Item 4D - Memo CITY OF Item 4D
SOUTH LAKE
MEMORANDUM
October 30, 2026
To: Alison Ortowski, City Manager
From: Pritam Deshmukh, Director of Public Works
Subject: Approve an Engineering Services Agreement with Bartlett &
West, Inc. to provide engineering design, inspection, and
construction phase services for the rehabilitation of the
Bicentennial Park Elevated Storage Tank in an amount not to
exceed $390,000.
Action
Requested: Approve an Engineering Services Agreement with Bartlett & West,
Inc. to provide engineering design, inspection, and construction
phase services for the rehabilitation of the Bicentennial Park
Elevated Storage Tank in an amount not to exceed $390,000.
Background
Information: The Bicentennial Park Elevated Storage Tank (EST) was originally
constructed in 1987 and is one of three ESTs providing water supply
and pressure to the City's low-pressure plane. This tank was last
rehabilitated and recoated in 2006-2007 and is nearing the end of
the typical service life of the existing coating system. The City
routinely inspects its water storage tanks to monitor the condition of
protective coatings and other tank components. Proactive
rehabilitation and replacement of protective coating systems
safeguards the existing structural steel from corrosion and
degradation and helps extend the usable service life of the tank.
Under this agreement, Bartlett & West, Inc. will provide engineering
design, inspection, bidding, and construction phase services for the
rehabilitation of the Bicentennial Park EST. The agreement includes
a pre-design condition assessment consisting of visual inspection of
the exterior and underwater Remotely Operated Vehicles (ROV)
inspection of the interior; preparation of plans and specifications for
interior and exterior recoating and other necessary tank repairs or
modifications; coordination with franchise utilities and City
departments to minimize impacts to service during construction;
resident construction inspection services to verify surface
preparation, coating application, welding, and other rehabilitation
work meet applicable industry standards; coordination with the
Federal Aviation Administration (FAA), including any required
permitting; and bidding and construction administration services.
Page 1 of 3
Item 4D
Coordination for the art elements is also included in the scope of
services. City Council previously provided direction for the graphics
to be incorporated into the project. Bartlett & West will incorporate
the approved graphics into the construction documents, including
preparation of scaled layout drawings showing artwork placement,
orientation, reference points, and coordination of colors and
materials.
The agreement for these services is not to exceed $390,000. This
project is aligned with Comprehensive Plan Objective 10.6.
The tank inspection is anticipated to be completed during winter
2026-2027, with design completed by summer 2027. Franchise
coordination is expected to begin in Spring 2027 and be completed
prior to bid opening in Fall 2027. Construction is anticipated to begin
during the lower water-demand season in late 2027/early 2028 to
minimize impacts to the water supply.
Financial
Considerations: This ESA is not to exceed $390,000. Funding for this agreement is
budgeted in the approved FY 2026 Utility Fund. This award is under
the approved project funding of $525,000 allocated for the
engineering design. These services include tank inspection and
cleaning, rehabilitation design, engineering services, construction
phase services, resident project inspection, and franchise utility
coordination.
Staff consider the proposed engineering fee of$390,000, reasonable
based on the scope of services and anticipated level of effort
required for the project. Approximately $198,000 is allocated for 14
weeks of full-time resident construction inspection, including
anticipated overtime for extended workdays and potential weekend
work. For comparison, the Florence EST Rehabilitation Project
included approximately $168,000 for 12 weeks of similar inspection
services under the same consultant. The remaining fee covers tank
condition assessment, rehabilitation design, franchise utility and FAA
coordination, bidding, construction administration, and other
associated engineering services.
Strategic Link: This item links to the City's Strategy Map strategic focus area of
Infrastructure and Development. It specifically relates to the City's
Objective, F2: Investing to Provide and maintain High-Quality Public
Assets.
Citizen Input/
Page 2 of 3
Item 4D
Board Review: No formal citizen input or board review has been completed for this
item. City Council previously provided direction regarding the
graphics for the Dove and Bicentennial Park Elevated Storage
Tanks. The approved graphic concepts will be incorporated into the
construction documents consistent with Council direction and the
City's established branding and standards.
Legal
Review: The proposed agreement is a standard agreement that the City
Attorney has reviewed and approved.
Alternatives: The City Council may approve or deny the agreement.
Staff
Recommendation: Approve an Engineering Services Agreement with Bartlett & West to
provide engineering design, inspection, and construction phase
services for Repainting of the Bicentennial Park Elevated Storage
Tank in an amount not to exceed $390,000.
Supporting
Documents: Attachment A: Engineering Services Agreement
Staff
Contact: Pritam Deshmukh, P.E., Director of Public Works
Jeff Ginn, P.E., City Engineer
Jimmy Sibert, P.E., Deputy City Engineer
Josue Hernandez, P.E., Civil Engineer
Page 3 of 3
Attachment A
AGREEMENT FOR ENGINEERING SERVICES
THIS Agreement for Engineering Services, hereinafter referred to as the "Agreement" is
made this day of , 2026 by and between the City of Southlake, Texas
(hereinafter referred to as "CITY"), and BARTLETT & WEST, INC. (hereinafter referred to as
"ENGINEER") referred herein individually as, the "Party," and collectively as, the "Parties.".
WHEREAS, CITY contemplates the need to inspect by drone the Bicentennial Elevated
Water Tank and issue plans and specifications for the rehabilitation/coating along with
construction observation/inspections., this project is to be known as Bicentennial Elevated Water
Tank and hereinafter referred to as the "Project".
WHEREAS, ENGINEER is qualified, able, and desirous of performing the necessary
engineering work upon which the Project is based and is willing and able to work with CITY
staff to organize and coordinate the engineering services necessary to complete the Project.
NOW, THEREFORE, CITY engages ENGINEER to perform, and ENGINEER agrees
to perform, the engineering work for the Project, as more fully described herein below, and
CITY agrees to pay as compensation, and ENGINEER agrees to accept as compensation, the
payments on the dates and in the amounts herein specified, all in accordance with the terms more
fully set out below and as provided in Attachment A, which are attached hereto and incorporated
by reference as if fully set forth herein.
I. ARTICLE
ENGINEERING SERVICES
A. Scope of Work
ENGINEER will provide the supervision, direction, personnel and equipment to perform
the engineering Services outlined in Attachment A in accordance with the terms set forth in this
Agreement and in Attachment A.
B. Personnel
ENGINEER hereby represents to CITY:
1. That it has all personnel required in performing the Services under this Agreement;
2. That all of the Services required hereunder will be performed by ENGINEER or under
ENGINEER's supervision; and
3. That all personnel engaged in the Services shall be qualified to perform such services in a
reasonably prudent manner and in accordance with Article VI—Standard of Care of this
Agreement.
C. Definitions
"Services" shall refer to the professional services performed by ENGINEER pursuant to
this Agreement.
D. Changes
The CITY may, without invalidating this Agreement, issue written orders to make
changes within the general scope of the work including additions, deletions, or modifications to
the work to be performed. If any change results in an increase or decrease in the ENGINEER's
cost, or the time required to perform any portion of the Services under this Agreement, the
Parties shall, by written mutual agreement, make an equitable adjustment, and this Agreement
shall be amended in writing accordingly.
E. Coordination with Owner
Upon receiving a written request by ENGINEER, the CITY shall make available to
ENGINEER for use in performing Services herein all existing plans, maps, field notes, statistics
computations and other data in the CITY's possession relative to existing facilities and to the
Project.
F. Site and Local Conditions
1. ENGINEER has the right to examine the site in order to become acquainted with local
conditions and accepts conditions at the site, "as-is", unless otherwise prevented by a
force majeure event and is noted in writing to the CITY.
2. Any coordination or scheduling of work by CITY shall not relieve ENGINEER from its
responsibilities specified herein.
G. Assignment and Subcontractors/Third Party Rights
1. The interests, rights, and obligations covered herein are personal to each Party hereto and
not to any third party and for this reason neither this Agreement nor any contract
hereunder shall be assigned, conveyed, or transferred by either Party in whole or in part;
nor shall ENGINEER subcontract any of its obligations under this Agreement without the
prior written consent of CITY, which may be withheld at the CITY's sole discretion.
2. Any attempted assignment, conveyance, transfer, or delegation in violation of this
provision shall be null and void and shall constitute a material breach of this Agreement.
In the event of an assignment by ENGINEER to which the CITY has consented, the
assignee or the assignee's legal representative shall agree in writing with the CITY to
personally assume, perform, and be bound by all the covenants, terms, obligations, and
agreements contained in this Agreement.
H. Independent Contractor
1. ENGINEER covenants and agrees that it will perform the work hereunder as an
independent contractor, and not as an officer, agent, servant, employee, or otherwise
under the control of CITY.
2. ENGINEER shall have exclusive control of and exclusive right to control the details and
manner of the Services performed herein, and all persons performing same.
3. ENGINEER shall be solely responsible for the acts and omissions of its officers, agents,
employees, contractors, subcontractors, sub-subcontractors, and consultants; the doctrine
of respondent superior shall not apply as between CITY and ENGINEER, its officers,
agents, employees, contractors, subcontractors, sub-subcontractors, and consultants, and
nothing herein shall be construed as creating a partnership or joint enterprise between
CITY and ENGINEER.
I. Disclosure
1. ENGINEER warrants to CITY that it has made full disclosure in writing of any existing
conflicts of interest or potential conflicts of interest, including personal financial
interests, direct or indirect, in property abutting the proposed Project and business
relations with abutting property owners.
2. ENGINEER warrants that it shall make full disclosure in writing of any conflicts of
interest that arises after execution of this Agreement and before final payment under the
contract is made. Such disclosure shall be provided to CITY within seven (7) days of
ENGINEER's discovery of the conflict. Finally, Engineer warrants that it has submitted
to the City a completed Conflicts of Interest Questionnaire as required by Chapter 176 of
the Texas Local Government Code.
J. Approval by CITY
1. Approval by CITY of this Agreement shall not constitute or be deemed to be a release of
the responsibility and liability of ENGINEER, its officers, agents, employees,
subcontractors, sub-subcontractors for the accuracy and competency of the Services
performed under this Agreement, including but not limited to surveys, designs, working
drawings and specifications and other engineering documents.
2. Such approval shall not be deemed to be a waiver or an assumption of such responsibility
and liability by CITY for any negligent act, error, or omission in the performance of
ENGINEER's engineering services or in the conduct or preparation of the subsurface
investigations, surveys, designs, working drawings and specifications or other
engineering documents by ENGINEER, its officers, agents, employees, subcontractors,
and sub-contractors.
K. Indemnification
IN ACCORDANCE WITH TEXAS LOCAL GOVERNMENT CODE
SECTION 271.904, THE ENGINEER SHALL HOLD HARMLESS AND
INDEMNIFY THE CITY FROM ALL CLAIMS AND LIABILITY FOR
DAMAGES ARISING OUT OF OR IN CONNECTION WITH THIS
AGREEMENT TO THE EXTENT THAT THE DAMAGE IS CAUSED BY OR
RESULTS FROM AN ERROR, OMISSION, ACT OF NEGLIGENCE,
INTENTIONAL TORT, INTELLECTUAL PROPERTY INFRINGEMENT, OR
FAILURE TO PAY A SUBCONTRACTOR OR SUPPLIER COMMITTED BY
ENGINEER OR THE ENGINEER'S AGENT, CONSULTANT UNDER
CONTRACT, OR ANOTHER ENTITY OVER WHICH THE ENGINEER
EXERCISES CONTROL. FOR CLAIMS OR LIABILITIES COVERD BY
ENGINEER'S PROFESSIONAL LIABILITY POLICY, THE ENGINEER SHALL
REIMBURSE (RATHER THAN DEFEND) THE CITY FOR ANY AND ALL
LEGAL COSTS AND EXPENSES, INCLUDING REASONABLE ATTORNEYS'
FEES WHICH ARE INCURRED BY THE CITY IN LITIGATION OR
OTHERWISE RESISTING SAID CLAIM OR LIABILITIES, WHICH ARE
INCURRED BY, CHARGED AGAINST, OR IMPOSED ON THE CITY AS THE
RESULT OF SUCH NEGLIGENT, INTENTIONAL TORT ACTS OR
OMISSIONS BY THE ENGIENEER IN PROPORTION TO THE ENGINEER'S
LIABILITY. NEITHER CITY NOR ENGINEER WAIVE ANY LEGAL
CONTENTIONS, DEFENSES, OR IMMUNITIES, INCLUDING, BUT NOT
LIMITED TO GOVERNMENTAL (I.E., SOVEREIGN) IMMUNITY. THIS
PROVISION SHALL SURVIVE THE EXPIRATION OR TERMINATION OF
THIS AGREEMENT.
L. No Third-Party Beneficiary
For purposes of this Agreement, including its intended operation and effect, the Parties
expressly agree and contract that:
i. This Agreement governs only the rights, obligations, and disputes between the
CITY and ENGINEER and is in no way intended to confer any rights, benefits, benefit or
remedies upon any third party or entity, except as expressly provided for indemnitees
identified in Article I, Section K., above,
ii. Nothing in this Agreement shall be construed to release, waive, or diminish any
obligation or liabilities that any third party or entity may owe to the CITY or ENGINEER
under contract, statute, or common law. The Parties expressly disclaim any intent to
create third-party beneficiary rights under this Agreement.
M. Successors and Assigns
CITY and ENGINEER each bind themselves and their successors, executors,
administrators, and assigns to the other Party to this Agreement and to the successors,
executors, administrators and assigns of such other Party with respect to all rights,
covenants, duties, and obligations of this Agreement.
II. ARTICLE
CITY'S RESPONSIBILITIES
CITY shall undertake and perform the following obligations in accordance with this
Agreement set forth herein:
1. The CITY shall provide ENGINEER with complete and accurate information regarding
the CITY's Requirements for the Project as reasonably necessary for the ENGINEER to
perform its Services under this Agreement. For purposes of this Agreement,
"Requirements" shall mean all written specifications, standards, criteria, objectives,
constraints, and other directives necessary to define the scope, design, and performance
expectations of the Project. All such requirements shall be provided in writing;
2. The CITY shall assist the Engineer by making available all information within the
CITY's possession or control that is relevant to the Project. Such information shall
include, without limitation, executed right-of-way easements and final field survey data;
3. The CITY shall review all work submitted by ENGINEER and shall provide a written
response to such submission within reasonable time of receipt;
4. The CITY shall bear and pay all costs associated with advertising for the solicitation of
bids or proposals from Contractors;
5. The CITY shall provide prompt written notice to ENGINEER upon observing, or
otherwise becoming aware of, any defect in ENGINEER's work or in Contractor's work;
6. The CITY shall designate, in writing, an individual to serve as its authorized
representative under this Agreement. Such representative shall have full authority to
transmit instructions, receive information, and make or interpret decisions on behalf of
the CITY;
7. Provide all information and criteria as to the CITY's requirements, objectives, and
expectations for the Project including all numerical criteria that are to be met and all
standards of development, design, or construction.
8. The CITY shall provide to the ENGINEER all existing studies, plans, and other
documents related to the Project, as well as new data reasonably deemed by the
ENGINEER, including but not limited to site survey, engineering data, environmental
impact assessments or statements, and applicable zoning or land use regulations. The
ENGINEER shall be entitled to rely upon the information provided by the CITY;
however, the CITY makes no representation or warranty as to the accuracy or
completeness of such information and shall not be liable for any errors, omissions, or
inaccuracies contained therein. The ENGINEER shall exercise reasonable diligence to
independently verify the accuracy and applicability of all information provided by the
CITY prior to its use in performing Services under this Agreement;
9. The CITY shall arrange and secure access to the Project site and any other private or
public property as reasonably necessary for the ENGINEER to perform its Services under
this Agreement.
10. The CITY shall provide any additional information or assistance as may be specified in
the Attachments to this Agreement, if and to the extent applicable. All Attachments
referenced herein are hereby incorporated by reference and made a part of this
Agreement as if fully set forth herein. In the event of any conflict or inconsistency
between the terms of this Agreement and the terms of any Attachment, the terms of this
Agreement shall control and govern.
III.ARTICLE
COMPENSATION FOR ENGINEERING SERVICES
The CITY shall compensate ENGINEER for services performed under this Agreement, in
accordance with the following:
For the completion of the work described in Article I, the ENGINEER shall be paid on a
lump sum basis in the amount of$390,000 for services outlined in Attachment A and
satisfactorily performed.. Payment shall be contingent upon the CITY's satisfactory completion
of all services described in Article I and AttachmentA attached hereto, and submission of
proper invoices to the CITY.
This Agreement is also contingent upon the appropriation of funds by the City of
Southlake, Texas. All payments by the CITY under this Agreement, including any provision in
the Agreement relating to penalties, overages, interest, collections, or any other additional costs,
shall be subject to and conditional upon the annual appropriation of public funds budgeted for
the specific purposes of the Agreement in accordance with the City Charter and Texas law. The
CITY shall make a good faith effort to appropriate funds in accordance with Texas law. If funds
are not appropriated for any fiscal year during the term of this Agreement, the CITY may
terminate this Agreement without penalty or further obligation.
IV. ARTICLE
TIMES OF BILLING AND PAYMENT
The ENGINEER shall submit invoices to the CITY on a monthly basis for any services
and reimbursable expenses incurred in accordance with the work performed, subject to the limits
set forth in Article III. Each invoice shall be properly prepared, accurate, and accompanied by
such supporting documentation, records, or other written proof as CITY may reasonably require
to verify the amounts billed. The CITY shall have no obligation to pay any invoice that is
incorrect, incomplete, or unsupported by adequate documentation. Failure by the ENGINEER to
provide the required documentation with an invoice shall constitute a waiver of the
ENGINEER's right to payment for the amounts billed in that invoice. Payment of approved
invoices shall be made within thirty (30) days after the CITY's receipt and acceptance of a
correct and properly documented invoice. All invoices shall be delivered to the CITY's Finance
Department at 1400 Main Street, Suite 420, Southlake, Texas 76092. The CITY reserves the
right to withhold payment for any disputed charges until such dispute is resolved to the CITY's
satisfaction. Any invoice submitted more than ninety (90) days after the date the Services were
performed shall be deemed invalid, and the ENGINEER shall waive any right to payment for
such Services.
If CITY fails to make any payment due to ENGINEER within thirty (30) days of the day
after such payment becomes due under this Agreement, the ENGINEER shall provide written
notice to the CITY of the delinquent amount. Interest shall begin to accrue on the unpaid balance
only if the CITY fails to remit payment within ten (10) days after receipt of such payment.
ENGINEER shall be entitled to interest on unpaid amount at the rate specified in Chapter 2251
of the Texas Government Code, as amended.
V.ARTICLE
ADDITIONAL ENGINEERING SERVICES
In addition to performing the engineering services described in Article I of this
Agreement, ENGINEER shall perform such additional services as the CITY may request from
time to time, provided that no additional services shall be undertaken without the CITY's prior
written authorization. The CITY shall compensate ENGINEER for such authorized services at
rates and terms mutually agreed upon in writing by the Parties, based on actual time expanded
and actual out-of-pocket expenses incurred. Any additional services performed without the
CITY's prior written authorization shall be deemed unauthorized and shall not be subject to
compensation. Such additional services may include, but are not limited to the following:
1. Make or prepare detailed description of sites, maps, or drawings related thereto and
outside the scope of the Project;
2. Appearances before courts or boards on matters of litigation or hearings related to the
Project;
3. Preparation of environmental impact assessments or statements for any governmental
entity or agency;
4. Miscellaneous engineering work for CITY not related to the Project;
5. To provide resident project construction inspection, unless such inspection is not
required, in writing, by the CITY; and
6. Other services agreed to by the parties in writing and incorporated herein.
VI. ARTICLE
STANDARD OF CARE
Pursuant to Texas Local Government Code §271.904(d), the ENGINEER will perform its
engineering services with the professional skill and care ordinarily provided by competent
engineers, practicing under the same or similar circumstances and professional license, and will
perform engineering services as expeditiously as is prudent considering the ordinary professional
skill and care of a competent engineer and in accordance with any other applicable governmental
laws, regulations, and ordinances.
VIL ARTICLE
PERIOD OF SERVICE
This Agreement shall be effective upon execution by CITY and ENGINEER, and shall
remain in force until work is completed on the Project or until terminated under the provisions
hereinafter provided in Article VIII.
VIII.ARTICLE
TERMINATION & CLAIMS
A. The CITY may terminate this Agreement at any time for convenience, with or without
cause by giving written notice to the ENGINEER. Such termination may be made
effective on such future date as agreed by the parties, but absent such agreement shall be
immediate. Upon receipt of such notice, the ENGINEER shall immediately cease all
services and work under this Agreement, including the placement of any orders or the
execution of contracts for supplies, assistance, facilities, or materials related to its
performance. The ENGINEER shall promptly take all necessary steps to cancel any
existing contracts to the extent they are attributable to this Agreement.
B. The ENGINEER, upon termination, shall be paid for all services rendered through the
date of termination together with any additional reimbursable expense then due in
accordance with Article IV.
C. Any claim, dispute, or other matter in question arising out of or related to this Agreement
shall be subject to mediation by mutual written agreement of the Parties but shall not be a
condition precedent to litigation in a court of competent jurisdiction. The Parties shall
share the mediator's fee and filing fees equally. The mediation shall be held in the place
where the Project is located, unless another location is mutually agreed upon.
D. The CITY and ENGINEER shall commence all claims and causes of action against the
other and arising out of or related to this Agreement, whether in contract, tort, or
otherwise, in accordance with applicable law.
E. The Parties hereby acknowledge and agree that the CITY is entering into this Agreement
pursuant to its governmental functions and that nothing contained in the Agreement shall
be construed as constituting a waiver of the CITY's governmental immunity from suit or
liability, which is expressly reserved to the extent allowed by law. Notwithstanding
anything to the contrary herein, the Parties hereby acknowledge and agree that to the
extent this Agreement is subject to the provisions of Subchapter I of Chapter 271, Texas
Local Government Code, as amended, the CITY's immunity from suit is waived only as
set forth in Subchapter I of Chapter 271 Texas Local Government Code. Further, the
Parties agree that this Agreement is made subject to all applicable provisions of the Texas
Civil Practice and Remedies Code ("CPRC"), including but not limited to all defenses,
limitations, and exceptions to the limited waiver of immunity from liability provided in
CPRC Chapter 101 and Chapter 75.
F. The CITY expressly reserves its legislative and municipal police power in accordance
with the laws of the State of Texas. Any provision, term, or condition in the Contract
requiring CITY to waive its rights under Texas or Federal Constitution, or under any
foreign law(s), or limiting the claims or remedies available to CITY, or requiring
settlement of claims through binding mediation or arbitration are void and shall be given
no effect.
IX. ARTICLE
OWNERSHIP OF DOCUMENTS
A. All reports, whether completed or partially completed, prepared under this Agreement
including the original drawings, designs, specifications, and related documents in both
paper and electronic formats—shall become the property of CITY upon termination of
this Agreement and upon payment of undisputed amounts in accordance with this
Agreement. Upon full performance and payment under this Agreement, all final design,
drawings, specifications and related documents, in both paper and electronic formats,
shall be the sole and exclusive property of CITY.
B. Any reuse, modification, or alteration of such documents by CITY, or by any party acting
on behalf of CITY, without the prior written consent of ENGINEER, shall be undertaken
at CITY's sole risk and responsibility. ENGINEER shall have no liability arising from
such unauthorized reuse, modification, or alteration.
C. Any reuse by ENGINEER will be at ENGINEER's sole risk and without liability or legal
exposure to CITY, and ENGINEER shall indemnify and hold harmless CITY from all
claims, damages, losses, and expenses including reasonable attorneys' fees arising out of
or resulting therefrom.
D. Upon payment of undisputed amounts in accordance with this Agreement, the
ENGINEER hereby assigns to CITY all rights, title, and interest in and to any intellectual
property created, developed, or produced in connection with the performance of this
Agreement, including but not limited to copyrights, design rights, and any other
proprietary rights in the deliverables. The ENGINEER shall execute any documents and
take any actions reasonably necessary to perfect such assignment.
E. The ENGINEER retains no rights to use, reproduce, or distribute any deliverables or
intellectual property created under this Agreement, except with the prior written consent
of CITY. Any pre-existing intellectual property of the ENGINEER incorporated into the
deliverables shall remain the property of the ENGINEER; however, upon payment of all
undisputed amounts in accordance with this Agreement, the ENGINEER grants CITY a
perpetual, irrevocable, royalty-free license to use, reproduce, modify, and distribute such
pre-existing materials solely for purposes related to the deliverables.
X.ARTICLE
INSURANCE
A. ENGINEER shall carry and maintain at all times relevant hereto, at ENGINEER's
expense, insurance of the type and of minimum coverage limits as follows:
1. Workers Compensation - Statutory Employer's Liability - Limits as required by the State
of Texas.
2. Comprehensive General Liability, Bodily Injury and Property Damage including
contractual liability in a combined single limit- $500,000 per occurrence.
3. Comprehensive Automotive Liability, Bodily Injury and Property Damage in a combined
single limit- $1,000,000 per accident.
a. ENGINEER shall provide Certificates of Insurance for the above coverage in a
form acceptable to CITY, evidencing the coverage required above, shall be
provided to CITY within ten (10) business days after execution of this Agreement
and prior to issuing Notice to Proceed. Such certificates shall provide that the
insurer will give CITY not less than ten (10) days notice of any material changes
in or cancellation of coverage. In the event any subcontractor of ENGINEER,
with CITY's consent, provides or renders services under this Agreement,
ENGINEER shall ensure that the subcontractor's services are covered by the
same insurance limits as set forth above.
b. ENGINEER shall not commence work under this Agreement until it has obtained
Professional Liability (Errors and Omissions) Insurance as required herein and
such insurance coverage has been approved by CITY. Such insurance shall be in
the minimum amount of $1,000,000 per claim and in the aggregate. The
insurance coverage described herein shall be maintained until two (2) years after
CITY's acceptance of the Project and shall not be canceled without prior written
notice to CITY. Upon execution and return of this Agreement by ENGINEER,
ENGINEER shall furnish CITY with a Certificate of Insurance evidencing that
the insurance coverage required under this Agreement has been obtained. The
Certificate shall state that such insurance shall not be cancelled, non-renewed, or
incur a reduction of coverage without providing CITY thirty (30) days prior
written notice. ENGINEER shall notify CITY within ten (10) days of any
reduction of coverage as required by this agreement in such Professional Liability
(Errors and Omissions) Insurance.
B. ENGINEER further agrees to name CITY as an additional insured under ENGINEER's
general liability insurance policy and provide any defense provided by the policy to
CITY as permitted by Texas Local Government Code §271.904(c).
XI. ARTICLE
AUTHORIZATION, PROGRESS AND COMPLETION
CITY and ENGINEER agree that the Project is planned to be completed as expeditiously
as is prudent considering the ordinary professional skill and care of a competent engineer.
ENGINEER shall employ manpower and other reasonably necessary resources, and use
professional skill and diligence to meet the schedule; however, ENGINEER shall not be
responsible for schedule delays resulting from a force majeure event. The Project schedule may
be modified during the course of the Project by written mutual agreement between CITY and
ENGINEER. If any such modification impacts ENGINEER's compensation, the compensation
shall be adjusted accordingly, subject to CITY's prior written approval. However, no adjustment
to compensation shall be made for modifications or changes resulting from a force majeure
event.
A. It is understood that this Agreement contemplates services for this Project as described in
this Agreement, including any and all Services necessary to complete the work. Any
authorization by CITY for additional Engineering Services, shall be in writing and shall
specify:
i. The scope and definition of the services to be performed;
ii. The schedule for commencing and completing such services; and
iii. The agreed-upon basis for compensation between CITY and ENGINEER.
XII. ARTICLE
NOTICE
Any notice required under this Agreement will be in writing and given either personally,
by certified mail, return receipt requested, or by a nationally recognized overnight courier
service, addressed to the parties as follows:
If to CITY: Alison Ortowski
City Manager
City of Southlake
1400 Main Street, Suite 460
Southlake, Texas 76092
Phone: 817-748-8400
Fax: 817-748-8010
If to ENGINEER: Lee Halencak
Senior Project Manager/Practice Builder
Bartlett &West, Inc.
4500 Mercantile Plaza, Suite 230
Fort Worth, TX 76137
817-840-1563
lee.halencak@bartwest.com
All notice shall be effective upon the date of receipt.
XIII.ARTICLE
SEVERABILITY
In case any one or more of the provisions contained in this Agreement shall for any
reason be held by a tribunal with jurisdiction over this Agreement to be invalid, illegal, or
unenforceable in any respect, such invalidity, illegality, or unenforceability shall not affect any
other provisions thereof and this Agreement shall be construed as if such invalid, illegal, or
unenforceable provision had never been contained herein.
XIV. ARTICLE
VENUE & GOVERNING LAW
The obligations of the Parties to this Agreement shall be performable in Tarrant County,
Texas and if legal action is necessary in connection with or to enforce rights under the
Agreement, exclusive venue of any suit or cause of action under this Agreement shall in Tarrant
County, Texas. This Agreement shall be governed by and construed in accordance with the laws
and court decisions of the State of Texas, without regard to conflict of law or choice of law
principles of Texas, or any other state or country.
XV.ARTICLE
FORCE MAJEURE
Neither CITY or ENGINEER shall be liable for failure to perform their obligations under
this Agreement if the performance is delayed or prevented by reason of war; civil commotion;
Acts of God; inclement weather; epidemics; pandemics; governmental restrictions, regulations,
or interferences; strikes; lockouts; national disasters; riots; material or labor restrictions;
transportations problems; or any other circumstances which are reasonably beyond the control of
the Party. Such Party's performance shall be excused for the length of time the force majeure
event(s) last, provided that Party makes a reasonable attempt to resume performance upon
conclusion of the force majeure event, unless such performance has become legally impossible,
in which case that Party may terminate this Agreement.
XVL ARTICLE
TEXAS PUBLIC INFORMATION ACT NOTICE
All information, documents, and communications relating to this Agreement shall be
subject to the Texas Public Information Act ("Act") and any opinion of the Texas Attorney
General or a court of competent jurisdiction relating to the Act. The requirements of
Subchapter J, Chapter 552, Texas Government Code, may apply to this Agreement and
ENGINEER agrees that the Agreement may be terminated if the ENGINEER knowingly or
intentionally fails to comply with a requirement of that subchapter. In accordance with the
Act, the Consultant agrees to:
1. Preserve all contracting information related to the Agreement as provided by the records
retention requirements applicable to the CITY for the duration of this Agreement;
2. Promptly provide to the CITY any contracting information related to this Agreement that
is in the custody, possession, or control of the ENGINEER on request of the CITY; and
3. On the completion of this Agreement, either:
a. Provide at no cost to the CITY, all contracting information related to this
Agreement that is in the custody, possession, or control of the ENGINEER; or
b. Preserve the contracting information related to this Agreement as provided by
the records retention requirements applicable to the city.
IN WITNESS WHEREOF the parties have caused this Agreement to be executed in two
equal originals on the date and year first above mentioned.
CITY OF SOUTHLAKE, TEXAS:
By:
Shawn McCaskill, Mayor
ATTEST:
By:
City Secretary
ENGINEER: BARTLETT & WEST, INC
By:
Lee M. Halencak, P.E.
Sr. Project Manager
THE STATE OF TEXAS §
COUNTY OF TARRANT §
Before me on this day personally appeared known to me [or proved to
me on the oath of or through (description of identity
card or other document)] to be the person whose name is subscribed to the foregoing instrument
and that he/she is the duly authorized of
, and acknowledged to me that he/she executed the same for
the purposes and consideration therein expressed.
Given under my hand and seal of office this day of , A.D.
(SEAL) Notary Public, State of Texas
Notary's Name Printed
BARTLETT & WEST,INC.
SCOPE OF WORK- CITY OF SOUTHLAKE BICENTENNIAL PARK ELEVATED TANK
ASSESSMENT/DESIGN REHABILITATION AND CONSTRUCTION OBSERVATION
The Consultant shall perform services for the purpose of Assessing the City's 1.5-million-gallon
Bicentennial Park Elevated water storage tank by use of underwater ROV. Upon completion of
condition assessment, plans and specifications will be developed based on ROV findings for
rehabilitation. The scope of work associated with the Project includes: interior inspection of
Bicentennial Park EST utilizing a remotely operated vehicle (ROV) and visual methods, exterior
inspection utilizing visual methods, compiling and submitting to the Client a detailed inspection,
development of a project manual, construction plans, graphics design and details (as necessary),
and specifications for tank rehabilitation,bidding phase services,construction phase services,and
construction observation:
1. Project Administration
i. Perform routine project management and administration of the inspection and
design contract including project initiation, invoices, team meetings, project
tracking, monthly status reports, etc.
ii. Coordination with Client staff and other stakeholders concerning scope, design
objectives, and design review. Designate point of contracts between B&W and
city departments.
iii. Prepare for and attend up to three (3) City Council and/or Stakeholder Meetings to
discuss the project as identified below:
1. Project Scope and Professional Services Agreement
2. Bid Results and Notice of Award
3. Public Meetings
2. Tank Assessment
i. Conduct initial tank assessments with City staff to identify preliminary
rehabilitation recommendations. Assessment will consist of visual evaluation of
the exterior of tank, and visual and ROV evaluation on the interior of the tank.
Evaluation with the ROV will allow the tank to remain in service during the
inspection period. ROV is unable to inspect the riser.
ii. During assessment,city has staff on site to assist in exercising valves and allowing
access to process piping for visual evaluation.
iii. Process ROV footage and provide a condition assessment and report of findings
and recommendations to the City.
3. Bicentennial Park EST Rehabilitation Design
i. Review condition assessment report for the Bicentennial Park elevated storage
tank (EST) and create list of rehabilitation items to be included in the Project
Manual/contract documents. Visit the Bicentennial Park EST site to determine if
any additional rehabilitation items require inclusion into the Project
Manual/contract documents.
ii. Create project plan sheets (8.5"xl l" or 11"xl7") as needed for inclusion into the
Project Manual. Plan sheets may consist of one or more of the following sheets as
necessitated by project scope.
1. Location Map
2. Site Plan with Site Modifications
3. Original Construction Submittal Drawings for Bidder's Reference
4. Design Details
5. Photographs
iii. Graphic Consultation will include guidance on do's/don'ts for graphic
design/color/bleed/material and size. Graphic Layout Plan Sheets- to include
artwork layout and placement on the tank (scaling, orientation, reference points)
and incorporation of the selected artwork into the final contract documents.
Coordination with City selected artist/vendor for final alignment and material
compatibility.
iv. Coordinate with city staff and vendor on mixing system to determine the size and
the proper equipment to be included in the bidding documents.
v. Develop Technical Specifications for recoating and rehabilitating the water
storage tanks. Project technical specifications will be developed based on the
following assumed rehabilitation work scope items:
1. Recoat or Overcoat the tank exteriors, including coating with HydroFlon.
2. Recoat the tank interiors,including blasting and coating with a zinc,epoxy,
epoxy coating system.
3. Other minor tank repairs and modifications.
vi. Develop Contract Documents for use in bidding and contracting the proposed
recoating and rehabilitation.
vii. Perform quality assurance/quality control reviews of the work as it progresses and
make any necessary revisions. Review the project deliverables with City and other
stakeholders and make any necessary revisions.
viii. Coordinate with the Federal Aviation Administration(FAA)as required and obtain
any necessary permits from the FAA for the rehabilitation work to be completed.
ix. Coordinate with franchise utilities as needed, including the coordination of
temporary facilities at the tank site in order for the franchise utilities to continue
providing service to customers. The location of any temporary facilities shall also
be coordinated with the Contractor in order to minimize any impacts to their
operations.
x. Coordinate with City departments as needed,for relocation of city radio equipment
to a temporary site.
xi. Submit review copies of project plan sheets, technical specifications, and the
Project Manual to City staff for review and comment on the following design
milestones:
1. 30% design completed
2. 60% design completed
3. 90% design completed
4. 100% design completed
xii. Make final revisions to the Project Manual. Following final approval, one (1)
electronic copy (PDF format) of the Project Bid Manual shall be provided to the
City.
4. Engineering Administration Services during Bidding Phase
i. Administer the process of advertising the project, including electronically
advertising the project on the City's procurement platform and on a third-party
platform such as Civcast.
ii. Conduct a Pre-Bid Meeting at City's office with prospective bidders, and answer
any questions asked during this conference.
iii. Continue to answer questions from prospective bidders until the deadline noted in
the Project Manual and issue any addenda necessary in order to clarify or correct
any items in the Project Manual.
iv. Attend Bid Opening at City's office.
v. Tabulate and evaluate bids received based on best value and prepare a
Recommendation of Award Letter. Send copies of the bid tabulations and
Recommendation of Award Letter to City staff.
5. Engineering Administration Services during Construction Phase
i. Administer the process of preparing the construction contract for execution.
ii. Conduct a Pre-Construction Conference at City's office with representatives of the
City and the Contractor present.
iii. Review shop drawings/submittals from Contractor for compliance with
specifications.
iv. Review Contractor's monthly partial payment requests.
v. Prepare and administer project change orders, as needed.
vi. Interpret Contract Documents when requested by the City or the Contractor.
vii. Revise contract drawings, based upon information provided by the contractor, to
show the work that was constructed. Furnish a set of these revised drawings to the
City and other agencies,as required.Documents furnished to the City will typically
include PDFs, CAD files, and hard copies (if requested). These are not certified as
as-built plans but will be record drawings as signed by the contractor.
viii. Assist the City in obtaining final acceptance of the project by TCEQ, if required.
ix. Perform and administer contract closeout upon completion of construction.
6. Construction Observation
i. Make up to three (3) visits to the site to observe the progress of construction and
to determine, in general, if the work is proceeding in accordance with the contract
documents. This observation should not be in lieu of work performed by the City's
inspectors or Resident Project Representatives (RPRs)but will be more general in
nature.
ii. Document observations and construction progress from each site visit in an
observation report and furnish to the City if requested.
iii. Accompany City staff on their final inspection of the project for compliance with
the contract documents.
iv. Accompany City staff on the twenty-three (23) month warranty inspection of the
project and document any warranty issues that shall be corrected by the Contractor
per the contract documents.
7. Resident Project Representation
i. Provide a full-time Resident Project Representative (RPR) to perform inspection
services on the Contractor's work.
ii. Estimated duration that RPR services will be required is approximately 14 weeks.
15 hours of overtime per week is included in these 14 weeks. If overtime is not
used, then the 14 weeks can be extended until monies are expired.
iii. RPR shall be fully trained and certified to inspect all areas of work, including
welding (Certified Welding Inspector is not included), surface preparations, and
application of each layer of the coating system. This includes but is not limited to
certification as an Association for Materials Protection and Performance (AMPP)
Coatings Inspector (formerly governed by NACE and SSPC), and contractor to
provide a certification as a Certified Welding Inspector (CWI) through the
American Welding Society for the RPR review.
8. Design Coordination
i. Attend meetings and coordinate with franchise utility providers and others,
including sharing of files and other documents, as requested by City. This includes
10 meetings.
9. Exclusions
i. Attending City Council Meetings beyond those mentioned in Section B.1. above.
ii. Field and topographical surveys, including the establishment of control points and
benchmarks.
iii. Deed research and legal descriptions for easements.
iv. Easement acquisition assistance.
v. Permitting not specifically defined above.
vi. Geotechnical investigation of the project site.
vii. Environmental, archeological, and cultural evaluations of the project site.
viii. Assistance in obtaining project financing, grants, and loans.
ix. Construction Staking of Right-of-Way lines,property lines, and easements.
x. Full-time construction observation services beyond those mentioned above.
xi. Services following construction contract closeout during the warranty period of
the project other than those mentioned above.
xii. Services resulting from significant changes in the scope, extent,or character of the
portions of the Project designed or specified by the Consultant including, but not
limited to, changes in size, complexity, Client's schedule, character of
construction, and method of financing. These services may also be as a result of
changes in laws or regulations after the signing of this Agreement or other causes
beyond the Consultant's control.
xiii. Serving as a consultant or witness for the Client in any litigation,arbitration,and/or
other dispute resolution process related to the Project.
xiv. Requirements and/or preparation of applications, documents, and reports for
grants.
xv. Additional and extended services during construction made necessary by(1)work
damaged by fire or other cause during construction, (2) a significant amount of
defective or neglected work by any contractor, (3) acceleration of the progress
schedule involving service beyond normal working hours, (4) default by any
Contractor, (5) significant delays, changes, or price increases caused directly or
indirectly by shortages of materials, equipment, or energy, and (6) failure of the
Contractor to complete the work within the assumed construction contract time.
xvi. Special services in connection with partial utilization of any part of the Project by
Client prior to substantial completion.
xvii. Review of more than two (2)resubmittals of each shop drawing/submittal.
xviii. Evaluation of unusually complex or unreasonably numerous claims submitted by
the Contractor and/or others in connection with the work.
xix. Other services performed by the Consultant not otherwise provided for in this
Agreement.
SUMMARY OF COSTS
1. Lump Sum fee for design and construction administration services for the Bicentennial Park
Elevated Tank Inspection/Design/Rehabilitation and construction inspection/observation of
$390,000.00 distributed between scope elements as follows:
Project Administration and Management $9,606.00
Tank Inspection $18,417.00
Rehabilitation Design Plans and Spec &Franchise Coord. $95,876.00
Bidding Administration $11,726.00
Construction Administration $16,523.00
Construction Observation $16,527.00
Resident Project Representation(Inspection) $197,640.00
Design Coordination $12,776.00
Design Contingency $10,909.00
Total Eng/Design/Inspection $390,000.00