Item 3B-3 November CIP Report CAPITAL
IMP OVEMENTS
PROGRAM
REPORT
NOVEMBER 2026
ry
r e
r,
l o
in Ily /oft bla
ABOUT THE CIP REPORT
The City of Southlake is committed to keeping the community informed about the progress of major
infrastructure investments. This monthly report shares updates on all active Capital Improvements
Program (CIP) projects.
HOW TO READ THIS REPORT
This monthly Capital Improvements Program (CIP) Report provides the current status
of all active projects, meaning projects that are currently in preconstruction, which
includes design, property or easement acquisition, study, or those actively in construction.
Each project highlight includes key details such as its current phase, percentage of
completion, adopted budget, and whether it is tracking under, at, or over budget.
Only active projects are included in this report. Projects that have not yet
entered preconstruction, or those that have been completed, are not shown here.
By reviewing this report each month, readers can track the City's progress in delivering CIP projects,
from early design through construction completion, ensuring transparency and accountability in how
public funds are invested.
UNDERSTANDING THE PROJECT HIGHLIGHTS
Each project highlight includes:
• Project Description - A short description of the outcome of the project.
• CIP Project Number - Reference to the Capital Improvements Program (CIP) Adopted Budget
project number. Useful for cross-referencing for more information about the project.
• Project Status - A quick reference to whether the project is on track, delayed, or otherwise
impacted.
• Project Phase - Indicates the current phase of the project.
• Overall Progress (Current Phase) - Percentage of completion for the current phase.
• CIP Funding Source(s) - Reflects the fund or funds that the project is receiving money through.
• Adopted Budget- The amount of funding currently awarded through the FY 2025 Capital Budget
and prior fiscal years. This does not include planned funding for future fiscal years.
• Future Planned Funding:The amount of funding currently planned for future fiscal years.Typicially
these will be an estimate based on the design.
• Budget Adherence - Shows whether the project is currently under budget, on target, or over
budget.
• Project Update - Gives a short summary of progress since the end of the previous month,
highlighting major milestones, current work, upcoming activities, or public impacts. Updates are
intentionally brief, focusing on information most relevant to City Council and the public.
• Department/ Engineering Firm / General Contractor - Identifies the City department managing
the project and, if awarded, the firms responsible for design and construction.
For full project descriptions and more details, visit www.CityofSouthlake.com/CIP.
in Ily /oft bla
. �� � ..
-
.��
.
hip
-•��,� �� .
�
■� � - � � � '
-
_�
� r¥ �-
: •� -. . .
�
CONTINENTAL BLVD. INTERSECTION - - •
Project Description: Realigns the intersection with
a new traffic signal, turn lane, and paving to reduce
congestion, and drainage improvements. This project is
a companion project to S. Peytonville & W. Continental
Intersection Improvements. INN"LiXal*P }
CIP Project Number: 2022-07c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 90%
CIP Funding Source(s): General Fund, Roadway Impact -
Fee Fund, Tarrant County Bond 1
Adopted Budget: $8,900,000 '
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: Work in this phase has reached substantial completion. A walk through was held
October 6th and the contractor is currently working through punch list items. City staff will still be
coordinating with TXDOT for a final inspection and then a 30-day testing period is required prior to
TXDOT's acceptance. Final completion of this phase of the work is expected by the end of the year.
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: McMahon Contracting LP
S. • NVILLE & W. CONTINENTAL INTERSECTION - - •
Project Description: Installs a landscaped roundabout
with drainage upgrades at the Continental Boulevard
and South Peytonville Avenue intersection. This project
is a companion project to FM 1938 & Continental Blvd.
Intersection Improvements. k—LJ:c-W-W-1—'N
CIP Project Number: 2022-17c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 10%
1
CIP Funding Source(s): General Fund, Utility Fund,
Roadway Impact Fee Fund, Storm Water Utility System, k �
Tarrant County Bond '
Adopted Budget: $6,185,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: City utility relocations resumed October 5th. Minimal traffic impacts are expected during
remaining utility work, as this work is located outside of the roadway. The utility work is expected to
continue through the end of the year. Project completion is anticipated Summer 2028.
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: McMahon Contracting LP
CIP REPORT NOVEMBER 2026 12
SOUTHWESTERN •
(FORMERLY •
Project Description: Extends Southwestern Street to
Brumlow Avenue to provide improved industrial area
access. 4
CIP Project Number: 2022-15 26
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 99%
CIP Funding Source(s): General Fund, Utility Fund,
Storm Water Utility System
Adopted Budget: $9,270,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: The 99% design has been completed. The City's consultant is continuing to conduct
ROW acquisition negotiations with adjacent property owners. The consultant will complete the
design once the ROW negotiations approach finalization. Once the ROW is acquired and the design is
completed, the project will be let out for bid.
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
N. CARROLL AVE. CORRIDOR
Project Description: Improves the corridor with #
medians, turn lanes, pavement markings, and safer
intersections for vehicles and pedestrians.
CIP Project Number: 2022-09 �
Project Status: In Progress
Project Phase: Construction 5
Overall Progress (Current Phase): 95%
� r
CIP Funding Source(s): General Fund �..
Adopted Budget: $2,070,000
Future Planned Funding: $0
Budget Adherence: On Target i
Project Update: Construction remains substantially complete. The remaining signal work at SH 114 and
N. Carroll Avenue has been completed, and the City is awaiting TxDOT's final inspection to begin the 30-
day testing period prior to TxDOT resuming maintenance of the intersection. The Texas Department of
Licensing and Regulation curb ramp correction is also being coordinated, with construction anticipated
to begin in early November and take approximately three days to complete. Project completion remains
anticipated in Fall 2026.
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: Tejas Cutters
CIP REPORT NOVEMBER 2026 13
RANDOL MILL WATER AND SIDEWALK IMPROVEMENTS
Project Description: Constructs a new sidewalk and
upsizes the existing water line from 8 inches to 12
inches along Randoll Mill Avenue, along with drainage
improvements. N
CIP Project Number: 2022-33c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 95%
CIP Funding Source(s): General Fund, Utility Fund,
Water Impact Fee Fund
Adopted Budget: $3,400,000 � #
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: This project is substantially complete. Pre-walkthroughs were conducted in July,
and the contractor is addressing the remaining punch-list items. A state accessibility inspection was
performed on August 18 by a Registered Accessibility Specialist on behalf of the Texas Department of
Licensing and Regulation (TDLR), and the resulting report identified no required corrections. Staff has
identified additional safety and quality enhancements beyond the project's legal requirements. A change
order is currently being negotiated to complete these improvements, including concrete and handrail
adjustments. The project is expected to be fully completed within the next few months.
Department: Public Works
Engineering Firm: KSA
General Contractor: Quality Excavation, LLC
DOVE SIDEWALK PHASE 1
Project Description: Constructs sidewalk between
Lonesome Dove Road and Heather Lane #
a�
r ■
CIP Project Number: 2022-02 1 t
Project Status: On Hold
Project Phase: Pre-Design
Overall Progress (Current Phase): 98%
CIP Funding Source(s): General Fund
Adopted Budget: $505,000 d
Future Planned Funding: $0 (estimate)
Budget Adherence: On Target
Project Update: Final schematic design was provided
to staff in early March. Staff has begun coordination efforts with affected residents as well as the City's
concrete contractor, Apex Concrete Construction, Inc. Staff has submitted plans to Texas Department
of Licensing and Regulation (TDLR) for regulatory review in October and construction is anticipated
to begin this Fall. The City competitively bid its existing contract with Apex, which covers the scope of
this project. Apex's pricing is approximately 52% ($268,080) below the City's benchmark, which uses
average unit prices plus one standard deviation based on 24 months of TxDOT bid data. Using the
contract will help expedite construction of the amenities requested by the community.
Department: Public Works
Engineering Firm: KSA
General Contractor: Not Awarded Yet
CIP REPORT NOVEMBER 202614
FM 0. IMPROVEMENTS
Project Description: Improves the intersection at
Southlake Boulevard and Pearson/Union Church with
new turn lanes, better traffic flow, and a sidewalk along
Pearson.
CIP Project Number: 2022-13c
Project Status: On Hold
Project Phase: Design
Overall Progress (Current Phase): 90%
CIP Funding Source(s): General Fund, Roadway Impact
Fee Fund, Storm Water Utility System, City of Keller
Adopted Budget: $960,000
Future Planned Funding: $2,440,000 (Estimate)
Budget Adherence: On Target
Project Update: No major changes since last update. The most recent milestone was the completion
of design in May 2024. Construction of the project was placed on hold to prioritize the Continental
Intersections improvements in the corridor. The project will resume once those improvements are
complete in order to maintain alternate means of travel for area residents.
Department: Public Works
Engineering Firm: DEC
General Contractor: Not Awarded Yet
CIP REPORT NOVEMBER 2026 5
This page intentionally left blank,
OOF
CIP REPORT NOVEMBER 2026 16
�r
ml -L --
a
i
ry 7 �_ •. _
- log
441
J �
INTERSECTIONON •
Project Description: Enhances intersections along SH
114 with landscaping and corridor beautification.
CIP Project Number: 2024-07 2 ` �r
Project Status: In Progress _
n
Project Phase: Construction� c o
Overall Progress (Current Phase): 70%
Y
CIP Funding Source(s): General Fund and TxDOT '`�" � y• ; • r '
Green Ribbon Funding } '•yLr�
Adopted Budget: $400,000
•-t �_• -y}r }�
Future Planned Funding: $0
Budget Adherence: On Target - - -
I
Project Update: Phase 2 construction remains under way, and the final phase of construction including
the installation of plant material has restarted with the arrival of cooler weather. The project is
anticipated to be complete, moving into the warranty period in late fall.
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Central North Construction LLC.
INTERSECTIONON : •
Project Description: Enhances intersections on SH 114
with landscaping and corridor beautification.
CIP Project Number: 2024-07 3 �-
■
Project Status: In Progress
Project Phase: Bidding/Pre-Con
Overall Progress (Current Phase): 90%
Y{
CIP Funding Source(s): General Fund and TxDOT
Green Ribbon Funding L'
"1
Adopted Budget: $420,000 -
Future Planned Funding: $0 �
Budget Adherence: On Target ��
Project Update: Phase 3 was awarded the full - - - - J
$420,000 to begin work at the intersection of White Chapel and SH 114. Design work on this phase
has been completed, the project has been bid, TxDOT has provided their concurrence of award for
construction, and City Council awarded a bid for construction at the November 3rd meeting. A pre-
construction meeting has been scheduled and work on the site is set to begin in late fall of this year.
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
CIP REPORT NOVEMBER 2026 18
1938 MEDIAN LANDSCAPING
Project Description: Constructs landscape, irrigation,
and hardscape improvements on FM 1938 from FM 1709
to the Southlake Citylimits, consistent with landscaped
median improvements north of FM 1709. The City's
scope includes landscape, irrigation, and hardscape '�"
only.
CIP Project Number: 2024-06
Project Status: In Progress -'
Project Phase: Design ;,� Imo
Overall Progress (Current Phase): 100%
CIP Funding Source(s): General Fund
Adopted Budget: $1,650,000 �"�"
Future Planned Funding: 0 }
Budget Adherence: On Target
Project Update: The City is revising its final plan submittal with TxDOT. Once completed, the next phase
will be to approve an Advanced Funding Agreement (AFA) and Landscape Maintenance Agreement
(LMA) with TxDOT. It is anticipated that that the landscape improvements will be constructed by the
end of Summer 2027.
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
TOWERMUNICIPAL SERVICE CENTER AND PUBLIC SAFETY TRAINING
Project Description: Constructs a new Municipal
Service Center with space for Streets & Drainage,
Water, Wastewater, Environmental Services, and
Traffic, Facilities, along with administrative offices for
Utility Billing and a public safety training tower.
CIP Project Number: 2022-79c
Project Status: In Progress
Project Phase: Construction I
%9
Overall Progress (Current Phase): 81% �.,
R
CIP Funding Source(s): General Fund and Utility Fund
Adopted Budget: $46,600,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: During October, the contractor began to close up the walls and construct the hard
ceiling. They also installed windows and doors to seal the envelope of the Admin Building. At the
Service Bay Buildings, the contractor installed electrical fixtures, completed tiling and sealed the
concrete floors. Sitewide, the contractor constructed sidewalk and installed landscaping. At the Training
Tower, the contractor continued with construction of the 2nd level. The project is anticipated for
completion in early 2027.
Department: Public Works
Engineering Firm: RPGA (Architect)
General Contractor: Byrne (CMAR)
CIP REPORT NOVEMBER 2026 19
TOWN HALL PLAZA PARK
Project Description: Completes the redevelopment
of Family Park in Town Square with new landscape,
hardscape, park amenities, fountain upgrades,
pedestrian and safety enhancements, and repair/
replacement of existing infrastructure to enhance
visitor experience and event use.
CIP Project Number: 2024-66c
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 60% t
CIP Funding Source(s): Southlake Parks Development
Corporation
Adopted Budget: $8,138,319
Future Planned Funding: Pending final design
Budget Adherence: On Target
Project Update: The consultant submitted the 60% design. It is currently in review by City staff. The
CMAR has provided an estimate for the 60% design and the estimate is being used as the basis for the
FY 2027 CIP budgeting process.
Department: Community Services
Engineering Firm: Kimley-Horn
General Contractor: Fransen Pittman Construction
TURF REPLACEMENT PHASE 11 (NORTH PARK)
Project Description: Implements high impact park
improvements including conversion of athletic fields
from grass to turf as recommended in the Southlake
2035 Parks, Recreation & Open Space Master Plan. This
project will complete turf installations at North Park.
CIP Project Number: 2024-05 2
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 23%
CIP Funding Source(s): Southlake Parks Development
Corporation
Adopted Budget: $6,355,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: Construction currently continues on the lacrosse fields, with subgrade stabilization
and drainage infrastructure being constructed during the month of October. It is anticipated that the
improvements will be completed in Spring 2027.
Department: Community Services
Engineering Firm: Baird, Hampton & Brown
General Contractor: North Rock Construction & Associates, LLC
CIP REPORT NOVEMBER 2026 110
Ir - h
. L
lb Ci
r '' i . •tea ,� � f � �'�• l;'+��'*�• }± - ¢_•�•l�''� #
Y ` 1
} i- ' y 1■4
� •7 1 f ti
1 .H
j •N.
t1 u a r
Project Description: Installs a new 8-inch sewer line
along East Highland street to North Kimball Avenue.
This project is a companion project to upsize existing
6-inch to 12-inch water line along East Highland from
Blythe Lane to North Kimball Avenue.
CIP Project Number: 2022-85c
Project Status: In Progress
Project Phase: ROW/ Easement Acquisition T
Overall Progress (Current Phase): 65%
CIP Funding Source(s): Sanitary Sewer Impact Fee and
Utility Fund
Adopted Budget: $245,000
Future Planned Funding: $2,395,000 (Estimate)
Budget Adherence: On Target
Project Update: No major changes since last update. Coordination with property owners for required
easements is ongoing. Updated offers were sent to three of the five property owners, and a meeting has
been held with one; one property is currently in probate, and one remains under legal review regarding
prescriptive right-of-way. TNP has been in ongoing negotiations and one easement has been finalized
so far. Depending on negotiation outcomes, alternative alignments may be considered as the project
advances toward anticipated construction in Summer 2027.
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
JONES BRANCH NEAR RAINTREE DR.
Project Description: Provides erosion control and
sewer protection improvements along Jones Branch
near Raintree Drive.
CIP Project Number: 2022-45c 2
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 5%
CIP Funding Source(s): Utility Fund and Storm Water
Utility System
Adopted Budget: $158,000
Future Planned Funding: $2,838,000 (Estimate)
Budget Adherence: On Target
Project Update: Engineering evaluation continues for the Jones Branch Sewer Protection Improvements
Project. Field investigations have been completed, and the consultant is finalizing the Existing Conditions
Assessment Report, anticipated in early November. The 30% conceptual design alternatives are
expected in mid-December. The project remains focused on identifying and prioritizing improvements
needed to protect the existing sanitary sewer infrastructure along Jones Branch Creek.
Department: Public Works
Engineering Firm: Westwood
General Contractor: Not Awarded Yet
CIP REPORT NOVEMBER 2026 112
JONES BRANCH NEAR SIMMONS
Project Description: Provides erosion control and
sewer protection improvements along Jones Branch
near Simmons Court.
CIP Project Number: 2022-51
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 5%
CIP Funding Source(s): Utility Fund and Storm Water
Utility System
Adopted Budget: $885,000
Future Planned Funding: $0 (Estimate)
Budget Adherence: On Target 1
Project Update: Engineering evaluation continues for the Jones Branch Sewer Protection Improvements
Project. Field investigations have been completed, and the consultant is finalizing the Existing Conditions
Assessment Report, anticipated in early November. The 30% conceptual design alternatives are
expected in mid-December. The project remains focused on identifying and prioritizing improvements
needed to protect the existing sanitary sewer infrastructure along Jones Branch Creek.
Department: Public Works
Engineering Firm: Westwood
General Contractor: Not Awarded Yet
LOCH MEADOWS • •
Project Description: Expands the Loch Meadows Lift
Station capacity from 0.4 MGD to 0.8 MGD to support
future development and provide additional wastewater
capacity for planned septic-to-sewer conversion .
projects within the N-18 basin.
r
CIP Project Number: 2026-05
Project Status: In Progress
Project Phase: Pre-Design
Overall Progress (Current Phase): 30% w ,:
CIP Funding Source(s): Utility Fund
Adopted Budget: $550,000
Future Planned Funding: $3,850,000
Budget Adherence: On Target
Project Update: The Loch Meadows Lift Station Expansion Project remains in the preliminary engineering
phase. The design consultant has completed initial field testing and hydraulic analysis and is preparing
the Preliminary Design Report. The study is evaluating improvements to allow Loch Meadows and
Lonesome Dove to operate as separate systems. Additional monitoring results will be incorporated into
the study to support the development of final recommendations.
Department: Public Works
Engineering Firm: Freese and Nichols, Inc.
General Contractor: Not Awarded Yet
CIP REPORT NOVEMBER 2026 113
LONESOME DOVE/SHADY • IMPROVEMENTS
Project Description: Installs emergency backup pumps
and generators at both lift stations. Upgrades electric
and SCADA systems at Lonesome Dove lift station.
CIP Project Number: 2024-04
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 0%
CIP Funding Source(s): Utility Fund
Adopted Budget: $2,810,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: Since the previous update, the contractor has submitted a revised construction schedule
reflecting additional delays associated with material procurement and remaining design coordination.
Staff continues working with the contractor and design consultant to resolve outstanding items and
prepare for construction. Mobilization at the Lonesome Dove Lift Station is now anticipated for late
March 2027, followed by Shady Lane in mid-June. Overall project completion is currently anticipated by
September 2027.
Department: Public Works
Engineering Firm: Garver, LLC.
General Contractor: Felix Construction
BIG BEAR CREEK IMPROVEMENTS NEAR TIMBER COURT
Project Description: Provides erosion control and T
sewer realignment to protect sewer infrastructure
along Big Bear Creek near Timber Court.
CIP Project Number: 2022-45c 3
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 59%
CIP Funding Source(s): Storm Water Utility System
Adopted Budget: $135,000
Future Planned Funding: $620,000 (Estimate)
Budget Adherence: On Target
Project Update: No major changes since last update. Design reached 90 percent completion in July
2024, after which the project was placed on hold due to reprioritization. Staff has been coordinating with
a Colleyville resident regarding a required sanitary sewer easement. Work will resume as other projects
are completed or if reprioritization occurs.
Department: Public Works
Engineering Firm: VRX
General Contractor: Not Awarded Yet
CIP REPORT NOVEMBER 2026 114
EAGLE BEND & STRATHMORE SANITARY SEWER RECONSTRUCTION
Project Description: Replaces the existing 8-inch sewer
with a 10-inch line under Timarron Golf Course Creek.
CIP Project Number: 2023-14
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 76%
CIP Funding Source(s): Utility Fund
Adopted Budget: $200,000 �^
Future Planned Funding: $820,000 (Estimate)
Budget Adherence: On Target 4.
Project Update: No major changes since last update.
Design reached 90 percent completion in July 2024, and property owner coordination for easements is
ongoing. One of the three permanent easements has been acquired, while agreements with the Timarron
HOA and Golf Course remain under legal review. A required temporary easement has not yet been
secured. The project is on hold due to reprioritization and will resume as other projects conclude.
Department: Public Works
Engineering Firm: Westwood
General Contractor: Not Awarded Yet
HIGGINS BRANCH NEAR • • : - • •
Project Description: Provides erosion control and
sewer protection improvements along Higgins Branch
near Woodbrook Lane.
CIP Project Number: 2022-45c 1
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 73% X14% �%N
CIP Funding Source(s): Utility Fund and Storm Water '
Utility System
Adopted Budget: $185,000 `��� r
Future Planned Funding: $525,000 (Estimate) �+
Budget Adherence: On Target i
Project Update: No major changes since last update. Coordination with property owners regarding
access easements is ongoing. Two temporary easements have been acquired, while one permanent
access easement remains under legal review. The project is on hold due to reprioritization and will
resume as other projects are completed.
Department: Public Works
Engineering Firm: VRX
General Contractor: Not Awarded Yet
CIP REPORT NOVEMBER 2026 115
This page intentionally left blank,
OF
CIP REPORT NOVEMBER 2026 116
. � �,��iY' ��� r-•i 4 _• is -�•�I ���� ..� tY.
39' x� r
b:L
Ly ;
No
• 1
f r r
f
�y � rlr •r, .• �•
PF r r
L "rp,
I
WilliL. y'
Alf F
M '•y 10 r
k Pi
v 'y �+ pI*
v �
.q y
k yti
k 4
ti
EkdlkLL41
STORMWATER
�~
i ^r k � .� ,��}' � � �, tip• —,r -
MORGAN ROAD DRAINAGE - - •
Project Description: Constructs a new drainage ditch, R
culvert, and channel to reduce flooding risk on Morgan j r *10
Road. -� +—
CIP Project Number: 2022-47 x{ �-
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 90%
CIP FundingSource(s): Storm Water Utility System J `
Y Y x
Adopted Budget: $1,425,000 J
Future Planned Funding: $0 (Estimate)
Budget Adherence: On Target a
Project Update: No major changes since last update. The design consultant is finalizing construction
plans following completion of the 100% design review. With the alignment of underground facilities
established, City staff began coordinating with franchise utilities in March to identify and address
potential conflicts. Coordination with franchise utilities continued in August with Atmos Energy, currently
identified as the only conflict. Atmos Energy relocations are now complete. City staff is working to
coordinate with residents in the area and expects to hold a community meeting prior to advertising the
project for construction this winter.
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
CIP REPORT NOVEMBER 2026 118
�— i
- —� _ �� , L
.�' r � �M - ti� i�� -
i 3. '�} _
'' - 1
•t-'
1 �.
+ � _
4 �
I-
r ' �
?� .`-q�• r �•
.7 L � - � Y
1 } L
F.
_ .. _ti
'I
L
1 �
t ;4
•
1 �
. _�-`•
- f
i
��
-t-, a1 i I .
DOVE ELEVATED STORAGEREPAINT
Project Description: Repaints the interior and exterior
of the Dove Elevated Storage Tank, replaces structural
steel and yard piping components as needed, and
updates the tank's exterior graphics to extend the life
and appearance of this critical water system asset.
CIP Project Number: 2022-39
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 85%
A 7
CIP Funding Source(s): Utility Fund
Adopted Budget: $3,000,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: City staff and Bartlett & West have completed the evaluation of proposals received
on September 24 and identified the best value contractor for this rehab project. Construction contract
award is anticipated at the November 17, City Council meeting. Coordination with wireless carriers for
equipment relocation is ongoing in preparation for construction. Rehabilitation is anticipated to begin in
December 2026, with final completion required by May 1, 2027.
Department: Public Works
Engineering Firm: Bartlett & West
General Contractor: Not Awarded Yet
SOUTHLAKE PARK WATER IMPROVEMENTS
Project Description: Constructs a new 8-inch water
main along Crescent Drive, Hillside Drive, and Southlake
Park Drive to provide adequate fire protection, enhance
water quality, and make service available if requested.
CIP Project Number: 2026-03
Project Status: In Progress
Project Phase: Pre-Design
Overall Progress (Current Phase): 0%
CIP Funding Source(s): Utility Fund
Adopted Budget: $4,125,000
Future Planned Funding: Pending Final Design
Budget Adherence: On Target
Project Update: No major changes since last update. A funding application to the Texas Water
Development Board (TWDB) was submitted July 30, 2026, and funding awards are expected to be
announced this Fall. Design award is contingent upon results of the funding application by the TWDB,
but City is planning on award for design by spring 2027.
Department: Public Works
Engineering Firm: Not Awarded Yet
General Contractor: Not Awarded Yet
CIP REPORT NOVEMBER 2026 120
STATIONTW KING PUMP D•
Project Description: Upgrades the pump station with
a generator, replaces the existing pumps and motors
and adds a new pump and motor to the Low Pressure
Plane.
CIP Project Number: 2022-96c
Project Status: In Progress -�
Project Phase: Bidding/Pre-Con
Overall Progress (Current Phase): 100%
CIP Funding Source(s): Utility Fund, Water Impact Fee
Fund '
Adopted Budget: $15,475,000
Future Planned Funding: $0 (Estimate)
Budget Adherence: On Target
Project Update: Pre-construction meeting held October 21st, and award for construction management
and inspection approved for FNI at the November 3rd council. Contractor has begun pulling submittals
together for review and dependent on availability of the generator when the generator submittal is
approved the contractor intends to begin construction in December. The generator is the longest lead
time item on this project and current lead times vary from 56 weeks to 110 weeks.
Department: Public Works
Engineering Firm: Freese and Nichols
General Contractor: Not Awarded Yet
UPSIZE EXISTING 6-INCH TO 12-INCH WATER LINE ALONG EAST HIGHLAND FROM
BLYTHE LANE TO NORTH
Project Description: Replaces the existing 6-inch water
line with a 12-inch line to improve service and capacity. #
This project is a companion project to the East
Highland/Kimball 8-inch Sewer Line.
CIP Project Number: 2022-28c
Project Status: In Progress '
Project Phase: ROW/ Easement Acquisition j
Overall Progress (Current Phase): 65%
CIP Funding Source(s): Utility Fund, Water Impact Fee j
Fund
Adopted Budget: $825,000
Future Planned Funding: $2,475,000 (Estimate)
Budget Adherence: On Target
Project Update: No Major Changes since last update. Coordination with property owners for required
easements is ongoing. Updated offers were sent to three of the five property owners, and a meeting has
been held with one; one property is currently in probate, and one remains under legal review regarding
prescriptive right-of-way. TNP has been in ongoing negotiations and one easement has been finalized
so far. Depending on negotiation outcomes, alternative alignments may be considered as the project
advances toward anticipated construction in Summer 2027.
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
CIP REPORT NOVEMBER 2026 121
STATIONTW KING PUMP D•
Project Description: Installs additional pumps and
related infrastructure improvements, including a
protective masonry enclosure, fencing, and drainage
enhancements, to increase water system capacity,
improve flow and pressure to the north and east
portions of the City, and enhance the safety, security,
and reliability of the City's water infrastructure.
CIP Project Number: 2023-06
Project Status: Not Started
Project Phase: Pre-Design
Overall Progress (Current Phase): 0%
CIP Funding Source(s): Utility Fund, Water Impact Fee
Fund
Adopted Budget: $1,990,000
Future Planned Funding: $24,460,000 (Estimate)
Budget Adherence: On Target
Project Update: The design team met in August, September on-site, and October with Planning to
review project scope, operational needs, expectations, and planned platting. Staff anticipates presenting
the design contract to Council in January 2027.
Department: Public Works
Engineering Firm: Not Awarded Yet
General Contractor: Not Awarded Yet
ALTA VISTA WATER LINE REPLACEMENT - PLANNING
Project Description: Completes design, easement
acquisition, and coordination for the rehabilitation of
the Alta Vista 30-inch and 36-inch water transmission
main through sliplining, along with a condition
assessment of the Alta Vista Pump Station to support f
the long-term reliability of one of the City's primary
water supply lines. ?fir
CIP Project Number: 2023-05
Project Status: Not Started r ,
Project Phase: Inactive
Overall Progress (Current Phase): 0%
CIP Funding Source(s): Utility Fund, City of Keller
Adopted Budget: $3,600,000
Future Planned Funding: $37,000,000
Budget Adherence: On Target
Project Update: The City continues to coordinate with Keller on the Alta Vista Water Line Replacement
Project. Southlake has completed it's legal review of the Interlocal Agreement (ILA) and provided
the agreement to Keller for partial execution. Keller will remain the sole EPA grant recipient and
administrator and has identified an additional $1 million in federal funding, bringing total federal
funding for the project to $1.75 million. Following execution of the ILA, the project can proceed toward
consultant procurement and design.
Department: Public Works
Engineering Firm: Not Awarded Yet
General Contractor: Not Awarded Yet
CIP REPORT NOVEMBER 2026 122