Item 4M - Memo CITY OF Item 4M
SOUTHLAKE
MEMORANDUM
June 16, 2026
To: Alison Ortowski, City Manager
From: Pritam Deshmukh, Director of Public Works
Subject: Approve an agreement with Westwood Professional Services,
Inc. for evaluation of the creek corridor, engineering design,
and related professional services associated with
infrastructure-related stabilization upgrades for the Jones
Branch Sewer Protection Improvements Project in an amount
not to exceed $700,000.
Action
Requested: Approve an agreement with Westwood Professional Services, Inc.
for evaluation of the creek corridor, engineering design, and related
professional services associated with infrastructure-related
stabilization upgrades for the Jones Branch Sewer Protection
Improvements Project in an amount not to exceed $700,000.
Background
Information: The purpose of this item is to seek City Council approval of an
agreement with Westwood Professional Services, Inc. (formerly
Peloton Land Solutions) for engineering design, creek corridor
evaluation, and related professional services associated with
infrastructure-related stabilization improvements for the Jones
Branch Sewer Protection Improvements Project in an amount not to
exceed $700,000.This agreement includes engineering, surveying,
geotechnical, environmental coordination, hydraulic analysis,
easement support, and design services associated with protecting
existing sanitary sewer infrastructure located along Jones Branch
Creek.
Following City Council direction to proceed with the Infrastructure
Related Stabilization option, additional engineering services are
required to update technical analyses, verify existing conditions,
complete environmental and permitting coordination, prepare
easement documents, and develop final construction plans,
specifications, and cost estimates. While prior technical work has
already been completed related to this project, the existing
engineering analyses and supporting data will need to be reviewed
and updated, as necessary, to support final design. Certain elements
Page 1 of 6
Item 4M
of the prior work may remain usable, while others may require
refinement based on current site conditions, survey information,
permitting requirements, and design assumptions.
The scope of services includes the following components:
Core Design Services
These services are necessary to advance the Infrastructure Related
Stabilization option from conceptual evaluation to a construction-
ready project. These services include project management, field
investigations, hydraulic analysis, geotechnical investigations,
surveying, environmental coordination, easement support,
engineering design, and bidding/construction phase support.
The proposed scope of work will provide the engineering, technical,
and regulatory support necessary to advance the project through
final design and prepare it for construction. Key deliverables include:
• Perform updated topographic surveying, utility investigations,
geotechnical, and hydraulic modeling to verify existing site
conditions and evaluate risks to sanitary sewer infrastructure;
• Complete the engineering design of the selected stabilization
improvements, including streambank stabilization measures,
sanitary sewer protection elements, grading, drainage,
erosion control, and associated infrastructure improvements;
• Prepare easement exhibits, legal descriptions, and supporting
documentation necessary for property acquisition and access
requirements;
• Coordinate environmental reviews, permitting activities, and
regulatory approvals with agencies including the U.S. Army
Corps of Engineers and other applicable authorities;
• Develop final construction plans, technical specifications,
engineer's cost estimates, and bid documents suitable for
public bidding and construction; and
• Provide bidding assistance, respond to contractor questions,
review submittals, and support construction administration
activities during project implementation.
Supporting Corridor Evaluation
In addition to the services required to complete design of the selected
stabilization improvements, the agreement includes an evaluation of
the Jones Branch corridor in areas where City infrastructure is
located or may be affected by ongoing erosion. This work includes a
geomorphologic assessment, aerial LiDAR mapping, erosion and
improvement study, field investigations, and updated hydraulic and
drainage analyses.
Page 2 of 6
Item 4M
The purpose of this effort is to develop a more comprehensive
understanding of creek behavior, erosion patterns, and sewer
infrastructure vulnerability. The evaluation will identify and prioritize
erosion hot spots, assess potential risks to existing public
infrastructure, and provide information that can support future capital
planning and proactive infrastructure protection efforts.
Key outcomes and deliverables of this effort include:
• Completion of geomorphologic, hydraulic, drainage, and
erosion-related technical analyses to better understand creek
behavior, channel migration, and erosion patterns affecting
City infrastructure;
• Identification and prioritization of erosion hot spots and
infrastructure vulnerabilities throughout the Jones Branch
corridor;
• Evaluation of potential infrastructure-related erosion risks that
may require future mitigation or monitoring; and
• Development of technical data, engineering
recommendations, and supporting analyses to inform future
capital planning and proactive infrastructure protection
strategies.
Collectively, these services will allow the City to update prior
engineering evaluations, refine erosion conditions within the Jones
Branch corridor, and advance engineering design for prioritized
stabilization improvements intended to protect vulnerable sanitary
sewer infrastructure. The proposed agreement also provides
additional corridor information that may support drainage planning
and regional coordination efforts.
Project Schedule
Design activities, including corridor assessment, field verification,
technical analyses, permitting coordination, and preparation of
construction documents are anticipated to take approximately ten
months following the notice-to-proceed. If approved, work is
expected to begin in summer 2026, with conceptual and preliminary
design activities occurring through late 2026 and final design
anticipated in late spring 2027.
Following completion of final design and receipt of applicable
permits, staff anticipates returning to City Council with a construction
contract for consideration as early as Summer 2027.
Environmental coordination and permitting activities may occur
concurrently with design; however, review timelines associated with
the U.S. Army Corps of Engineers and other regulatory agencies are
Page 3 of 6
Item 4M
outside the control of the City and consultant and may affect the
ultimate construction schedule.
Project History
The Jones Branch project originated from concerns regarding
ongoing erosion impacts to sanitary sewer infrastructure located
within and adjacent to the creek corridor. While concerns regarding
erosion within Jones Branch date back many years, City staff began
actively evaluating conditions in 2020 after concerns were raised
regarding erosion around sanitary sewer manholes and creek
crossings. Subsequent field inspections identified locations where
erosion had reduced soil cover over sanitary sewer infrastructure
and created potential risks to the long-term integrity of the City's
wastewater system.
As part of a broader citywide effort to identify and address erosion-
related risks to critical wastewater infrastructure, the City initiated
engineering evaluations in 2021 to assess sanitary sewer facilities
located within creek corridors. Following completion of the initial
study, City Council allocated funding within the FY 2022 Capital
Improvement Program for sanitary sewer erosion protection projects.
Engineering services were subsequently authorized to further
evaluate conditions along Jones Branch and develop potential
infrastructure protection alternatives.
Engineering investigations completed between 2022 and 2023
included surveying, hydraulic analysis, geotechnical investigations,
environmental review, and a feasibility study evaluating multiple
alternatives to protect the sanitary sewer system. Alternatives
considered included streambank stabilization, sanitary sewer
relocation concepts, lift station alternatives, and other infrastructure
protection measures. During these evaluations, additional erosion
concerns and infrastructure vulnerabilities were identified within the
corridor, resulting in a broader understanding of conditions affecting
the sanitary sewer system.
Throughout the evaluation process, staff coordinated with affected
property owners, conducted field investigations requiring access to
private property, held multiple neighborhood meetings, and gathered
resident feedback regarding the alternatives under consideration. As
the project evolved, both the engineering evaluation and public
outreach efforts expanded to address additional infrastructure
concerns, property considerations, and stakeholder input.
Following completion of the feasibility evaluation and resident
outreach process, staff presented the conceptual alternatives and
community feedback to City Council. Based on the technical
Page 4 of 6
Item 4M
evaluation, stakeholder input, and discussion with Council, direction
was provided to advance the Infrastructure Related Stabilization
option, which focuses on protecting existing sanitary sewer
infrastructure through targeted stabilization improvements.
Financial
Considerations: Funding for this agreement is budgeted in the Capital Improvements
Program via the Stormwater Utility System Fund and the Utility Fund.
The proposed agreement totals $700,000 and includes both the Core
Design Services necessary to advance the Infrastructure Related
Stabilization option selected by City Council and the Supporting
Corridor Evaluation effort described above. Approximately $550,000
is associated with the Core Design Services required to complete
design of the stabilization improvements. Approximately $150,000 is
associated with the Supporting Corridor Evaluation effort, which will
provide additional analysis of erosion patterns, infrastructure
vulnerability, and future infrastructure protection needs within the
Jones Branch corridor.
The proposed agreement is considered a continuation of previously
authorized engineering services with Peloton Land Solutions, which
was subsequently acquired by Westwood Professional Services, Inc.
Because the project team, technical analysis, feasibility evaluations,
survey, geotechnical work, and preliminary design efforts have
already been completed under prior agreements, utilizing Westwood
allows the City to maintain continuity of project knowledge, leverage
prior technical work, and avoid duplication of engineering effort and
cost.
Based on the current conceptual design and preliminary cost
estimates, the Infrastructure Related Stabilization option is estimated
at approximately $3.12 million, including contingency. Combined
with the proposed engineering services agreement, the current
planning-level project cost is approximately $3.88 million.
As the project advances through engineering design, cost estimates
will continue to be refined based on updated field information,
permitting requirements, easement needs, design development,
market conditions, and construction assumptions.
Strategic Link: This item links to the City's Strategy Map strategic focus area of
Infrastructure. It specifically relates to the City's Corporate Objective,
F2: Invest to Provide & Maintain High Quality Public Assets.
Page 5 of 6
Item 4M
Citizen Input/
Board Review: During the evaluation of alternatives, staff conducted meetings with
affected property owners, gathered written feedback from residents,
and presented conceptual options to City Council. Following
consideration of the technical analysis and resident input, City
Council provided direction to advance the Infrastructure Related
Stabilization option. The proposed agreement is intended to
complete the engineering and supporting analyses necessary to
implement that direction.
Legal
Review: The proposed agreement is based on a standard agreement that
the City Attorney has reviewed and approved.
Alternatives: City Council may approve the proposed Engineering Services
Agreement as presented, including both the Core Design Services
necessary to advance the Infrastructure Related Stabilization option
and the Supporting Corridor Evaluation effort.
Alternatively, City Council may direct staff to modify the scope of
services by reducing or deferring portions of the Supporting Corridor
Evaluation effort while retaining the Core Design Services necessary
to complete engineering design of the stabilization improvements.
City Council may also deny the agreement and provide alternative
direction to staff.
Supporting
Documents: Attachment A: Engineering Services Agreement
Staff
Recommendation: Approve an agreement with Westwood Professional Services, Inc.
for evaluation of the creek corridor, engineering design, and related
professional services associated with infrastructure-related
stabilization upgrades for the Jones Branch Sewer Protection Project
in an amount not to exceed $700,000.
Staff
Contact: Pritam Deshmukh, Director of Public Works
Jeff Ginn, P.E.,CFM, City Engineer
Josue A. Hernandez, P.E., Civil Engineer
Page 6 of 6