subject: Ordinance No. 1305, 2nd Reading Approval of Final Project and
Financing Plan for Tax Increment Reinvestment Zone Number
Two, City of Southlake, Texas
Action
Requested: Conduct a Public Hearing and consider 2nd Reading approval of
Ordinance No. 1305, approving the Final Project and Financing
Plan for Tax Increment Reinvestment Zone Number Two (TIRZ #2).
Background
Information: In June 2026, the City Council approved a Master Development
Agreement (MDA) with Trademark Retail Holdings, LLC for the
mixed-use development located at 1900 N. White Chapel
Boulevard, approved by the City Council on October 21 , 2025,
under Ordinance No. 480-837 (Planning Case ZA25-0045). The
MDA provided for City Council consideration of the future creation
of a Tax Increment Reinvestment Zone (TIRZ) on the commercial
portion of the property, to be established with a base year and a
term of up to twenty-one years, as one of the mechanisms
available to fund public improvements within the zone. The
agreement established a maximum amount of $18,850,000 that
applies to any payments reimbursed to the developer for these
public improvement expenditures, with the developer eligible for no
more than eighteen annual reimbursement payments subject to
that cap.
Purpose of the Zone. A tax increment reinvestment zone is a
financing tool, and Tax Increment Reinvestment Zone Number Two
(TIRZ #2) was created to fund public infrastructure and public
improvements within the zone's boundaries. Encompassing
approximately 27.3 acres across two parcels that are largely
undeveloped with a single homestead and designated as Mixed
Use on the City's Future Land Use Plan, the zone captures a
portion of the incremental property tax and sales tax revenue
generated by new development inside its boundaries, revenue that
does not exist today and would not be generated absent the
development, and dedicates it to public improvements that will be
Page 1 of 11
owned, accepted, and maintained by the City , and to Chapter 380
economic development grants authorized under the MDA
Chapter 380 Economic Development Grants. The MDA also
establishes an economic development program under Chapter 380
of the Texas Local Government Code. In exchange for the
developer's capital investment and performance obligations, the
City will provide limited-term grants funded from new General Fund
sales tax revenue generated by the development:
• Construction sales tax: 50% of the City's General Fund sales
tax revenue attributable to qualifying construction materials
sourced to the Property for two years after the first certificate of
occupancy is issued for the commercial portion.
• Operational retail sales tax: 95% of the City's General Fund
sales tax revenue generated by commercial retail sales once
tenants are open for business within the development and are
subject to the same term established for the TIRZ #2.
These grants will further supplement and be incorporated into the
TIRZ #2 and have been incorporated into the Final Project and
Financing Plan. Grants are paid only from sales tax revenue
collected by the City. They are performance-based incentives, and
every grant dollar counts against the $18,850,000 maximum
incentive amount.
Proposed Public Improvements: Total project costs are
estimated at $18,850,000 and fall into six general categories,
detailed in Exhibit C of the Final Project and Financing Plan:
• Public Utilities - water, sanitary sewer, and storm water facilities
and improvements ($3,526,807)
• Street and Intersection Improvements and Pedestrian
Enhancements ($4,344,867)
• Open Space, Park and Recreation Facilities and Improvements,
Public Facilities and Improvements ($1,576,162)
• Professional Services Costs ($2,348,920)
• Economic Development Grants — Chapter 380 which may
include grants, loans, and services for public and private
development ($6,864,744)
• Administrative Costs ($188,500)
Anticipated projects include a full four-lane divided Kirkwood
Boulevard, a new traffic signal at the intersection of White's Chapel
Boulevard and Kirkwood Boulevard, and water, sanitary sewer,
Page 2 of 11
and drainage improvements supporting development within the
zone. The specifics of these improvements can be found within the
Final Project and Financing Plan.
Any reimbursement from the tax increment fund is a
reimbursement of documented, TIRZ-eligible public improvement
costs advanced by a private party on the City's behalf, subject to
City review and acceptance of the completed improvements and
capped by the $18,850,000 maximum established in the Master
Development Agreement. Within the Final Project and Financing
Plan, the City is illustrated as participating at 95% of the real
property increment and 95% of General Fund sales tax revenue
generated within the zone. The approval of this ordinance would
not preclude any overlapping taxing jurisdictions, principally
Tarrant County, from participating in the Zone; should the County
elect to participate, the City's participation would be reduced
accordingly and an Amended Project and Financing Plan in
addition to an agreement with Tarrant County would be brought
forward for City Council consideration at a future date.
Performance Requirements: To qualify for and maintain eligibility
for incentives including the City creating and maintaining this Tax
Increment Reinvestment Zone, the developer must meet defined
construction and performance obligations as established within the
MDA, including:
• Achieving a minimum Capital Investment of $127,900,000 by
the time the full development reaches completion of
construction.
• The development must also generate and maintain a minimum
taxable value for the 2031 tax year and each year thereafter
during the term of the agreement and for at least twenty-one
years after completion of construction within the TIRZ
boundaries, with failure to maintain this threshold subjecting the
developer to default, potential recapture, and possible reduction
or suspension of TIRZ reimbursements.
• In addition, the developer is obligated to create a minimum
amount of full-time equivalent (FTE) jobs by June 30, 2028, and
to maintain that employment level through the term of the
agreement, with annual certification of FTE counts and related
documentation. If FTE requirements are not met in a given
year, the next payment or reimbursement due to the developer
is reduced by $1,000 per FTE shortfall, and material
misrepresentation of FTE data constitutes an event of default
Page 3 of 11
that may trigger termination and repayment of incentives.
• The MDA also established specific construction
commencement and completion deadlines, specifically
commencement of construction by January 1, 2027 and all
public improvements, private infrastructure and all infrastructure
for the commercial portion of the development must be
completed by December 31, 2028.
• The MDA also included annual reporting and certification
requirements, audit and verification rights for the City, and
remedies, such as the reduction, suspension, or termination of
incentives, and the recapture of previously paid Chapter 380
grants and tax increment reimbursements, if the developer fails
to meet its obligations.
The Final Project and Financing Plan is consistent with the Master
Development Agreement (MDA) approved by the City Council in
June 2026 with Trademark Retail Holdings, LLC for the mixed-use
development located at 1900 North White Chapel Boulevard. The
MDA contemplated the future consideration of a TIRZ for City
Council consideration on the commercial portion of the property,
established with a base year and a term of up to twenty-one years,
as one of the mechanisms available to fund public improvements
within the zone, and set the $18,850,000 maximum applicable to
any payments reimbursed to the developer for those expenditures,
payable over no more than eighteen annual reimbursements.
Approval on 2nd Reading for Ordinance No. 1305 is the final action
that accepts the Final Project and Financing Plan for Tax
Increment Reinvestment Zone Number Two. Each expenditure
remains subject to the terms of the MDA, this final plan, and the
availability of tax increment revenue actually collected.
Strategic Link: F1 — Safeguarding the public trust through a commitment to
thoughtful planning and responsible, conservative financial
management.
F2 — Investing to provide & maintain high-quality public assets
B2 — Collaborating with select partners to implement service
solutions
Financial
Considerations: The Policy Statement for Public Investment notes as a guiding
principle that it is the City's desire that public investment is
performance-based and considers a reasonable return on
investment via direct financial return and other indirect benefits.
Page 4 of 11
The total appraised value of the taxable real property in the zone,
using the 2026 base year values provided by the Tarrant Appraisal
District, is $803,531 . The taxable value of those same properties
is $16,575,400, after deducting a total of $15,771,869 for
agricultural deferrals and tax-exempt properties. This is the base
year value established for the zone.
The estimated 2026 taxable value of the private development
investment within the zone, the non-project costs not funded by
the TIRZ, is $68,307,050. Increment generated by that private
investment is projected to produce $18,850,800 in TIRZ revenue
over the life of the zone. Project costs will be funded solely from
tax increment received; it is not anticipated that the zone will incur
any bonded indebtedness, and expenses will be budgeted
annually in alignment with the identified expenditures in the project
and financing plan.
A taxable value analysis was prepared as part of the plan and is
included in its entirety as Exhibit B within the Final Project and
Financing Plan. Based on that analysis, the City is being asked to
consider if that plan is economically feasible through the
consideration of the ordinance adoption and that it will provide the
City and other taxing jurisdictions with economic benefits that
would not occur without its implementation.
Citizen Input/
Board Review: The Community Enhancement and Development Corporation
(CEDC) reviewed the request for public investment and provided
evaluation and feedback to the City Council per the provisions of
the Policy Statement for Public Investment.
TIRZ #2 Board
of Directors: On November 3, 2026, the TIRZ #2 Board of Directors
recommended approval (7-0) of the Final Project and Financing
Plan for Tax Increment Reinvestment Zone Number Two (TIRZ
#2).
City Council: On November 3, 2026, the City Council approved (7-0) the 1st
Reading of the Final Project and Financing Plan for Tax Increment
Reinvestment Zone Number Two (TIRZ #2) on consent.
Legal Review: The City Attorney's office prepared and reviewed the ordinance
and preliminary project and financing plan for City Council's
consideration.
Page 5 of 11
Alternatives: The City Council can consider the following alternatives for this
request:
• Approve the 2nd Reading for the Tax Increment Reinvestment
Zone Number Two Final Project and Financing Plan with
amendments
• Deny the 2nd Reading for the Tax Increment Reinvestment
Zone Number Two Final Project and Financing Plan
Supporting
Documents: Ordinance No. 1305
TIRZ #2 Preliminary Project and Financing Plan
Staff Contacts: Daniel Cortez (817) 748-8039
Page 6 of 11
ORDINANCE NO. 1305
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF SOUTHLAKE,
TEXAS, APPROVING A FINAL PROJECT AND FINANCING PLAN FOR TAX
INCREMENT REINVESTMENT ZONE NUMBER TWO, CITY OF SOUTHLAKE,
TEXAS; PROVIDING A SEVERABILITY CLAUSE; AND PROVIDING AN
EFFECTIVE DATE
WHEREAS, after second reading on October 6, 2026, the City of Southlake, Texas
(the "City") adopted Ordinance No. 1303 (the "Creation Ordinance"), pursuant to Chapter
311 of the Texas Tax Code, as amended (the "Act"), to designate a geographic area within
the City and create tax increment Reinvestment Zone Number Two, City of Southlake,
Texas (the "Zone"); and
WHEREAS, pursuant to and as required by the Act, the City Council adopted the
Reinvestment Zone Number Two, City of Southlake, Texas, Preliminary Project and
Financing Plan for the Zone; and
WHEREAS, the Zone Board of Directors (the "Board") convened in a public meeting
on November 3, 2026, and recommended approval of the Final Project and Financing Plan
for the Zone (the "Final Plan"), which is attached to this Ordinance as Exhibit A, and is
incorporated into this Ordinance as if fully set forth herein; and
WHEREAS, notice of the public hearing on the adoption of the Final Plan by the City
Council was published in a newspaper of general circulation in the City, such publication
date being not later than seven (7) days prior to the date of the public hearing; and
WHEREAS, this Ordinance is being considered by the City Council at First Reading
on November 3, 2026; and
WHEREAS, a public hearing will be held to consider this Ordinance at Second
Reading on November 17, 2026, and interested persons will be allowed to speak for or
against the adoption of the Final Plan and will be given a reasonable opportunity to protest
the Final Plan; and
WHEREAS, the Board and the City have taken all actions required by the Act, the
Texas Open Meetings Act, and all other laws applicable to the adoption of the Final Plan;
and
WHEREAS, pursuant to the Creation Ordinance, there shall be no funds utilized
from the Zone dedicated to funding the residential public improvements related to the
residential portion of the Shivers Farm development; and
WHEREAS, the City Council desires to approve the Final Plan in accordance with
Page 7 of 11
the Creation Ordinance and the Act.
NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF
SOUTH LAKE,TEXAS,THAT:
Section 1. FINDINGS.
(a) The recitals, findings, and determinations contained in the preamble
to this Ordinance and the Creation Ordinance, are incorporated into
the body of this Ordinance as if fully set forth in this Section and are
hereby found and declared to be true and correct legislative findings
and are adopted as part of this Ordinance for all purposes.
(b) The City Council finds that the Final Plan for the Zone conforms with
and satisfies all requirements set forth in Section 311.011 of the Act.
(c) The City Council finds that the Final Plan is economically feasible.
(d) The City Council finds that the Board of Directors for the Zone have
prepared, approved, and recommended this Final Plan, and have
submitted it to the City Council for final approval. The City Council
hereby approves the Final Plan, a copy of which is attached hereto as
Exhibit A and is incorporated herein for all purposes.
Section 2. ECONOMIC DEVELOPMENT IN THE ZONE.
Pursuant to Section 311.010(h) of the Act and Article III, Section 52-a of the
Texas Constitution, the Town Council hereby authorizes the Board, as
necessary or convenient to implement the Project and Financing Plan and
achieve its purposes, to establish and provide for the administration of one
or more programs for the public purposes of developing and diversifying the
economy of the Zone, eliminating unemployment and underemployment in
the Zone, and developing or expanding transportation, business, and
commercial activity in the Zone, including programs to make grants of land
and buildings and make grants from the TIRZ Fund for the Zone for activities
that benefit the Zone and stimulate business and commercial activity in the
Zone, subject to final City Council approval. In addition, the Town Council
hereby authorizes the Board to exercise all of the powers of the Town under
Chapter 380, Texas Local Government Code, as amended, subject to final
City Council approval.
Page 8 of 11
Section 3. TAX INCREMENT.
Pursuant to Section 311.013(l) of the Act, ninety five percent (95%) of the
Town's ad valorem real property taxes and ninety five percent (95%) of the
general fund sales tax revenue generated from the commercial development
within the Zone and collected and received by the Town on the Captured
Appraised Value in the Zone, shall be the portion of the Town Tax Increment
deposited into the TIRZ Fund for the Zone.
Section 4. SEVERABILITY.
If any provision, section, subsection, sentence, clause or phrase of this
Ordinance, or the application of same to any person or set of circumstances,
is for any reason held to be invalid, the validity of the remaining provisions of
this Ordinance or their application to other persons or sets of circumstances
shall not be affected thereby, it being the intent of the City Council in
adopting this Ordinance that no provision of this Ordinance shall become
inoperative because of the invalidity of another provision; and, therefore, all
provisions of this Ordinance are declared severable for that purpose.
Section 5. OPEN MEETINGS.
It is hereby found, determined, and declared that sufficient written notice of
the date, hour, place and subject of the meeting of the City Council at which
this Ordinance was adopted was posted at a place convenient and readily
accessible at all times to the general public at the City Hall of the City for the
time required by law preceding its meeting, as required by the Texas Open
Meetings Act, Chapter 551 of the Texas Government Code, as amended, and
that this meeting has been open to the public as required by law at all times
during which this Ordinance and the subject matter hereof has been
discussed, considered and formally acted upon. The City Council further
ratifies, approves and confirms such written notice and the contents and
posting thereof.
Section 6. This Ordinance shall be in full force and effect from and after its passage
and/or publication after second reading as required by law.
Page 9 of 11
PASSED AND APPROVED at Second Reading by the City Council of the City of Southlake,
Texas, this 17T" day of November, 2026.
City of Southlake, Texas
Shawn McCaskill, Mayor
Attest:
Amy Shelley, City Secretary
Approved as to legal form:
Cara L. White, City Attorney
Page 10 of 11
EXHIBIT A
FINAL PROJECT AND FINANCING PLAN
Page 11 of 11