Item 4BITEM 4B
Award construction contract for intersection improvements located at South White Chapel Boulevard and Continental Boulevard to Quality Excavation, LTD. in the amount of $516,054.21 and
authorize construction phase contingencies
S. White Chapel Blvd./Continental Blvd. Intersection Improvements
S. White Chapel Blvd./Continental Blvd. Intersection Improvements
Bid opening April 21, 2009
Four bids received
Quality Excavation, Ltd. submitted
low bid
Design engineer recommends award to Quality Excavation, Ltd.
Total Bid $516,054.21
Construction Phase Contingency 51,945.79
Project Budget $568,000.00
Roadway Impact Fee CIP $ 430,841.03
General Fund CIP Budget 137,158.97
Project Budget $568,000.00
S. White Chapel Blvd./Continental Blvd. Intersection Improvements
Recommendation
Award construction contract for Intersection Improvements located at South White Chapel Boulevard and Continental Boulevard to Quality Excavation, LTD. in the amount of $516,054.21 and
authorize construction phase contingencies
Questions?