Item 3B-2 CIP Report - AugustAUGUST 2026
The information in this report is updated as of July 31, 2026.
ITEM 3B-2
No Text
ABOUT THE CIP REPORT
The City of Southlake is committed to keeping the community informed about the progress of major
infrastructure investments. This monthly report shares updates on all active Capital Improvements
Program (CIP) projects.
HOW TO READ THIS REPORT
This monthly Capital Improvements Program (CIP) Report provides the current status
of all active projects, meaning projects that are currently in preconstruction, which
includes design, property or easement acquisition, study, or those actively in construction.
Each project highlight includes key details such as its current phase, percentage of
completion, adopted budget, and whether it is tracking under, at, or over budget.
Only active projects are included in this report. Projects that have not yet
entered preconstruction, or those that have been completed, are not shown here.
By reviewing this report each month, readers can track the City’s progress in delivering CIP projects,
from early design through construction completion, ensuring transparency and accountability in how
public funds are invested.
UNDERSTANDING THE PROJECT HIGHLIGHTS
Each project highlight includes:
• Project Description – A short description of the outcome of the project.
• CIP Project Number - Reference to the Capital Improvements Program (CIP) Adopted Budget
project number. Useful for cross-referencing for more information about the project.
• Project Status – A quick reference to whether the project is on track, delayed, or otherwise
impacted.
• Project Phase – Indicates the current phase of the project.
• Overall Progress (Current Phase) – Percentage of completion for the current phase.
• CIP Funding Source(s) - Reflects the fund or funds that the project is receiving money through.
• Adopted Budget – The amount of funding currently awarded through the FY 2025 Capital Budget
and prior fiscal years. This does not include planned funding for future fiscal years.
• Future Planned Funding: The amount of funding currently planned for future fiscal years. Typicially
these will be an estimate based on the design.
• Budget Adherence – Shows whether the project is currently under budget, on target, or over
budget.
• Project Update – Gives a short summary of progress since the end of the previous month,
highlighting major milestones, current work, upcoming activities, or public impacts. Updates are
intentionally brief, focusing on information most relevant to City Council and the public.
• Department / Engineering Firm / General Contractor – Identifies the City department managing
the project and, if awarded, the firms responsible for design and construction.
For full project descriptions and more details, visit www.CityofSouthlake.com/CIP.
No Text
ROADWAY
AUGUST 2026 | 2CIP REPORT
FM 1938 & CONTINENTAL BLVD. INTERSECTION IMPROVEMENTS
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: McMahon Contracting LP
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: All planned traffic signal improvements on Union Church were completed this summer.
Roadway improvements on the W. Continental Blvd side of the intersection paused during July to
provide time for a developer to complete work in the area. The pause in this area lasted four weeks,
with no apparent movement from the developer, construction restarted in this area the second week of
August. The northbound right-turn lane on Davis is now open, about half the construction on Continental
is complete, and construction in this phase is expected to be complete in October.
Project Description: Realigns the intersection with
a new traffic signal, turn lane, and paving to reduce
congestion, and drainage improvements. This project is
a companion project to S. Peytonville & W. Continental
Intersection Improvements.
CIP Project Number: 2022-07c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 80%
CIP Funding Source(s): General Fund, Roadway Impact
Fee Fund, Tarrant County Bond
Adopted Budget: $8,900,000
N. CARROLL AVE. CORRIDOR
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: Tejas Cutters
Project Update: Construction remains substantially complete. The pedestrian poles needed to
accommodate the upgraded radar detection system have been installed, and radar detection
programming at the SH 114 and N. Carroll Avenue intersection has been completed. Remaining work is
limited to installation of the internally lighted street name signs and retroreflective signal backplates.
Once complete, TxDOT will complete an inspection and accept the intersection. Prior to closing out the
project, N. Carroll Avenue will be restriped from the project limit to FM 1709. The project completion
remains on schedule and is anticipated to be completed in September 2026.
Project Description: Improves the corridor with
medians, turn lanes, pavement markings, and safer
intersections for vehicles and pedestrians.
CIP Project Number: 2022-09
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 95%
CIP Funding Source(s): General Fund
Adopted Budget: $2,070,000
Future Planned Funding: $0
Budget Adherence: On Target
AUGUST 2026 | 3CIP REPORT
RANDOL MILL WATER AND SIDEWALK IMPROVEMENTS
Department: Public Works
Engineering Firm: KSA
General Contractor: Quality Excavation, LLC
Budget Adherence: On Target
Project Update: This project is substantially complete. Pre-walkthroughs were conducted in July and
punch list items are being addressed by the contractor. State level inspection through Texas Department
of Licensing and Regulation (TDLR) by a Registered Accessibility Specialist (RAS) is scheduled August
18th. Final walkthrough and project completion expected in August.
Project Description: Constructs a new sidewalk and
upsizes the existing water line from 8 inches to 12
inches along Randoll Mill Avenue, along with drainage
improvements.
CIP Project Number: 2022-33c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 95%
CIP Funding Source(s): General Fund, Utility Fund,
Water Impact Fee Fund
Adopted Budget: $3,400,000
Future Planned Funding: $0
S. PEYTONVILLE & W. CONTINENTAL INTERSECTION IMPROVEMENTS
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: McMahon Contracting LP
Adopted Budget: $6,185,000
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: To minimize impacts during the school year, the City approved a revised construction
sequencing plan that temporarily shifted work from the Davis Boulevard roadway improvements to
culvert and isolation valve installation while construction activities near Davis were paused. During
July, the contractor moved forward with this work and focused on restoring the roadway before the
school year. Utility relocations are expected to resume in October 2026, with overall project completion
anticipated in Summer 2028.
Project Description: Installs a landscaped roundabout
with drainage upgrades at the Continental Boulevard
and South Peytonville Avenue intersection. This project
is a companion project to FM 1938 & Continental Blvd.
Intersection Improvements.
CIP Project Number: 2022-17c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 1%
CIP Funding Source(s): General Fund, Utility Fund,
Roadway Impact Fee Fund, Storm Water Utility System,
Tarrant County Bond
AUGUST 2026 | 4CIP REPORT
MUSTANG COURT INDUSTRIAL AREA ACCESS
Department: Public Works
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
Project Update: The 90% design has been completed. The City’s consultant is continuing to conduct
ROW acquisition negotiations with adjacent property owners. Discussions are also being conducted with
the utility companies regarding relocation of existing facilities. The consultant will continue advancing
the design to 99% while the ROW discussions are continuing. Once the ROW is acquired and the design
is completed, the project will be let out for bid.
Project Description: Extends Southwestern Street to
Brumlow Avenue to provide improved industrial area
access.
CIP Project Number: 2022-15
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 90%
CIP Funding Source(s): General Fund, Utility Fund,
Storm Water Utility System
Adopted Budget: $1,975,000
Future Planned Funding: $5,050,000 (Estimate)
Budget Adherence: On Target
DOVE SIDEWALK PHASE 1
Department: Public Works
Engineering Firm: KSA
General Contractor: Not Awarded Yet
to staff in early March. Staff has begun coordination efforts with affected residents, and will need to
submit plans to Texas Department of Licensing and Regulation (TDLR) for regulatory review, and
obtain a construction estimate from the City’s concrete contractor, Apex Concrete Construction, Inc.
Construction is anticipated to begin this Fall. Apex’s contract with the City covers the scope of work
for this project and was already competitively bid. Utilizing Apex’s contract for this work will greatly
expedite this project and allow the City to provide amenities requested by the community.
Project Description: Constructs sidewalk between
Lonesome Dove Road and Heather Lane.
CIP Project Number: 2022-02 1
Project Status: On Hold
Project Phase: Pre-Design
Overall Progress (Current Phase): 98%
CIP Funding Source(s): General Fund
Adopted Budget: $505,000
Future Planned Funding: $0 (estimate)
Budget Adherence: On Target
Project Update: Final schematic design was provided
AUGUST 2026 | 5CIP REPORT
FM 1709 & PEARSON INTERSECTION IMPROVEMENTS
Department: Public Works
Engineering Firm: DEC
General Contractor: Not Awarded Yet
Budget Adherence: On Target
Project Update: No major changes since last update. The most recent milestone was the completion
of design in May 2024. Construction of the project was placed on hold to prioritize the Continental
Intersections improvements in the corridor. The project will resume once those improvements are
complete in order to maintain alternate means of travel for area residents.
Project Description: Improves the intersection at
Southlake Boulevard and Pearson/Union Church with
new turn lanes, better traffic flow, and a sidewalk along
Pearson.
CIP Project Number: 2022-13c
Project Status: On Hold
Project Phase: Design
Overall Progress (Current Phase): 90%
CIP Funding Source(s): General Fund, Roadway Impact
Fee Fund, Storm Water Utility System, City of Keller
Adopted Budget: $960,000
Future Planned Funding: $2,440,000 (Estimate)
AUGUST 2026 | 6CIP REPORT
This page intentionally left blank.
PARKS, FACILITIES
& COMMUNITY
ENHANCEMENTS
AUGUST 2026 | 8CIP REPORT
INTERSECTION ENHANCEMENTS ON SH 114 GREEN RIBBON PHASE 2
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Central North Construction LLC.
Project Update: Phase 2 construction remains under way, and the final phase of construction including
the installation of plant material is on hold until cooler weather arrives. The project is anticipated to be
complete, moving into the warranty period early this fall.
Project Description: Enhances intersections along SH
114 with landscaping and corridor beautification.
CIP Project Number: 2024-07 2
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 60%
CIP Funding Source(s): General Fund and TxDOT
Green Ribbon Funding
Adopted Budget: $400,000
Future Planned Funding: $0
Budget Adherence: On Target
MUNICIPAL SERVICE CENTER AND PUBLIC SAFETY TRAINING TOWER
Department: Public Works
Engineering Firm: RPGA (Architect)
General Contractor: Byrne (CMAR)
Budget Adherence: On Target
Project Update: Construction continues to progress on the Municipal Service Center and Public
Safety Training Tower. During July, underground mechanical, electrical, and plumbing (MEP) work
and slab preparation advanced at the Administration Building, while Service Bay framing, insulation,
and MEP rough-in inspections were substantially completed. Pole barn construction was completed,
covered parking structures continued, and Training Tower foundation work remained underway. Site
improvements, including landscaping and fencing, also began as the project remains on schedule with
expected completion in early 2027.
Project Description: Constructs a new Municipal
Service Center with space for Streets & Drainage,
Water, Wastewater, Environmental Services, and
Traffic, Facilities, along with administrative offices for
Utility Billing and a public safety training tower.
CIP Project Number: 2022-79c
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 65%
CIP Funding Source(s): General Fund and Utility Fund
Adopted Budget: $46,600,000
Future Planned Funding: $0
AUGUST 2026 | 9CIP REPORT
INTERSECTION ENHANCEMENTS ON SH 114 GREEN RIBBON PHASE 3
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
Project Update: Phase 3 was awarded the full $420,000 to begin work at the intersection of White
Chapel and SH 114. Phase 3 bids were opened earlier this summer and City staff and Kimley Horn are
currently awaiting TxDOT concurrence of the bid award prior to bringing an award for construction to
Council this fall.
Project Description: Enhances intersections on SH 114
with landscaping and corridor beautification.
CIP Project Number: 2024-07 3
Project Status: In Progress
Project Phase: Pre-Design
Overall Progress (Current Phase): 90%
CIP Funding Source(s): General Fund and TxDOT
Green Ribbon Funding
Adopted Budget: $420,000
Future Planned Funding: $0
Budget Adherence: On Target
1938 MEDIAN LANDSCAPING
Department: Community Services
Engineering Firm: Kimley Horn
General Contractor: Not Awarded Yet
Future Planned Funding: $0
Budget Adherence: On Target
Project Update: This project involves the construction of a raised concrete median from FM 1709 in
Southlake, through Keller and into North Richland Hills. The City aims to partner with TxDOT to include
landscape improvements on the new medians. The City consultant submitted the 100% design. The next
phase is to approve an Advanced Funding Agreement (AFA) and Landscape Maintenance Agreement
(LMA) with TxDOT. TxDOT completed construction of the medians with temporary landscaping (sod)
within the City of Southlake. It is anticipated that the landscape improvements will be constructed by
Summer 2027 as a later phase of the project.
Project Description: Constructs landscape, irrigation,
and hardscape improvements on FM 1938 from FM 1709
to the Southlake City limits, consistent with landscaped
median improvements north of FM 1709. The City’s
scope includes landscape, irrigation, and hardscape
only.
CIP Project Number: 2024-06
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 95%
CIP Funding Source(s): General Fund
Adopted Budget: $1,650,000
AUGUST 2026 | 10CIP REPORT
TOWN HALL PLAZA PARK
Department: Community Services
Engineering Firm: Kimley-Horn
General Contractor: Not Awarded Yet
Adopted Budget: $7,938,319
Future Planned Funding: Pending final design
Budget Adherence: On Target
Project Update: The consultant has completed the 30% design on the project. An RFQ process was
completed to prequalify CMAR candidates for this project at which point an RFP was issued to the most
qualified candidates who submitted proposals and completed in person interviews with City staff. Staff
have chosen a final candidate to move forward as the CMAR for the design portion of this project.
Project Description: Completes the redevelopment
of Family Park in Town Square with new landscape,
hardscape, park amenities, fountain upgrades,
pedestrian and safety enhancements, and repair/
replacement of existing infrastructure to enhance
visitor experience and event use.
CIP Project Number: 2024-66c
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 30%
CIP Funding Source(s): Southlake Parks Development
Corporation
TURF REPLACEMENT PHASE II (NORTH PARK)
Department: Community Services
Engineering Firm: Baird, Hampton & Brown
General Contractor: Not Awarded Yet
Future Planned Funding: Pending final design
Budget Adherence: On Target
Project Update: The project has been let out to bid, and staff have completed a best value analysis
on the four bids that were received. An award for construction is being brought forward to Council in
September, and construction is anticipated to begin shortly after the award date.
Project Description: Implements high impact park
improvements including conversion of athletic fields
from grass to turf as recommended in the Southlake
2035 Parks, Recreation & Open Space Master Plan. This
project will complete turf installations at North Park.
CIP Project Number: 2024-05 2
Project Status: In Progress
Project Phase: Contract Award
Overall Progress (Current Phase): 100%
CIP Funding Source(s): Southlake Parks Development
Corporation
Adopted Budget: $5,673,000
STORMWATER
AUGUST 2026 | 12CIP REPORT
MORGAN ROAD DRAINAGE IMPROVEMENTS
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
Project Update: The design consultant is finalizing construction plans following completion of the 100%
design review. Coordination with franchise utilities continued during July, with Atmos Energy identified
as the only remaining utility conflict and relocation work expected to be completed in August. Following
utility relocations, the City will hold a community meeting before advertising the project for construction
this winter.
Project Description: Constructs a new drainage ditch,
culvert, and channel to reduce flooding risk on Morgan
Road.
CIP Project Number: 2022-47
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 90%
CIP Funding Source(s): Storm Water Utility System
Adopted Budget: $1,425,000
Future Planned Funding: $0 (Estimate)
Budget Adherence: On Target
WASTEWATER
AUGUST 2026 | 14CIP REPORT
JONES BRANCH NEAR RAINTREE DR.
Department: Public Works
Engineering Firm: Westwood
General Contractor: Not Awarded Yet
Project Update: During July, the consultant initiated field investigations for the Jones Branch Sewer
Protection Improvements Project, including topographic surveying, aerial LiDAR mapping, and
sanitary sewer CCTV inspections. Information collected will be used to refine the design of prioritized
stabilization improvements to protect existing sanitary sewer infrastructure within the Jones Branch
corridor.
Project Description: Provides erosion control and
sewer protection improvements along Jones Branch
near Raintree Drive.
CIP Project Number: 2022-45c 2
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 5%
CIP Funding Source(s): Utility Fund, Storm Water
Utility System
Adopted Budget: $158,000
Future Planned Funding: $2,838,000 (Estimate)
Budget Adherence: On Target
JONES BRANCH NEAR SIMMONS CT
Department: Public Works
Engineering Firm: Westwood
General Contractor: Not Awarded Yet
Project Update: During July, the consultant initiated field investigations for the Jones Branch Sewer
Protection Improvements Project, including topographic surveying, aerial LiDAR mapping, and
sanitary sewer CCTV inspections. Information collected will be used to refine the design of prioritized
stabilization improvements to protect existing sanitary sewer infrastructure within the Jones Branch
corridor.
Project Description: Provides erosion control and
sewer protection improvements along Jones Branch
near Simmons Court.
CIP Project Number: 2022-51
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 5%
CIP Funding Source(s): Utility Fund, Storm Water
Utility System
Adopted Budget: $885,000
Future Planned Funding: $0 (Estimate)
Budget Adherence: On Target
AUGUST 2026 | 15CIP REPORT
LOCH MEADOWS LIFT STATION EXPANSION
Department: Public Works
Engineering Firm: Freese and Nichols, Inc.
General Contractor: Not Awarded Yet
Budget Adherence: On Target
Project Update: The project kickoff meeting with Freese and Nichols (FNI) was held in June for the Loch
Meadows Lift Station Expansion Project. Staff has provided available record drawings, GIS information,
and background data to support the study. Flow monitoring equipment has been installed, and
drawdown testing at the Loch Meadows and Lonesome Dove Lift Stations was completed in July. FNI is
reviewing the collected data and will use the results to develop improvement recommendations for the
lift station system.
Project Description: Expands the Loch Meadows Lift
Station capacity from 0.4 MGD to 0.8 MGD to support
future development and provide additional wastewater
capacity for planned septic-to-sewer conversion
projects within the N-18 basin.
CIP Project Number: 2026-05
Project Status: In Progress
Project Phase: Pre-Design
Overall Progress (Current Phase): 30%
CIP Funding Source(s): Utility Fund
Adopted Budget: $550,000
Future Planned Funding: $3,850,000
LONESOME DOVE/SHADY LANE LIFT STATION IMPROVEMENTS
Department: Public Works
Engineering Firm: Garver, LLC.
General Contractor: Felix Construction
Project Update: Since the previous update, the City and contractor have finalized a change order to
address design revisions, allowing the contractor to move forward with ordering project materials.
Staff continues coordinating with the contractor, design consultant, and Public Works Operations on
construction planning and project sequencing. The contractor is preparing an updated project schedule
that will establish the anticipated construction timeline and mobilization.
Project Description: Installs emergency backup pumps
and generators at both lift stations. Upgrades electric
and SCADA systems at Lonesome Dove lift station.
CIP Project Number: 2024-04
Project Status: In Progress
Project Phase: Construction
Overall Progress (Current Phase): 0%
CIP Funding Source(s): Utility Fund
Adopted Budget: $2,810,000
Future Planned Funding: $0
Budget Adherence: On Target
AUGUST 2026 | 16CIP REPORT
E HIGHLAND/KIMBALL 8” SEWER LINE
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
Future Planned Funding: $2,395,000 (Estimate)
Budget Adherence: On Target
Project Update: Coordination with property owners for required easements has restarted. Updated
offers have been sent to three of the five property owners, and a meeting has been held with one; one
property is currently in probate, and one remains under legal review regarding prescriptive right-of-
way. TNP has been in ongoing negotiations and has facilitated required paperwork for one agreement
so far. Easement coordination is expected to continue in the coming months. Depending on negotiation
outcomes, alternative alignments may be considered as the project advances toward anticipated
construction in summer 2027.
Project Description: Installs a new 8-inch sewer line
along East Highland street to North Kimball Avenue.
This project is a companion project to upsize existing
6-inch to 12-inch water line along East Highland from
Blythe Lane to North Kimball Avenue.
CIP Project Number: 2022-85c
Project Status: In Progress
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 65%
CIP Funding Source(s): Sanitary Sewer Impact Fee,
Utility Fund
Adopted Budget: $245,000
HIGGINS BRANCH NEAR WOODBROOK LN
Department: Public Works
Engineering Firm: VRX
General Contractor: Not Awarded Yet
Project Update: No major changes since last update. Coordination with property owners regarding
access easements is ongoing. Two temporary easements have been acquired, while one permanent
access easement remains under legal review. The project is on hold due to reprioritization and will
resume as other projects are completed.
Project Description: Provides erosion control and
sewer protection improvements along Higgins Branch
near Woodbrook Lane.
CIP Project Number: 2022-45c 1
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 73%
CIP Funding Source(s): Utility Fund, Storm Water
Utility System
Adopted Budget: $185,000
Future Planned Funding: $525,000 (Estimate)
Budget Adherence: On Target
AUGUST 2026 | 17CIP REPORT
BIG BEAR CREEK IMPROVEMENTS NEAR TIMBER COURT
Department: Public Works
Engineering Firm: VRX
General Contractor: Not Awarded Yet
Project Update: No major changes since last update. Design reached 90 percent completion in July
2024, after which the project was placed on hold due to reprioritization. Staff has been coordinating with
a Colleyville resident regarding a required sanitary sewer easement. Work will resume as other projects
are completed or if reprioritization occurs.
Project Description: Provides erosion control and
sewer realignment to protect sewer infrastructure
along Big Bear Creek near Timber Court.
CIP Project Number: 2022-45c 3
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 59%
CIP Funding Source(s): Storm Water Utility System
Adopted Budget: $135,000
Future Planned Funding: $620,000 (Estimate)
Budget Adherence: On Target
EAGLE BEND & STRATHMORE SANITARY SEWER RECONSTRUCTION
Department: Public Works
Engineering Firm: Westwood
General Contractor: Not Awarded Yet
Design reached 90 percent completion in July 2024, and property owner coordination for easements is
ongoing. One of the three permanent easements has been acquired, while agreements with the Timarron
HOA and Golf Course remain under legal review. A required temporary easement has not yet been
secured. The project is on hold due to reprioritization and will resume as other projects conclude.
Project Description: Replaces the existing 8-inch sewer
with a 10-inch line under Timarron Golf Course Creek.
CIP Project Number: 2023-14
Project Status: On Hold
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 76%
CIP Funding Source(s): Utility Fund
Adopted Budget: $200,000
Future Planned Funding: $820,000 (Estimate)
Budget Adherence: On Target
Project Update: No major changes since last update.
AUGUST 2026 | 18CIP REPORT
This page intentionally left blank.
WATER
AUGUST 2026 | 20CIP REPORT
DOVE ELEVATED STORAGE TANK (EST) REPAINT
Department: Public Works
Engineering Firm: Bartlett & West
General Contractor: Not Awarded Yet
Budget Adherence: On Target
Project Update: City staff and the consultant continue advancing the rehabilitation design and project
manual for the Dove Elevated Storage Tank Repainting Project. The 90% design submittal has been
reviewed, and City comments have been provided to the consultant for incorporation into the final
design documents. Graphic branding concepts for the water tower will be presented to City Council
at the August 18 Work Session to obtain direction on the preferred design. Following incorporation of
Council’s direction, the project is anticipated to be advertised for construction bids in late August.
Project Description: Repaints the interior and exterior
of the Dove Elevated Storage Tank, replaces structural
steel and yard piping components as needed, and
updates the tank’s exterior graphics to extend the life
and appearance of this critical water system asset.
CIP Project Number: 2022-39
Project Status: In Progress
Project Phase: Design
Overall Progress (Current Phase): 85%
CIP Funding Source(s): Utility Fund
Adopted Budget: $490,000
Future Planned Funding: $0
ALTA VISTA WATER LINE REPLACEMENT - PLANNING
Department: Public Works
Engineering Firm: Not Awarded Yet
General Contractor: Not Awarded Yet
Adopted Budget: $3,600,000
Future Planned Funding: $37,000,000
Budget Adherence: On Target
Project Update: The City is coordinating with the City of Keller to advance the Alta Vista Water Line
Replacement Project. An updated draft Interlocal Agreement has been shared with the City of Keller for
review and prepared for legal review, and preliminary project phasing, funding responsibilities, and next
steps for design are being coordinated.
Project Description: Completes design, easement
acquisition, and coordination for the rehabilitation of
the Alta Vista 30-inch and 36-inch water transmission
main through sliplining, along with a condition
assessment of the Alta Vista Pump Station to support
the long-term reliability of one of the City’s primary
water supply lines.
CIP Project Number: 2023-05
Project Status: Not Started
Project Phase: Inactive
Overall Progress (Current Phase): 0%
CIP Funding Source(s): Utility Fund, City of Keller
AUGUST 2026 | 21CIP REPORT
SOUTHLAKE PARK WATERLINE IMPROVEMENTS (PHASE 3)
Department: Public Works
Engineering Firm: Not Awarded Yet
General Contractor: Not Awarded Yet
Project Update: During July, the City submitted a funding application to the Texas Water Development
Board (TWDB) and continued project scoping with the design consultant. Staff anticipates awarding
the design contract this fall to begin engineering for the water main improvements that will enhance fire
protection and support future water service in the Southlake Park area.
Project Description: Constructs a new 8-inch water
main along Crescent Drive, Hillside Drive, and Southlake
Park Drive to provide adequate fire protection, enhance
water quality, and make service available if requested.
CIP Project Number: 2026-03
Project Status: In Progress
Project Phase: Pre-Design
Overall Progress (Current Phase): 0%
CIP Funding Source(s): Utility Fund
Adopted Budget: $4,125,000
Future Planned Funding: Pending Final Design
Budget Adherence: On Target
TW KING PUMP STATION #2 BUILDOUT PHASE 2
Department: Public Works
Engineering Firm: Not Awarded Yet
General Contractor: Not Awarded Yet
Fund
Adopted Budget: $1,990,000
Future Planned Funding: $24,460,000 (Estimate)
Budget Adherence: On Target
Project Update: This project is expected to begin this fall. Staff is coordinating with the design
consultant to prepare for project kick-off.
Project Description: Installs additional pumps and
related infrastructure improvements, including a
protective masonry enclosure, fencing, and drainage
enhancements, to increase water system capacity,
improve flow and pressure to the north and east
portions of the City, and enhance the safety, security,
and reliability of the City’s water infrastructure.
CIP Project Number: 2023-06
Project Status: Not Started
Project Phase: Pre-Design
Overall Progress (Current Phase): 0%
CIP Funding Source(s): Utility Fund, Water Impact Fee
AUGUST 2026 | 22CIP REPORT
TW KING PUMP STATION #2 BUILDOUT PHASE I
Department: Public Works
Engineering Firm: Freese and Nichols
General Contractor: Not Awarded Yet
Budget Adherence: On Target
Project Update: Regulatory approval by TCEQ was received for this project in July as well as a bid
opening held July 24, 2026. Nine contractors proposed prices for this project and both staff and our
design consultant are currently evaluating the bids received and verifying references. Staff intends to
select the proposal that will be the best value to the City and award a construction contract for this
project at the September 15th council meeting.
Project Description: Upgrades the pump station with
a generator, replaces the existing pumps and motors
and adds a new pump and motor to the Low Pressure
Plane.
CIP Project Number: 2022-96c
Project Status: In Progress
Project Phase: Bidding/Pre-Con
Overall Progress (Current Phase): 100%
CIP Funding Source(s): Utility Fund, Water Impact Fee
Fund
Adopted Budget: $15,475,000
Future Planned Funding: $0 (Estimate)
UPSIZE EXISTING 6-INCH TO 12-INCH WATER LINE ALONG EAST HIGHLAND FROM
BLYTHE LANE TO NORTH KIMBALL AVENUE
Department: Public Works
Engineering Firm: TNP
General Contractor: Not Awarded Yet
Budget Adherence: On Target
Project Update: Coordination with property owners for required easements is ongoing. Updated offers
were sent to three of the five property owners, and a meeting has been held with one; one property is
currently in probate, and one remains under legal review regarding prescriptive right-of-way. TNP has
been in ongoing negotiations and has facilitated required paperwork for one agreement so far. Easement
coordination is expected to continue in the coming months. Depending on negotiation outcomes,
alternative alignments may be considered as the project advances toward anticipated construction in
summer 2027.
Project Description: Replaces the existing 6-inch water
line with a 12-inch line to improve service and capacity.
This project is a companion project to the East
Highland/Kimball 8-inch Sewer Line.
CIP Project Number: 2022-28c
Project Status: In Progress
Project Phase: ROW/ Easement Acquisition
Overall Progress (Current Phase): 65%
CIP Funding Source(s): Utility Fund, Water Impact Fee
Fund
Adopted Budget: $825,000
Future Planned Funding: $2,475,000 (Estimate)